ML20233A921

From kanterella
Jump to navigation Jump to search
AN1-2020-04 Draft Operating Test Comments
ML20233A921
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 06/05/2020
From: Greg Werner
Operations Branch IV
To:
Entergy Operations
References
ES-301-7
Download: ML20233A921 (23)


Text

ES-301 Operating Test Review Worksheet Form ES-301-7 Facility: ANO1 Op Test Date: June 1, 2020 1 2 3 4 5 6 Attributes Job Content ADMIN Topic and LOD Admin JPMs U/E/S Explanation K/A (1-5) I/C Critical Scope Perf. Job Cues Overlap Key Minutia Focus Steps (N/B) Std. Link General comments:

1. Admin JPMs that have a KEY should be included for each admin JPM and correctly marked as KEY for A4, as an example.
2. Header labels are all A1.

Each JPM should have its unique header label at the top (such as A1, A2, A3, A4, S1, S2, P1, etc).

3. Some task standards need improvement. See specifics below.
4. Should have a history of use field for each JPM and a unique name for each JPM.

This helps with overlap, search criteria, etc.

5. Alternate path field is missing on attributes cover sheet. It might be better to have the cover sheet with initial conditions, initiating cue then on second sheet have the attributes and include Alt path field there.

You should compare your form to other sites in industry.

6. You should put the applicable procedure step (1108.03 step 4e as an example) in the JPM step so it is clear which step is being discussed in the write-up for comments/failures and also for clear Rev. 11

ES-301 Operating Test Review Worksheet Form ES-301-7 communications during validation week and draft submittals.

1. Title at top is A1
2. No key, screen shots of program, Table or Figure B6 E

not in JPM key.

3. JPM key, when submitted, will complete the JPM Calculate submittal.

Boron to 4. Title of JPM should match A1 maintain S/D 2 title of JPM on outline Margin 5. Cant tell how you got your (2.1.43) error bands. Key will fix this.

6. Task standard answer should be 631 + 14 ppm.

All comments resolved after S

validation week. Validation comments included as an addendum to this file.

1. Title at Top is A2 E 2. Need to send original JPM that was modified to create this JPM-explained the original JPM in office prior to val week.

Calculate time 3. Step 3 error bars are to boil / Core incorrect. It should be A2 uncover 3 Estimation 29.9 + 0.46 (2.1.25) 4. Title of JPM should match title of JPM on outline

5. Step 4.2 low answer is incorrect. It should be 268.8 not 268.6.

S All comments resolved after validation week.

1. Title at top is A3 E
2. Step 4 error bars should be 97.5 + 0.5 psid Perform SW Step 5 answer is A3 Surveillance 3 10 psid + 0.5 psid (2.2.12) 3. The marked-up figures for key should have x y axis values written on graph, S

such as 4522 gpm for pump Rev. 11

ES-301 Operating Test Review Worksheet Form ES-301-7 curve, with line drawn up to value, then over or across to 87.5 psid.

All comments resolved after validation week.

1. Title at top is A4 E 2. Task standard should have that max stay time is based on RWP limit not individual Ability to comply dose remaining for this JPM A4 with RWP 3 (2.3.7) (to be clear from JPMs where the opposite is true).

S All comments resolved after validation week.

1. Title at top is A5 E 2. No key
3. Not SRO only because after review you have to make some recommendation, do some TS call, or something at the SRO level to make the JPM for the SRO level license. Just needed to add Assess risk for the second step on the cue unplanned sheet and in JPM standard A5 (SRO) 3 Maintenance to compete SRO portion.

(2.1.39) 4. Title should be Review Boron calculationfor errors and refuse the package or something like that because it is incorrect.

5. Table or Figure B6 not in JPM.

S All comments resolved after validation week.

U 1. Title at top is A6

2. Not SRO only because after review you have to make Review TTB some recommendation, do A6 (SRO) calculation 3 some TS call, find and and(2.1.25) report errors to SM, or something to make the JPM at the SRO license level.

Rev. 11

ES-301 Operating Test Review Worksheet Form ES-301-7 Licensee will modify for hatch closure within 30 minutes (an SRO only function)

S All comments resolved after validation week.

Determine 1. Title at top is A7 E

operability of A7 (SRO) 3 SW Pump All comments resolved after S

( 2.2.37) validation week.

