Text
., .
,
1
August 29,1997
Mr. W. T. Subalusky, Jr.
Site Vice President
LaSalle County Station
' Commonwealth Edison Company
2001 North 21st Road
Marseilles, IL 61341
t
Dear Mr. Subalusky:
SUBJECT:
NRC INSPECTION REPORT NO. 50 373/97007; 50 374/97007 AND
Dear Mr. Suba!usky:
This refers to the inspection conducted on May 10 through June 27,1997, at the LaSalle
f acility. The enclosed report presents the results of that inspection.
During this 7-week inspection period, your staff's performance on three occasions
demonstrated a non conservative approach to equipment operability. Specifically,
operations shif t management waited 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> to declare a residual heat removal pump
inoperable for the low pressure coolant injection mode and 24 houre for the shutdown
cooling mode, while pursuing the calibration accuracy of test instrumentation as the
possible cause of the pump's failure to meet surveillance test acceptance criteria, la
addition, operations shift management directed and operators conducted a radioactive
waste discharge without first resolving operability concerns with lake blowdown flow
Indication. Finally, post-maintenance testing to ensure operability following replacement of
all four air start motors on an emergency diesel generator did not reflect the possible effect
of the maintenance on emergency diesel generator start time.
- Based on the results of this inspection, the NRC determined that three violations of NRC
requirernents occurred. These violations are cited in the enclosed Notice of Violation
(Notice) and the circumstances surrounding them are described in detailin the subject
inspection report. Two of the violations are of concern because they involve the non-
conservative approach to equipment operability discussed above. The third violation
involves a f ailure to apply appropriate radiological markings to tygon tubing installed in the
Jplant and indicates that plant personnellack knowledge of radiological administrative
controls.
You are required to respond to this letter and should follow the instructions specified in the
enclosed Notice when preparing your response. The NRC will use your response, in part,
to determine whether further enforcement action is necessary to ensure compliance with
regulatory requirements.
9709250007 970829
ADOCK 05000373
0
-PDR
"
,
-_
_
-
,
W. T.- Subalusky, Jr.
2-
- In accordance with 10 CFR 2.790 of the NRC's " Rules of Practices," a copy of this letter,
its enclosures, and your response will be placed in the NRC Public Document Room (PDR),
Sincerely,
Orig, signed by Melvyn Leach
Melvyn N. Leach, Chief
Operator Licensing Branch
Division of Reactor Safety
- Docket Nos.: 50 373; 50-374
Enclosures:
1.-
2.
Inspection Report
50 373/97007; 50 374/97007
cc w/encls:
T. J. Maiman, Senior Vice President
Nuclear Operations Division
D. A. Sager, Vice President,
Generation Support
,
H. W. Keiser, Chief Nuclear
Operating Officer
F. Dacimo, Plant General Manager
P. Barnes, Regulatory Assurance
Supervisor
4
1. Johnson, Acting Nuclear
Regulatory Services Manager
Richard Hubbard
Nathan Schloss, Economist
Office of the Attorney General
State Liaison Officer
Chairman, Illinois Commerce
Commission
Document Control Desk-Licensing
DOCUMENT NAME: R:\\lNSPRPTS\\ POWERS \\LASA\\LAS97007.DRP
To ,ecewe e copy of ttwo document, traficate in the boa 'C' = Copy without attachnent/ enclosure "E' = Copy with attachmentlenclosu,e
- N* = No
copy
OHICL
Riu
]
Rh8
[
Riu
l
Ritt
l
Hill
l
NAMt
Hes/co
Oenoway
Stua,
ihn0
Leach
Daft
09! 49 7
09/ 19 7
09/ /97
09/ 19 7
09/ s97
OFFIC AL MECORD COPY
f
.- m.
.
..
i
.
.
.
--
-.+. -c-.
- - . -
%
.
.-
.
- . , .
.~.
. _ - - . ~ .
. _ ..
. . . ,
. _ . _
._.
_ .. _ . ._
.__
-
<
w
.-
W. T. Subalusky, Jr _
-3.
,
. t
- Distribution:
Docket File w/encls
DRP w/encls
PUBLIC IE-01 w/encle
Rlli PRR w/encls
,
OC/LFDCB w/encls
SRI LaSalle w/encls -
,
CAA1 w/encls (E mail);
A. B. Beach w/encls
Project Manager, NRR w/encls -
Deputy RA w/encls
RAC1 (E-Mail)
DRS (2) w/encls
Rlll Enf. Coordinator w/encls
DOCDESK (E-mail)
,
TSS w/encis-
.
$
4
. . ,
.,
.
.
,-
-
3---
-
r-
, - .
-