Amend 43 to License NPF-29,changing Tech Spec to Reflect Changes to Divisional Power Supplies & Associated Primary Containment Penetration Conductor Overcurrent Protective Devices for Two Isolation Valves in RWCU Sys
ML20234D798
Person / Time
Site: Grand Gulf 
Issue date: 01/04/1988
From: Adensam E
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20234D802 List:
References
NUDOCS 8801070210
Download: ML20234D798 (9)


Text

!(f jo,,

UNITED STATES NUCLEAR REGULATORY COMMISSION n

h WASHINGTON, D C. 20555

%,.,.../

MISSISSIPPI POWER & LIGHT COMPANY SYSTEM ENERGY RESOURCES, INC.

SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION DOCKET NO. 50-416 GRAND GULF NUCLEAR STATION, UNIT 1 AMENDMENT TO FACILITY OPERATING LICENSE i

Amendment'No. 43 License No. NPF-29 1.

The Nuclear Regulatory Commission (the Commission) has found that A.

The application for amendment by System Energy Resources, Inc.

(the licensee), dated November 25, 1987, complies with.the standards and *.irements of'the Atomic Energy Act of 1954, as amended (the Act), und the Commission's rules and regulations. set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the' health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 l

of the Commission's regulations and all applicable requirements have been satisfied.

P

2.

Accordingly, the license is amended by changes to the Technical Specifications, as indicated in the attachment to this license amendment; and paragraph 2.C.(2) of Facility Operating License No. NPF-29 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 43, are hereby incorporated into this license.

System Energy Resources, Inc. shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3.

This license amendment is effective as of its date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION Origiaal'Siped Dy Elinor G. Adensam Elinor G. Adensam, Director Project Directorate 11-1 Division of Reactor Projects-1/II

Attachment:

Changes to the Technical Specifications Date of Issuance:

January 4,1988 f

N r,

^

PAnd4ts;chhR LA: PL1 PM:PD21:DRPR OGC-B C

ST BC: EMEB: DEST D:PD2 :DRPR LKinEter h.:

[L.MarshLA9/7 I V/30/1'

]

EAdensa

+/4/K]

n/) /

/ /

/

jf3 3g 3

ATTACHMENT TO LICENSE AMENDMENT NO. 43 FACILITY OPERATING LICENSE N0. NPF-29 DOCKET N0. 50-416 Replace the following pages of the Appendix A Technical Specifications with the enclosed pages.

The revised ~ areas are indicated by marginal lines.

The corresponding overleaf page(s) have been provided to maintain document completeness.

Remove Insert 3/4 6-33 3/4 6-33 (overleaf) 3/4 6-34 3/4 6-34 3/4 8-27 3/4 8-27 (overleaf) 3/4 8-28 3/4 8-28 3/4 8-35 3/4 8-35 3/4 8-36 3/4 8-36 (overleaf) i

i 9

TABLE 3.6.4-1 (Continued)

CONTAINMENT AND DRYWEL' ISOLATION VALVES MAXIMUM SYSTEM AND PENETRATION ISOLATION TIME VALVE NUMBER NUMBER VALVE GROUP (,)

(Seconds)

Containment (Continued)

Comb. Gas Control E61-F009-(A) 65(0) 7 4

f.ont. Purge (Outside Air Supply)

Comb. Gas Control E61-F010-(B) 65(I) 7 4

Cont. Purge (Outside Air i

Supply)

Purge Filter Train E61-F056-(B)

~66(I) 7

'4 Isolation Purge Filter Train E61-F057-(A) 66(0) 7 4

Isolation RHR "B" Test Line E12-F024B-B 67(0)(d) 5 90 To Suppr. Pool RHR "B" Test Line E12-F011B-B 67(0)(d) 5 36-To Suppr. Pool Refueling Water P11-F130-(A) 69(0)(c) 6A 8

Transf. Pump Suction Retueling Water P11-F131-(B) 69(0)(C) 6A 8

Transf. Pump Suction Instr. Air to ADS P53-F003-A 70(0) 6A 4

3 RCIC Turbine Exh.

E51-F078-B 75(0)'

9 10 l

Vacuum Breaker RWCU to Feedwater G33-F040-B 83(I)

B 35.

l RWCU to Feedwater G33-F039-A 83(0) 8 35 Chemical Waste P45-F098-(B) 84(I) 6A 8

Sump Discharge Chemical Waste P45-F099-(A) 84(0)~

6A 8

Sump Discharge Supp. Pool Clean-P60-F009-A 85(0) 6A 8

up Return Supp. Pool Clean-P60-F010-B 4 85(0) 6A 8

l up Return I

1 Demin. Water P21-F017-A 86(0) 6A 19 i

Supply to Cont.