1. Title at top is A8 E 2. Dont cue to answer on Ability to answer sheet-use assess comply with A8 (SRO) 3 WCO determination and RWP Conclusions

( 2.3.7)

S All comments resolved after validation week.

1. Title at top is A9 Classify an E 2. No key provided for EPIP A9 (SRO) Event 2 form.

(2.4.41) S All comments resolved after validation week.

1 2 5

3a 3b 3c 3d 3e 3f 3h 4a 4b 6 Simulator/In-Plant Safety Function JPMs and K/A LOD Job U/E/S (1-5) I/C Cues Critical Scope Overlap Perf. Key Minutia Link Explanation General 1. JPM standards should have a clear comments for line item for where/when in the all JPMS JPM the alternate path starts.

S1 1 (004 A4.07) 3 E 1. Needs a title at top for S1 Rev. 11

ES-301 Operating Test Review Worksheet Form ES-301-7

1. Not alt path as written-the U applicant starts on cue to verify reactor building sump not blocked and it is (need to back up the JPM a few steps and/or change the initiating cue to fix S2 2 (006 A2.02) 3 this).
2. Cant start the JPM at the alt path
3. Cueing (see above)
4. Wrong title at top for S2 S All comments resolved after validation week.
1. Wrong title at top for S3 E 2. Put an Alt path band after step 7.3 in the JPM standard to identify S3 3 (010 A2.03) 2 where alt path begins.

S All comments resolved after validation week.

1. Wrong title at top for S4 E 2. Task standard need to have the text added with power from S4 4S (E04 EA1.1) 3 London Line.

S All comments resolved after validation week.

1. Wrong title at top for S5 E 2. Step 8.2.3 not critical since not an S5 5 (028 A4.01)) 3 action step.

All comments resolved after validation S

week.

1. Wrong title at top for S6 E 2. Step 7.9.6 is critical for the JPM.

S6 6 (064 A2.05) 3 All comments resolved after validation S

week.

1. Wrong title at top for S7 E 2. This JPM needs clarity for each of the four switches that are S7 7 (E02 EA1.1) 1 manipulated in the JPM standard.

S All comments resolved after validation week.

1. Wrong title at top for S8 E 2. Wanted this to be alt path due to high radiation alarm, get isolation that fails to occur and applicant has to manually perform the alignment.

S8 9 (071 A1.06) 2 Licensee made it alt path because flow is too high and must stop the release. No auto isolation on rad at this plant.

S All comments resolved after validation week.

E 1. No title at top for P1 P1 4S (041 A4.01) 3

2. Task standard is incomplete-needs Rev. 11

ES-301 Operating Test Review Worksheet Form ES-301-7 to have withdraw supply monitor, then close breakers S1 and S2, then reinsert supply monitor 2 7 2.

3. Might be good to have a picture of this.

S All comments resolved after validation week.

1. No title at top for P2 E 2. Task standard incomplete for alt path-need to have that when halon fails to actuate, then pull pin on P2 8 (086 A4.06) 3 pilot valve and pull down handle on reserve pilot cylinder to actuate halon.

S All comments resolved after validation week.

1. No title at top for P3 E

P3 3 (006 A4.05) 3 All comments resolved after validation S

week.

Rev. 11

ES-301 7 Form ES-301-7 Instructions for Completing This Table:

Check or mark any item(s) requiring a comment and explain the issue in the space provided using the guide below.

1. Check each JPM for appropriate administrative topic requirements (COO, EC, Rad, and EP) or safety function requirements and corresponding K/A. Mark in column 1.

(ES-301, D.3 and D.4)

2. Determine the level of difficulty (LOD) using an established 1-5 rating scale. Levels 1 and 5 represent an inappropriate (low or high) discriminatory level for the license that is being tested. Mark in column 2 (Appendix D, C.1.f)
3. In column 3, Attributes, check the appropriate box when an attribute is not met:

The initial conditions and/or initiating cue is clear to ensure the operator understands the task and how to begin. (Appendix C, B.4)

The JPM contains appropriate cues that clearly indicate when they should be provided to the examinee. Cues are objective and not leading. (Appendix C, D.1)

All critical steps (elements) are properly identified.

The scope of the task is not too narrow (N) or too broad (B).

Excessive overlap does not occur with other parts of the operating test or written examination. (ES-301, D.1.a, and ES-301, D.2.a)

The task performance standard clearly describes the expected outcome (i.e., end state). Each performance step identifies a standard for successful completion of the step.

