Informs That After Further Mgt Review of AP600 Fire Protection Design,Review Determined That Certain Aspects of Design May Not Meet Intent of Commission Policy Identified in Secy 93-087
ML20217Q637
Person / Time
Site: 05200003
Issue date: 04/08/1998
From: Roe J
NRC (Affiliation Not Assigned)
To: Liparulo N
WESTINGHOUSE ELECTRIC COMPANY, DIV OF CBS CORP.
References
SECY-93-087-C, SECY-93-87-C, NUDOCS 9804130055
Download: ML20217Q637 (3)


Text

Tjrtci IM

$m te

^

t UNITED STATES g

NUCLEAR REGULATORY COMMISSION

'M O

E WASHINGTON, D.C. 3000dMantN April 8, 1998 r2o Mr. Nicholas J. Liparulo, Manager Nuclear Safety and Regulatory Analysis Nuclear and Advanced Technology Division Westinghouse Electric Corporation

{

P.O. Box 355 i

Pittsburgh, PA 15230

SUBJECT:

FIRE PUMP INSTALLATION WITHIN THE TUR3lNE BUILDING

Dear Mr. Liparulo:

After further management review of the AP600 fire protection design, it has been determined that certain aspects of the design may not meet the intent of Commission policy identified in SECY-93-087, " Policy, Technical, and Licensing issues Pertaining to Evolutionary and Advanced

{

Light-Water Reactor (ALWR) Designs." SECY-93-087 states that passive piant designs be 4

reviewed using the newest industry standards endorsed by the Nuclear Regulatory Commission (NRC). Concems regarding this issue center on the location of the fire pumps in the turbine 1

building. Specifically, the fire pumps should be protected against possible interruption of service through damage caused by explosion and fire as specified by NFPA 20. Therefore, you are requested to reassess the fire pump location and layout to demonstrate how they provide an -

' lent level of facility fire safety comparable to that of pumps at operating plants and in the er-reantly certified evolutionary plant designs. In addition, you should address how the AP600 fire protection design addresses the latest fire protection standards endorsed by the NRC.

In performing your reassessment of the fire pumps, you should consider improving the overall AP600 fire protection design by adopting one of the following enhancements:

1. Meet the intent of past industry practice approved by the staff by moving at least one, and I

preferably both, of the fire pumps to a diverse location outside the turbine building.

2. Provide sprinkler protection in the turbine building in accordance with the recommended actions of NFPA 804 and modify the fire pump room fire wall barriers that interface with the l

turbine building and the boiler room by making them blank walls with no through-penetrations or door openings. In addition, confirm that the fire area established by the fire pump rooms is of 3-hour fire resistive construction as defined in BTP CMEB 9.5.1. Specifically, the BTP defines a fire barrier as those components of construction (walls, floors, and ceilings, and their supports) including beams, joists, columns, penetration seats or closures, fire doors, l

and fire dampers that are rated by approving laboratories in hours of resistance to fire and are used to prevent the spread of fire.

3; in addition to the current design, provide a third 100-percent fire pump in a location other than in the turbine building. The sources of water for this pump should be either the l

proposed fire water tanks, the CSW intake canal, or a separate 100-percent capacity storage tank.

i I

2 3 M1 l

[

h 3

' U.

Mr. Nicholas J. Liparuto Apri1 8, 1998

)

Your immediate attention to this issue is necessary in order that the sis" meet the AP600 final safety evaluation report and final design approval schedule dates. In this regard, the staffis available if necessary to meet with Westinghouse at its earliest convenience to discuss and resolve this issue. Please contact Dino Scaletti at (301) 415-1104 with ouestions regarding this request. This issue is idantified as Final Safety Evaluation Report Open item Number 280.38F.

Sincerely, original signed by:

Jack W. Roe, Acting Director Division of Reactor Program Management Office of Nuclear Reactor Regulation cc: See next page DISTRIBUTION:

Docket File PDST R/F SCollins/FMiraglia. 0-5 E7 PUBLIC BSheron,0-5 E7 JRoe DMatthews TQuay TMarsh,0-8 D1 GHolahan WHuffman JNWilson TKenyon DScaletti ACRS (11) 1 JSebrcsky GHolahan,0-8 E2 I

DOCUMENT NAME: A:\\FIREDPV.DCS To receive a copy of this document, indicate in the box: "C" = Copy without attachment /ege; sure "E" = Npy

' with attachment / enclosure "N" = No copy f

OFFICE PM:PDST:DRPM l BS:SPLS;Q$SA:

D:PDST:DRPM l D:lA ' # l NAME DCScaletti:sd TMars@

TRQuay W

@gidhan DATE 04/ /98

  1. ~

04/J./98 OVif /98

= b:

sas:

aan ase :

OFFICE (A)ADTp. t/

t D:N

/

l NAME BSherdrfV N SJCo U DATE 04/ 6 /98

- OC B/98 OFFICIAL RECORD COPY 4, a f

1 e-

. )

Mr. Nicholas J. Liparuto Docket No.52-003 W,stinghouse Electric Corporation AP600 cc.

B. A. McIntyre Mr. Russ Bell

,anced Plant Safety & Licensing Senior Project Manager, Programs Westinghouse Electric Corporation Nuclear Energy institute j

Energy Systems Business Unit 1776 i Street, NW P.O. Box 355 Suite 300 Pittsburgh, PA 15230 Washingtor., DC 20006-3706 l

Ms. Cindy L. Haag Ms. Lynn Connor Advanced Plant Safety & Licensing Doc-Search Associates

- Westinghouse Electric Corporation Post Office Box 34 Energy Systems Business Unit Cabin John, MD 20818

]

l Box 355 Pittsburgh, PA 15230 Dr. Craig D. Sawyer, Manager Advanced Reactor Programs Mr. Sterling Franks GE Nuclear Energy U.S. Depanment of Energy 175 Curtner Avenue, MC-754 l

NE-50 San Jose, CA 95125 19901 Germantown Road Germantown, MD 20874 Mr, Robert H. Buchholz l

GE Nuclear Energy Mr. Frank A. Ross 175 Curtner Avenue, MC-781 i

U.S. Department of Energy, NE-42 San Jose, CA 95125 Office of LWR Safety and Technology 19E01 Germantown Road Barton Z. Cowan, Esq.

Gennantown, MD 20874 Eckert Seamans Cherin & Mellott 600 Grant Street 42nd Floor i

Mr. Charles Thompson, Nuclear Engineer Pittsburgh, PA 15219 AP600 Certification l

NE-50 Mr. Ed Rodwell, Manager i

19901 Germantown Road PWR Design Certification Germantown, MD 20874 Electric Power Research institute 3412 Hillview Avenue Mr. Robert Maiers, P.E.

Palo Alto, CA 94303 Pennsylvania Department of

. Environmental Protection Bureau of Radiation Protection Rachel Carson State Office Building P.O. Box 8469 l

Harrisburg, PA 17105-8469 l

l

.I