1 Demin. Water P21-F018-B 86(I) 6A IF Supply to Cont.

{

RWCU Pump Suction G33-F001-B 87(I) 8 35 J

[

GRAND GULF-UNIT 1 3/4 6-33

TABLE 3.5.4-1 (Continued)

CONTAINMENT AND DRYWELL ISOLATION VALVES MAXIMUM SYSTEM AND PENETRATION ISOLATION TIME VALVE NUMBER NUMBER VALVE GROUP (a)

(Seconds)

Containment (Continued)

RWCU Pump Suction G33-F252-B 87(I) 8 35 l

RWCU Pump Suction G33-F004-A 87(0) 8 35 RWCU Pump Disch.

G33-F053-B 88(I) 8 35 RWCU Pump Disch.

G33-F054-A 88(0) 8 35 b.

Drywell Instrument Air P53-F007-B 335(0) 6A 7

Drywell Chilled P72-F125-A 331(I) 6A 32 Water Return Drywell Chilled P72-F126-B 331(0) 6A 32 Water Return Drywell Chilled P72-F124-B 332(0) 6A 32 Water Return RWCU Pump Suction G33-F250-A 337(I) 8 35 RWCU Pump Suction G33-F251-B 337(0) 8 35 Combustible Gas E61-F003B-B 338(0) 5 84 Con.

Combustible Gas E61-F003A-A 339(0) 5 84 Con.

Combustible Gas E61-F005A-A 340(0) 5 84 Con.

Combustible Gas E61-F005B-B 340(0) 5 84 Con.

Combustible Gas E61-F007-(A) 341(0) 5 9

Con.

Combustible Gas E61-F020-(B) 341(0) 5 18 Con.

Drywell Air Purge M41-F015-(A) 345(I) 7 4

Supply Drywell Air Purge M41-F013-(B) 345(0) 7 4

Supply l

Drywell Air Purge M41-F016-(A) 347(I) 7 4

Exhaust Drywell Air Purge M41-F017-(B) 347(0) 7 4

Exhaust Equipment Drains P45-F009-(A) 348(I) 6A 6

Equipment Drains P45-F010-(B) 348(0) 6A 6

Floor Drains P45-F003-(A) 349(I) 6A 6

Floor Drains P45-F004-(B) 349(0)

GA 6

Service Air PS2-F195-B 363(0) 6A 16 Chemical Sump P45-F096-A 364(I) 6A 9

Disch.

Chemical Sump P4E-F097-B 364(0) 6A 9

Disch.

RWCU to Heat G33-F253-A 366(0) 8 35 l

Exch.

Reactor Water B33-F019-8 465(I) 10 36 Sample Line Rea-tor Water B33-F020-A 465(0) 10 36 Sample Line GRAND GULF-UNIT 1 3/4 6-34 Amendment No. 43 1

TABLE 3.8.4.1-1 (Continued)

PRIMARY CONTAINMENT PENETRATION CONDUCTOR OVERCURRENT PROTECTIVE DEVICES l

c.

480 VAC Circuit Breakers (Continued)

Molded Case, Type NZM i

TRIP

RESPONSE

BREAKER SETPOINT TIME SYSTEM / COMPONENT NUMBER (Amperes)

(Seconds)

AFFECTED i

52-1412-01 17.5 0.100 REAC RECIRC HPU OIL PUMP FAN (N18330003B3-N) 52-1412-02 60 0.100 CNTMT CHEM WASTE SUMP PUMP (N1P45CO27B-N) 52-1412-03 60 0.100 DRYWELL FLOOR DRAIN SUMP PUMP (N1P45C001A-N) 52-1412-05 12.5 0.100 MOV CRD C00LWTR PRESS CONTROL (NIC11F003-N) i 52-1412-08 105 0.100 MOV REAC RECIRC PUMP B SUCTION (Q1833F023B-N) 52-1412-09 175 0.100 RWCU DEMIN PREC0AT PUMP (N1G36C002-N) 52-1412-12 90 0.100 RWCU DEMIN HOLDING PUMP (NIG36C0018-N) 52-1412-15 600 0.100 REAC RECIRC HPU OIL PUMP (N1B33D003B1-N) 52-1412-17 320 0.100 CNTMT EQUIP DRAIN SUMP PUMP (N1P45C004A-N) 52-1412-20 800 0.100 480 V RECEPTAqLE 52-1412-23 600 0.100 REAC RECIRC HPU OIL PUMP (N18330003B2-N)

GRAND GULF-UNIT 1 3/4 8-27

F TABLE 3. 8. 4.1- ] (Cor,tinued)

PRIMARY CONTAINMENT DENITRATION CONDUCTOR OVERCURRENTPR00fl[f'VEDEVICES c.

