ML20217A989

From kanterella
Jump to navigation Jump to search
Discusses 970821 Nrc/Cns Engineering Focus Meeting & Provides Listed Actions Relative to Lessons Learned Re Operability Assessment Process & Test Till Pass Concerns Recently Raised.W/List of Commitments Encl
ML20217A989
Person / Time
Site: Cooper 
Issue date: 09/17/1997
From: Peckham M
NEBRASKA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLS970166, NUDOCS 9709230122
Download: ML20217A989 (3)


Text

.

P.O hox os B L NB SKA 6P321 s

Nebraska Public Power District

  • T e ith""

m========m= === ===n =ww w--

=

==

NLS970166 September 17,1997 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D C. 20555-0001 Gentlemen:

Subject:

Follow-up to NRC/CNS Engineering Focus Meeting of August 21,1997 Cooper Nuclear Station, NRC Docket 50-298, DPR-46 i found the focus meeting on Operability Assessments (OAs) and 50.59s, conducted on August 21,1997, to be of tremendous value. I gained a perspective of regulator concerns and issues not possible through the normal inspection process. I thought the meeting was well conducted by both sides of the table. The venue was conducive to open communication and audience panicipation. It was clear that the NRC and Cooper staff were very interested in improving Cooper performance.

The CNS staff has initiated the following actions relative to lessons learned concerning the operability assessment process and the " test till pass" concerns recently raised by your staff.

1. An immediate action was taken to enhance the procedure governing OA performance by more clearly articulating the requirements for documenting the safety significance of the condition being evaluated. This was completed July 31,1997, while the inspectors were still on site, in response to their concerns regarding the quality of OAs.
2. The number of active OAs was reduced from in excess of 90 to less than ten. This drastic reduction is due to the fact that previous criteria defining active (open) OAs was not clear.

Previously, an OA was still" active" if the Problem Identification Report (PIR) remained open.

Therefore, the criteria have been clearly defined, which revealed the fact that many of the conditions identified had been corrected or were not representative of actual degraded / nonconforming conditions, or were controlled by another program (e.g.,

10CFR50.65).

3. The concerns raised during t'ne meeting related to cumulative elTects have been addressed.

The smaller number of active OAs facilitates a more rigorous review of the aggregate efTects and integrated risks of active OAs and any compensatory actions. The periodic review by the Station Operations Review Committee (SORC) of the cumulative effects will cominue, and

\\

will also become a procedure.

/.\\oD- )

4.

EfTective immediately, OAs will be reviewed by SORC within two weeks ofinitiation. I expect that this will be a short term ir,itiative to provide a back end review and is designed to create learning opportunities for the organization while improving quality and enhancing plant safety.

9fo9230122970917 h,h h e R~'ADOCR 05000298

+

P PDR p

Wel b

A M

NLS970166 Scpterpher 17,1997

'Page 2 of 2

5. OA performance indicators will be established, based on SORC reviews, to measure and i

monitor efTectiveness in addition, input from Engineering and Operations will be utilized.

6.

A project to review and improve the process for OAs has been initiated by the assistant operations manager. INPO will be assistin;; CNS with this efTort anc will include industry bench marking, resulting in appropriate procedural guidance.

7. Currently CNS is ta' r3 actions to bound the " test till pass" issue by resiewing past surveillances to deteimine the extent of the condition in this area. This effort is being pursued by our issues Management Team. Identified problems will be aggressively pursued. In addition, management expectations continue to be reinforced and communicated to the CNS staff.

As we learn more through bench marking and our own experience, these actions will undoubtedly change to adapt to new lessons learned.

I encoutage you, to the extent that your schedule will allow, to continue to have these focus meetings at Cooper rather than the region. This provides us with the opportunity to expose a larger number of the site stalTto learning opportunities.

I look fonvard to our next meeting. Should you have any questions concerning this matter, please contact me.

l Sincerely, l

Mike Pec ham i

Plant Manager

/Ird cc:

Regional Administrator USNRC - Region IV Senior Project Manager USNRC - NRR Project Directorate IV-1 Senior Resident inspector USNRC NPG Distri% tion

(

ATTACHMENT 3 LIST OF NRC COMMITMENTS l

Correspondence No: NLS970166 The following table identifies those actions committed to by the District in this document. Any other actions discussed in the submittal represent intended or planned actions by the District.

They are described to the NRC for the NRC's information and are not regulatory commitments.

Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding this document or any associated regul atory commitments.

COMMITTED DATE COMMITMENT OR OUTAGE Develop a procedure for the review of cumulative effects N/A of OAs.

SORC review of OAs within 2 weeks of OA initiation.

This N/A is a short term initiative.

Develop performance indicators for OAs,

"^

"^

Review and improve the OA process.

Review past surveillances to determine the extent of the

" test till pass" issue and take corrective actions as N/A necessary for problems identified, f

[_

PROCEDURE NUMBER 0.42 l

REVISION NUMBER 5 l

PAGE 9 OF 13 l

__ _ _ _