ML20234B489

From kanterella
Jump to navigation Jump to search
Forwards Dcrdr Final Rept Dtd Nov 1987,consisting of Engineering Rept on 130 Human Engineering Discrepancies Not Previously Corrected at Submittal of 861223 Summary of Dcrdr Program.Mods May Change During Program Implementation
ML20234B489
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 12/30/1987
From: Gucwa L
GEORGIA POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML20234B492 List:
References
SL-3760C, NUDOCS 8801050578
Download: ML20234B489 (2)


Text

_ . _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _

Georgia Power Company 333 P.edmont Avenue Atlanta, Georgia 30308 Tetephone 404 526-6526 l Mamr.g Admess Post Off.ce Box 4545 Acanta Georg.a 30302 Georgia Power L T. Gucws " '

Manager Nuclear Safety and Licens>rg SL-3760c 1854C X7GJ10-H000 j December 30, 1987 U. S. Nuclea, Regulatory Commission ATTN: Document Control Desk j Hashington, D. C. 20555 '

l l

PLANT HATCH - UNITS 1, 2 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 DETAILED CONTROL ROOM DESIGN REVIEW SUBMITTAL OF ENGINEERING REPORT Gentlemen:

By letter dated December 23, 1986, Georgia Power Company (GPC) submitted a Summary Report on its Detailed Control Room Design Review (DCRDR) Program. The report described the methodology and approach, as well as a discussion of each of the 760 Human Engineering Discrepancies (HEDs) which had been identified. Approximately 630 of the HEDs were to be corrected with surface enhancements, required no corrective action, or had already been corrected at the time of our December 23, 1986 submittal. In the submittal we committed to supply an engineering report on the remaining 130 HEDs, some of which require hardware modifications.

l This report is provided in Enclosure 1.

Implementation of surface enhancements (which will resolve almost 300 of the 630 HEDs mentioned above) is proceeding on schedule. The  ;

corrective actions for Unit 1 HEDs will be completed by November 30, l 1988, or Cycle 12 start-up (whichever is later). Unit 2 corrective actions relative to these HEDs will be completed by April 30, 1989 or Cycle 9 start-up (whichever is later). Unit 1 is currently operating in Cycle 11 and Unit 2 is scheduled to shutdown from Cycle 7 on January 13, 1988. Thus, when the surface enhancements are complete, approximately 630 HEDs will have been addressed.

Georgia Power Company plans to use panel overlays, similar to those existing, on the main consoles, rather than applying the surface enhancements directly on the panels. For reasons of coordination and focus, we prefer to finish these surface enhancements prior to doing systematic panel by panel instrument relocations. As you know, care Ok $[o$$$,y .

PDR \ .

d Georgia Power b U. S. Nuclear Regulatory Commission December 30, 1987 Page Two needs to be taken when performing control room modifications to avoid

" negative transfer" into a new panel arrangements. Flexibility in the program is important, particularly since control room modifications often can be performed only during scheduled outages. Therefore, GPC may change or modify the recommendations contained in the enclosed engineering report as the implementation phase progresses. In such a case we will notify the NRC.

If you have any questions in this regard, please contact this office at any time.

Sincerely,

  1. Ws L. T. Gucwa GKH/lc

Enclosure:

DCRDR Final Report c: Georaia Power Comoany Mr. J. P. O'Reilly, Sr. Vice President - Nuclear Operations (w/o)

Mr. J. T. Beckham, Jr., Vice President - Plant Hatch (w/o)

GO-NORMS U. S. Nuclear Reaulatory Commission. Washington. D. C.

Mr. L. P. Crocker, Licensing Project Manager - Hatch U. S. Nuclear Regulatorv Commission. Reaion II Dr. J. N. Grace, Regional Administrator Mr. P. Holmes-Ray, Senior Resident Inspector - Hatch l

1854C 700775