Discusses Inservice Testing Program for Installation of Flow Measuring Instrumentation for Svc Water Pumps,Per NRC 870116 SER Denying Util Pump Relief Request 7.After Installation, Util Will Have Capability of Measuring Flow from Each Pump
ML20234E981
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/29/1987
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Wagner D
NRC, NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CON-NRC-87-134 VPNPD-87-547, NUDOCS 8801110280
Download: ML20234E981 (2)


Text

-

s O

Wisconsin Electnc eom come 231 W. MICHIGAN,P.O. BOX 2046, MILWAUKEE Wl53201 (414)277-2345 VPNPD 547.

NRC 134 December 29, 1987 U.

S.

NUCLEAR REGULATORY COMMISSION Document Control Desk Washington, D.C.

20555 Attention:

Mr. Dave Wagner, Project Manager Gentlemen:

DOCKETS 50-266 AND 50-301 INSERVICE TESTING PROGRAM FOR PUMPS AND VALVES PUMP FLOW RATE MEASUREMENT FOR THE SERVICE WATER PUMPS PUMP RELIEF REQUEST NUMBER 7 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 l

Your letter dated January 16, 1987 transmitted a draft Safety Evaluation Report (SER) for the Point Beach Nuclear Plant l

Inservice Testing Program for Pumps and Valves.

Item 6 under l

Section 3.0 of the SER denied our Pump Relief Request No. 7~for relief from measuring service' water flow in accordance with Section XI requirements.

In our letter dated April 2, 1987, we committed to conducting an engineering review into the feasibility of installing flow measuring instrumentation for the service water pumps, and advising you of the results of the review by January 15, 1988.

We propose to install connections to the service water system north and south headers to. accommodate averaging pitot tube I

measurement of the pump flow rates.

The design will permit L

insertion and removal of the pitot tube ~during operation.

The l

instrument will only be inserted during the testing to minimize any potential for inaccuracies due to clogging of the tube by suspended solids.

The connections will be located in the horizontal straight run of piping downstream of where each header enters the control building.

This is the first available section of piping on the pump discharge where turbulence is reduced sufficiently to permit the use of flow measuring instrumentation.

For the. south 8801110200 871229 I

h PDR ADOCK 05000266 L

P PDR fy c

q f

4m

i

^

t NRC Document Control Desk December 29, 1987 Page 2 i

'i l

header, the connection will be located in the south diesel I

generator room.

Installation of the south header connection is I

planned for the upcoming Olit 1 outage in April 1988.

For the

)

north header, the connection will be located in the air compressor room and will be installed during the Unit 2 outage scheduled for fall 1988.

I l

After the instrumentation is installed, we will have the capability of measuring flow from each of the service water pumps.

If you have any questions, please contact us.