A valid marked up key was provided (e.g., graph interpretation, initialed steps for handouts).

4. For column 4, Job Content, check the appropriate box if the job content flaw does not meet the following elements:

Topics are linked to the job content (e.g., not a disguised task, task required in real job).

The JPM has meaningful performance requirements that will provide a legitimate basis for evaluating the applicant's understanding and ability to safely operate the plant. (ES-301, D.2.c)

5. Based on the reviewers judgment, is the JPM as written (U)nacceptable (requiring repair or replacement), in need of (E)nhancement, or (S)atisfactory? Mark the answer in column 5.
6. In column 6, provide a brief description of any (U)nacceptable or (E)nhancement rating from column 5.

Save initial review comments and detail subsequent comment resolution so that each exam-bound JPM is marked by a (S)atisfactory resolution on this form.

Rev. 11

ES-301 8 Form ES-301-7 Facility: ANO1 General comments on scenarios Op Test Date: June 1, 2020 1 2 3 4 5 6 7 8 9 10 Required Verifiable Scen.

Event Realism/Cred. LOD TS CTs U/E/S Explanation Actions actions Overlap General Comments for all scenarios

1. ANO used to have a CT table, a procedures used list, and more clarity in the scenario guides.
2. You should bold only things like CTs and TSs so they have emphasis.

There are way too many items bolded in the guides.

3. Every TS call needs to have the LCO letter with it in D-1 and summary pages and for D-2 it needs the actual LCO condition in the guide.

Furthermore, for RPS instrument TS calls, you have to have information in the guide down to the function level because that is what we grade on for these types of TS calls (such as function 6 for Hi RCS pressure).

4. Every switch that is touched must be in the D-2 guide. The right column in the D-2 guide is the applicant actions, which are the switches that are to be manipulated. This means that you cant just cut and paste from a procedure into the D-2 and submit that as the scenario guide.

For example, scenario 1, event 1, you have a note for the examiner that the applicant will start two items for the loss of bus event. All the other items, I dont know if that means the applicant may or may not start those items or they are already running and not necessary or what. You have to be specific in the guide of what is manipulated with its standard (ie you start the C-5B vacuum pumpthis is not a note but a gradable action).

5. Critical tasks have a number and if they dont then assign one so it is clear (CT-1 is the first one in the scenario, CT-2, or if you have a specific CT number from your owners group list, use that number, such as CT-19). That number is applied each time the CT is referenced in the D-1 or D-2.
6. If you dont use a CT table you must still put all the attributes for the CT at the front of the guide and then have the CT and its associated expected actions in the D-2 body of the guide (this is all the switches necessary to complete the task, the time if time critical, the bounding Rev. 11

ES-301 9 Form ES-301-7 conditions, and MOST of these should be based on parameters not procedure exits).

7. Each line item in the guide must have an assigned position and the expected actions column to the right. You cant cut and paste items such as page 9 of scenario 1 where you have the ATC, NA, BOP, and SRO in one large field and the entire step out of the procedure in the right field next to it. If the ATC performs step 7, for example, then the ATC is the position field then all the items to the right are for the ATC.

Only the SRO directs procedure transitions and makes TS calls so this left to right format for the SRO applies in a similar fashion.

8. Alarms for each event should be placed at the top of the event just under the event title with bullets and detailed windows and panels.

These are not examiner notes as you have described in scenario 1 event 2 page 7.

9. For parameters to record for grading purposes, we will need to work thru the required parameters to capture for scenarios for grading during validation week.

Rev. 11

ES-301 10 Form ES-301-7 Facility: ANO1 Scenario: 1 Op Test Date: June 1, 2020 1 2 3 4 5 6 7 8 9 10 Required Verifiable Scen.

Event Realism/Cred. LOD TS CTs U/E/S Explanation Actions actions Overlap Add CT-23 for event 5 and CT-1 for event 8 on D-1 first page.

Note: All comments from validation week added as addendum to this file.

Dont need .N/A in scenario guide. (page 6 at bottom of page).

E Bulletize major alarms that occur for this event at the top for each event.

Cant tell if need to start air compressors or not, what about EHC pumps? This type of event is more dynamic is something fails or is tagged out at the beginning (this may be the case but I cant tell from the guide as submitted). For example, if one of the EHC pumps is out of 1 2 service and then the standby fails to start, this could lead to low EHC pressure and cause secondary transients like the steam dump valves or turbine valves to oscillate or failthis displays control of the plant and provides more attributes for grading an applicants ability to operate the plant. Hard to grade LOD of the event without all the information.