480 VAC Circuit Breakers (Continued)

Molded Case, Type NZM TRIP P.F.5P0NSE BREAKER SETPOINT TIME SYSTEM / COMPONENT NUMBER (Amperes)

(Seconds)

AFFECTED 52-1412-25 17.5 0.100 REAC RECIRC HPU OIL PUMP FAN (N1B330003B4-N) 52-1412-26 38 0.100 MOV REACTOR VESSEL HEAD VENT (Q1821F001-N) 52-1412-28 38 0.100 M0V PEACTOR VESSEL HEAD VENT (Q1B21F005-N) 52-1412-32 800 0.100 CNTMT CLR FAN COIL UNIT FAN (N1M41B001A-N) 52-1412-33 105 0.100 MOV - REAC RECIRC PUMP A DISCHARGE (Q1B33F067B-N) 52-1412-35 500 0.100 CRD REMOVAL HOIST (N1M31E003-N) 52-1412-39 1200 0.100 DRYWELL VALVE H0IST (Q1M31E002-N) 52-1412-41 32 0.100 CNTMT AIRLOCK AIR SHOWER FAN (N1M410005-N) 52-1511-07 50 0.100 MOV - RWCU INL INB ISOL VLV (Q1G33F250-A) 52-1511-24 50 0.100 MOV - RWCU INL OUT ISOL VLV (Q1G33F253-A) 52-1511-44 12.5 0.100 MOV - DRYWELL CLG WATER.ISOL (Q1P42F116-A)

GRAND GULF-UNIT 1 3/4 8-28 Amendment No. 43

TABLE 3.8.4.1-1 (Continued)

PRIMARY CONTAINMENT PENETRATION CONDUCTOR OVERCURRENT PROTECTIVE DEVICES c.

480 VAC Circuit Breakers (Continued)

Molded Case, Type NZM TRIP

RESPONSE

BREAKER SETPOINT TIME SYSTEM / COMPONENT NUMBER (Amperes)

(Seconds)

AFFECTED 52-1631-41 8

0.100 MOV - REACTOR WATER SAMPLE (Q1833F019-B) 52-1631-47 50 0.100 MOV - INST AIR DRWL OUTBD ISOL (Q1P53F007-B) 52-1631-50 32 0.100 MOV - RWCU OUTLET TO MAIN CONDENSER (Q1G33F028-B) 52-1631-51 32 0.100 MOV RWCU SYS ISOLATIN VALVE (Q1G33F053-B) 52-1631-52 50 0.100 MOV - RWCU SYS ISOLATION (Q1G33F040-B) 52-1631-53 50 0.100 MOV - RWCU SYS ISOLATION (Q1G33F001-B) 52-1641-06 32 0.100 MOV - MAKE UP WATER CNTMT ISOL (Q1P21F018-B) 52-1641-07 50 0.100 MOV - RWCU INL OUT ISOL VLV (Q1G33F251-B) l 52-1641-08 50 0.100 MOV - RWCU OUT INB ISOL VLV (Q1G33F252-B) 52-1641-16 7

0.100 MOV INSTRUMENT LINE INBOARD 150 (01023Fb91-B)

GRAND GULF-UNIT 1 3/4 8-35 Amendment No. 43

TABLE 3.8.4.1-1.(Continued)

PRIMARY CONTAINMENT PENETRATION CONDUCTOR ~

OVERCURRENT PROTECTIVE DEVICES l

c.

480 VAC Circuit Breakers (Continued)

Molded Case, Type.NZM TRIP

RESPONSE

BREAKER SETPOINT TIME SYSTEM / COMPONENT NUMBER (Amperes)

(Seconds)

AFFECTED 52-1641-18 7

0,100

-MOV - INSTRUMENT LINE INBOARD 150' (Q1D23F593-B) 52-1641-24 7

0.100 CONTAINt4ENT ISOL VALVE (Q1B33F126-B) 52-1641-26 32 0.100 MOV - DRYWELL CHEM WASTE ISOL (Q1P45F097-B) 52-1641-35 10 0.100 MOV - SUPPR POOL.

MAKE UP VALVE (Q1E30F0018-B) 51-1641-36 10 0.100 MOV - SUPPR POOL MAKE UP VALVE' (Q1E30F002B-B) 52-1642-05 320 0.100 DRYWELL COOLER FAN COIL UNIT (N1M51B001B-8) 52-1642-06' 320 0.100 DRYWELL COOLER FAN COIL UNIT (N1M51B0028-B) 52-1642-07 320 0.100 DRYWELL COOLER FAN C0ll UNIT (N1M51B003B-B) 52-1642-08 320 0.100 DRYWELL COOLER FAN COIL UNIT (N1M51B004B-B) 52-1642-09 320

-0.100 DRYWELL COOLER FAN COIL' UNIT' (N1M51B005B-B)

GRAND GULF-UNIT 1 3/4 8-36'