August 21, 2020 Mr. William Ross Director Manufacturing Quality Systems EnerSys 2366 Bernville Rd.
Reading, PA 19605
SUBJECT:
VENDOR INSPECTION OF ENERSYS QUALITY ASSURANCE PROGRAM AND TITLE 10 OF THE CODE OF FEDERAL REGULATIONS PART 21 PROGRAM IMPLEMENTATION
Dear Mr. Ross:
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staffs plan to perform an inspection to review implementation of your quality assurance program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B and 10 CFR Part 21.
Specifically, the quality assurance program and Part 21 implementation, will be reviewed as they pertain to EnerSys design, fabrication, testing, and commercial-grade dedication of safety-related components to operating nuclear power plants. As discussed through e-mail on August 6, 2020, the NRC inspection team plans to commence its virtual inspection activities on Monday, September 14, 2020, and will conduct an inspection through Friday, September 18, 2020. Subsequent to the inspection, a report will be issued and transmitted to you via letter.
The lead inspector for this effort is Mr. Paul Prescott and you may contact him at (301) 415-3026 or via electronic mail at Paul.Prescott@nrc.gov.
This inspection activity has been assigned the following docket number: 99990352. Please reference this number on any correspondence relating to this inspection activity sent to the NRC.
Sincerely, Kerri A. Kavanagh, Chief /RA/
Quality Assurance and Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation Docket No.: 99990352
ML20233A633 via mail NRR-106 OFFICE NRR/DRO/IQVB* NRR/DRO/IQVB*
NAME PPrescott KKavanagh DATE 8/21/2020 8/20/2020