S All comments resolved after validation week.

E Bulletize major alarms that occur for this event at the top. Need TS LCO 2? and condition on page 7.

2 S All comments resolved after validation week.

Major alarms need to be at top of event. Same story as above, page 9 is U

bad. Need to split steps by position (see general comment above on SRO/ATC/NLO/NA). Where is the TS LCO and statement? Where is 3? the procedure step to secure the RCP once power is down? This is not an examiner note.

S 3 All comments resolved after validation week.

There is no event 4 in the D-2 right now. Event numbering is off from E

here to the end of this guide.

2?

S 4 All comments resolved after validation week.

E Examiner note for CT not necessary for event 6 as labeled at top of this 3 event. Bullets for alarms to start the event 5

Rev. 11

ES-301 11 Form ES-301-7 S All comments resolved after validation week.

6 3 S U CTs need basis in D-2, time, parameters as necessary.

7 2 S All comments resolved after validation week.

Numbering is off on the events. These are supposed to be ready to give E

when submitted.

8 3 S

All comments resolved after validation week.

9 Rev. 11

ES-301 12 Form ES-301-7 Facility: ANO1 Scenario: 2 Op Test Date: June 1, 2020 1 2 3 4 5 6 7 8 9 10 Required Verifiable Scen.

Event Realism/Cred. LOD TS CTs U/E/S Explanation Actions actions Overlap E Discussed remainder of scenario changes during in office review prior to validation week.

S All comments resolved after validation week.

1 2

3 4

5 6

7 8

9 Rev. 11

ES-301 13 Form ES-301-7 Facility: ANO1 Scenario: 3 Op Test Date: June 1, 2020 1 2 3 4 5 6 7 8 9 10 Required Verifiable Scen.

Event Realism/Cred. LOD TS CTs U/E/S Explanation Actions actions Overlap Discussed remainder of scenario changes during in office review prior to E

validation week.

S All comments resolved after validation week.

1 2

3 4

5 6

7 8

Rev. 11

ES-301 14 Form ES-301-7 Facility: ANO1 Scenario: 4 Op Test Date: June 1, 2020 1 2 3 4 5 6 7 8 9 10 Required Verifiable Scen.

Event Realism/Cred. LOD TS CTs U/E/S Explanation Actions actions Overlap E Discussed remainder of scenario changes during in office review prior to validation week.

S All comments resolved after validation week.

1 2

3 4

5 6

7 8

CT-16 bounded with faulted SG words. Need to clarify this for the E

guide because there is not a faulted SG (ie busted steam or feed line) in the scenario. A valve has failed and that is what should be included in the CT.

S 9 All comments resolved after validation week.

E No CT-8 in the D-2 guide.

10 S All comments resolved after validation week.

Rev. 11

ES-301 15 Form ES-301-7 Instructions for Completing This Table:

1 Use this table for each scenario for evaluation.

2 Check this box if the events are not related (e.g., seismic event followed by a pipe rupture) OR if the events do not obey the laws of physics and thermodynamics.

3, 4 In columns 3 and 4, check the box if there is no verifiable or required action, as applicable. Examples of required actions are as follows: (ES-301, D.5f)

  • opening, closing, and throttling valves
  • starting and stopping equipment
  • raising and lowering level, flow, and pressure
  • making decisions and giving directions
  • acknowledging or verifying key alarms and automatic actions (Uncomplicated events that require no operator action beyond this should not be included on the operating test unless they are necessary to set the stage for subsequent events. (Appendix D, B.3).)

5 Check this box if the level of difficulty is not appropriate.

6 Check this box if the event has a TS.

7 Check this box if the event has a critical task (CT). If the same CT covers more than one event, check the event where the CT started only.

8 Check this box if the event overlaps with another event on any of the last two NRC examinations. (Appendix D, C.1.f) 9 Based on the reviewers judgment, is the event as written (U)nacceptable (requiring repair or replacement), in need of (E)nhancement, or (S)atisfactory? Mark the answer in column 9.

10 Record any explanations of the events here.

In the shaded boxes, sum the number of check marks in each column.

