October 14, 1999 l

Mr. Donald R. Metzler i

U.S. Department of Energy Grand Junction Office 2597 8 3/4 Road Grand Junction, CO 81503

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION ON THE U.S. DEPARTMENT OF ENERGY GROUND WATER COMPLIANCE ACTION PLAN FOR THE SALT LAKE CITY, UTAH, UMTRA SITE

Dear Mr. Metzler:

The enclosed request for additional information (RAl) is being issued as a result of the U.S.

Nuclear Regulatory Commission (NRC) staff's review of rnaterials provided by the U.S.

Department of Energy (DOE) by letters dated February 5,1999, and September 27,1999.

Based on the review of the documents, the staff has determined that additionalinformation is necessary to complete the review.

Details of the. cdditionalinformation requested are provided in the enclosure to this letter. Your response should be provided no later than November 5,1999. If you cannot meet this schedule, you snould notify me immediately at (301) 415-7238. If you have any questions regarding this request, please contact William von Till at (301) 415-6251.

Sincerely, l

Original Signed By i

I John J. Surmeier, Chief i

Uranium Recovery and Low-Level Waste Branch i

Division of Waste Management Office of Nuclear Material Safety -

and Safeguards

Enclosure:

RAI Specific Comments g h kh (yh cc: William Sinclair, Utah Department of Environmental Quality Docket Number: WM-41 l

glq DISTRIBUTION :

File Center NMSS r/f URLL rif PUBLIC

/

ACNW JHolonich MLayton DOCUMENT NAME: G:\\URLL\\rwv\\SLC-GWCAP-RAl.wpd

[)

x l

OFC URLL URLL URLt

/

URL NAME WvonTill:cc h HLefevb DGill JSbeler DATE 10/ / /99 10//2/99 1

/9 10/1Y/99 OFFICIAL RECOF(D COPY 180030 9910190070 991014 PDR WASTE WM-41 PDR L-

.p -

pm 4

UNITED STATES

, [4 j

NUCLEAR REGULATORY COMMISSION t

WASHINGTON, D.C. 20M1

%,* *,,*,o October 14, 1999 Mr. Donald R. Metzler U.S. Department of Energy Grand Junction Office 2597 8 3/4 Road Grand Junction, CO 81503

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION ON THE U.S. DEPARTMENT OF ENERGY GROUND WATER COMPLIANCE ACTION PLAN FOR THE SALT LAKE CITY, UTAH, UMTRA SITE

Dear Mr. Metzler:

The enclosed request for additioaalinformation (RAI) is being issued as a result of the U.S.

Nuclear Regulatory Commission (NRC) staff's review of materials provided by the U.S.

Department of Energy (DOE) by letters dated February 5,1999, and September 27,1999.

Based on the review of the documents, the staff has determined that additional information is necessary to complete the review.

Details of the additionalinformation requested are provided in the enclosure to this letter. Your response should be provided no later than November 5,1999. If you cannot meet this schedule, you should notify me immediately at (301) 415-7238. If you have any questions regarding this request, please contact William von Till at (301) 415 6251.

Sincerely, d

da &

John J. Surmeier, Chief Uranium Recovery and Low-Level Waste Branch Division of Waste Management Office of Nuclear Material Safety and Safeguards

Enclosure:

RAI Specific Comments cc: William Sinclair, Utah Department of EnvironmentalQuality

1 REQUEST FOR ADDITIONAL INFORMATION (RAI) i DEPARTMENT OF ENERGY GROUND WATER COMPLIANCE ACTION PLAN FOlt THE SALT LAKE CITY, UMTRA PROJECT SITE DOE is requested to submit, in writing to John J. Surmeier, Chief, Uranium Recovery and Low-Level Waste Branch, Division of Waste Management, Office of Nuclear Material Safety and

Safeguards, U.S. Nuclear Regulatory Commission, Washington D.C. 20555, by November 5,1999, j

the following information:

I 1)

Monitoring should be implemented annually for a minimum period of 5 years. At the end of the 5-year period, an evaluation should be made as to the need for future monitoring.

It should be stated that DOE should receive NRC approval prior to the termination of i

monitoring. MW-131 should be added to the monitoring network due to recent increases in constituent concentrations in this area and due to the future migration of constituents toward the highway infiltration drain at the southeast corner of the site. With the I

cessation of pumping from the Central Valley Water Reclamation Facility (CVWRP) dewatering, it is anticipated that the highway drain will influence site groundwater flovi more strongly. The addition of MW 131 will aid in the effect of this drain on groundwater flow and constituent concentrations.

1 2)-

Documentation that the Vitro water supply well has been plugged, based on state and local regulations, should be provided.

-3)

A' discussion of anticipated future on-site groundwater pumping / dewatering is needed.

Sump pumps on-site should also be identified and plotted on a map. Potential risk from these activities should be evaluated.

4)

An areal photograph cf iho site and a map showing major water supply wells in the vicinity should be pro 3.: %.

5)

. The Long Term Surveillance Plan should also be modified based on the GWCAP.