  • In column 1, sum the number of events.
  • In columns 2-4, record the total number of check marks for each column.
  • In column 5, based on the reviewer's judgement, place a checkmark only if the scenario's LOD is not appropriate.
  • In column 6, TS are required to be 2 for each scenario. (ES-301, D.5.d)
  • In column 7, preidentified CTs should be 2 for each scenario. (Appendix D; ES-301, D.5.d; ES-301-4)
  • In column 8, record the number of events not used on the two previous NRC initial licensing exams. A scenario is considered unsatisfactory if there is < 2 new events. (ES-301, D.5.b; Appendix D, C.1.f)
  • In column 9, record whether the scenario as written (U)nacceptable, in need of (E)nhancement, or (S)atisfactory from column 11 of the simulator scenario table.

Rev. 11

ES-301 16 Form ES-301-7 Facility: ANO1 Op Test Date: June 1, 2020 1 2 3 4 5 6 7 8 11 Scenario  % Unsat. Explanation Event Events TS TS CT CT Scenario U/E/S Totals Unsat. Total Unsat. Total Unsat.

Elements Discussed remainder of scenario changes during in office review prior to validation U

1 8 0 2 2 2 1 3 week.

S All comments resolved after validation week.

Discussed remainder of scenario changes during in office review prior to validation E

2 8 0 2 0 2 1 1 week.

S All comments resolved after validation week.

Discussed remainder of scenario changes during in office review prior to validation E

3 8 0 2 0 3 0 0 week.

S All comments resolved after validation week.

Discussed remainder of scenario changes during in office review prior to validation E

4 10 0 2 1 2 0 0 week.

S All comments resolved after validation week.

Instructions for Completing This Table:

Check or mark any item(s) requiring comment and explain the issue in the space provided.

1, 3, 5 For each simulator scenario, enter the total number of events (column 1), TS entries/actions (column 3), and CTs (column 5).

This number should match the respective scenario from the event-based scenario tables (the sum from columns 1, 6, and 7, respectively).

2, 4, 6 For each simulator scenario, evaluate each event, TS, and CT as (S)atisfactory, (E)nhance, or (U)nsatisfactory based on the following criteria:

a. Events. Each event is described on a Form ES-D-2, including all switch manipulations, pertinent alarms, and verifiable actions. Event actions are balanced between at-the-controls and balance-of-plant applicants during the scenario. All event-related attributes on Form ES-301-4 are met. Enter the total number of unsatisfactory events in column 2.
b. TS. A scenario includes at least two TS entries/actions across at least two different events. TS entries and actions are detailed on Form ES-D-2. Enter the total number of unsatisfactory TS entries/actions in column 4. (ES-301, D.5d)
c. CT. Check that a scenario includes at least two preidentified CTs. This criterion is a target quantitative attribute, not an absolute minimum requirement. Check that each CT is explicitly bounded on Form ES-D-2 with measurable performance standards (see Appendix D). Enter the total number of unsatisfactory CTs in column 6.

Rev. 11

ES-301 17 Form ES-301-7 2+4+6 7 In column 7, calculate the percentage of unsatisfactory scenario elements: 100%

1+3+5 8 If the value in column 7 is > 20%, mark the scenario as (U)nsatisfactory in column 8. If column 7 is 20%, annotate with (E)nhancement or (S)atisfactory.

9 In column 9, explain each unsatisfactory event, TS, and CT. Editorial comments can also be added here.

Save initial review comments and detail subsequent comment resolution so that each exam-bound scenario is marked by a (S)atisfactory resolution on this form.

Rev. 11

ES-301 18 Form ES-301-7 Rev. 11

ES-301 19 Form ES-301-7 Site name: ANO 1 Op Test Date: June 1, 2020 OPERATING TEST TOTALS Total Total Total  %

Total Explanation Unsat. Edits Sat. Unsat.

Admin.

9 1 8 0 JPMs Sim./In-Plant 10 1 9 0 JPMs Scenarios 4 1 0 0 Licensee came in office after draft submittal to work through comments and correct Op. Test 13%

23 3 20 0 deficiencies prior to validation Comments from Totals:

validation are uploaded as an addendum to this form.

Instructions for Completing This Table:

Update data for this table from quality reviews and totals in the previous tables and then calculate the percentage of total items that are unsatisfactory and give an explanation in the space provided.

1. Enter the total number of items submitted for the operating test in the Total column. For example, if nine administrative JPMs were submitted, enter 9 in the Total items column for administrative JPMs.

For scenarios, enter the total number of simulator scenarios.

Enter the total number of (U)nsatisfactory JPMs and scenarios from the two JPMs column 5 and 2.

simulator scenarios column 8 in the previous tables. Provide an explanation in the space provided.

Enter totals for (E)nhancements needed and (S)atisfactory JPMs and scenarios from the previous 3.

tables. This task is for tracking only.

4. Total each column and enter the amounts in the Op. Test Totals row.

Calculate the percentage of the operating test that is (U)nsatisfactory (Op. Test Total Unsat.)/(Op. Test 5.

Total) and place this value in the bolded % Unsat. cell.

Refer to ES-501, E.3.a, to rate the overall operating test as follows:

  • satisfactory, if the Op. Test Total % Unsat. is 20%
  • unsatisfactory, if Op. Test Total % Unsat. is > 20%

Update this table and the tables above with post-exam changes if the as-administered operating test 6.

required content changes, including the following:

  • The JPM performance standards were incorrect.
  • The administrative JPM tasks/keys were incorrect.
  • CTs were incorrect in the scenarios (not including postscenario critical tasks defined in Appendix D).
  • The EOP strategy was incorrect in a scenario(s).

Rev. 11

ES-301 20 Form ES-301-7

  • TS entries/actions were determined to be incorrect in a scenario(s).

Rev. 11

Operating test notes Licensee came to region 4 office February to work out operating test comments. An updated version (rev 2) was provided on the files that week.

The week of February 20th a revision 3 of the operating test files was sent and then again updated on February 24th.

The operating tests were validated March 2, 2020, and the final rev 5 version of the operating test was submitted April 1st.

Comments from validation include the items at the end of this package Due to Covid-19 the Operating test administration was delayed until the first week in June, 2020.

S1-E 8.11.1 is the critical step, not 8.11. Resolved Does the simulator model fluctuate No panel indication for amps. The amps as well as suction and dis simulator models voltage for A3 S2-S pressure for the pump for these and A4 buses but it remains conditions? steady. Resolved.

S3-S Seems like closing London line A1512 is normally closed. Then S4-E breaker step 1.2.2 is critical? Not remove London Line from task marked as C. standard. Resolved.

S5-S For step 5 of this JPM. Is it conduct Added guidance from OP-1015-of Ops that requires tripping the 043. Resolved.

S6-E Diesel Gen? e might need a note that states that what governs the securing of the EDG.

Does pressure keep going down in It takes 11 minutes for MSLI at this the setup for the JPM? If not, then starting pressure. Task standard the task standard stating that was updated accordingly.

S7-E before MSLI occurs is not needed. Resolved.

It might take forever anyway to get to 600#.

Wanted to see the bank JPM on a Dont have a bank JPM on this release with alarm RI-7460 or 7461 detector. SRO-U will do this one coming in and they must secure and two in-plants. Resolved.

from the release that way. Do you have that in your bank?

S8-E I would rather the SRO-U applicants perform this JPM than three in-plant. There is minimal value for an upgrade to do the in-plant JPMs. This affects the outline and the schedule.

Do we need a picture for inside the Yes. Provided and this comment is P1-E cabinet or can it be opened at Resolved.

power?

Done. Resolved.

This would be the one to NOT have the SRO-U perform and instead perform S8.

The task standard still needs to have the actions for the Main Pilot cylinder. These are actions that get them to the alt path.

P2-E Also need to mark those first two steps as critical because they have to try that first and they are action steps. If they go straight to the Reserve cylinder then they did not even try the main cylinder and that would also be incorrect.

Added Examiner notes for Alara P3-S purposes.

Addendum for validation comments Scenario 1 val week comments CT-23 needs added within 15 minutes to bound it properly Malfunction after EOP entry is 2 not 1 (in the table page 2)

Page 7 need examiner note that they may use AOP for condenser vacuum so insert it and its steps on the next page.

Insert various notes as marked up during prep week TS call incorrect for RCP seal cooler leak (Condition B not condition A for 3.4.13.)

Scenario 2 comments Add booth cue for event 2 after actuation that it was an I and C error. All bistables have been checked and all are clear - none are tripped.

Scenario 4 comments Misc comments provided to licensee (page and simple edit items).

Scenario 3 designated as spare and not used, therefore not uploaded to Adams.

Scenario 5 was originally the low power during outline submittal, it became scenario 4 with all the edits and it was ran on the applicants. Scenario 5 was removed from the exam as class size decreased over the span of the exam process (up to an including the audit exams).