{{#Wiki_filter:1 W d b March 13, 1998 MEMORANDUM TO: Richard L. Bangart, Director j Office of State Programs i FROM: Carl J. Paperiello, Director (ORIGINAL SIGNED BY) Office of Nuclear Material Safety and Safeguards

SUBJECT:

PROPOSED AGREEMENT WITH THE STATE OF OHIO in response to your memorandum of February 27,1998, NMSS expects to be able to meet the schedule you propose for review of the draft application, assuming that it proves to be reasonably complete and that there are no unforeseen questions requiring additional information and review. If NMSS priorities are changed so as to call the schedule into question, we will advise you. We note that the schedule does not include points of contact with the State or the considerable effort that will have to go into transferring documents. CONTACT: Paul F. Goldberg, NMSS/IMNS (301) 415-7842 QISTRfBUTION: NMSS9800075 NRC Central File Cb IMNS r/f i p)()ly NMSS r/f CPoland i PDR: YES X NO To receive a copy of this document, indicate in the box: "C"= Copy w/o att/ encl. "E" = Copy w/att/enct"N" = No copy DOC NAME: G:\\ohioosp 398

  • SEE PREVIOUS CONCURRENCE op,.

_/ananoeees.eese OFC OB* E MSB* DWM* OB* IMNS* NMSSe /) NAME PGoldberg/II SBaggett JGreeves FCombs DCool CPa riEllo DATE 3/09/98 3/09/98 3/09/98 3/09/98 3/10/98 3/ J & /98 OFFICIAL RECORD COPY IMNS/SEC . ~.- - q T- ,,.p p 7* JM ce3/10/98 ftj,? g LL-{ i""~~~'p ) 9803230480 980313 PDR STPRG ESGOH PDR f Jf

I .w. 4 MEMORANDUM TO: Richard L. Bangart, Director Office of State Programs FROM: Carl J. Paperiello, Director Office of Nuclear Material Safety and Safeguards

SUBJECT:

PROPOSED AGREEMENT WITH THE ST E OF OHIO in response to your memorandum of February 27,1998 MSS expects to be able to meet the schedule you propose for review of the draft app!' ation, assuming that it proves to be reasonably complete and that there are no unforeseen uestions requiring additional information and review. If NMSS priorities are ch ged so as to call the schedule into question, we will advise you. We note that the schedule oes not include points of contact with the State or the considerable effort that will have to into transferring documents. CONTACT: Paul F. Goldberg, N S/IMNS (301)415-7842 DISTRIBUTION: NMSS9 0075 NRC Central File 4 IMNS r/f NMSS r/f CPoland PDR: YES X O DOCUMEN NAME: G%hioosp.398 To receive copy of this document, indicate in the box: "C"= Cop lo att/enci "E" = Copy w/att/ encl."N" = No copy $10-@ b M 't /% - IM NMSS OF OB E MSB hME PGolk/ll SBafgett Jhs k htA h1' CPaperiello DATE 3/Cf /98 3/ 9 /98 3 h /98 N/ /98 3///)/98 3/ /98 OFFICIAL RECORD COPY \\ iMNS/SEC / /98 j i

r an TICKET DATE RECEIVED: 03/02/98 ORIGINAL DUE DT: 03/11/98 CONTROL NO: 9800075 DIVISION DATE: 03/09/98 DOC DT: 02/27/98 FROMt TIME: COMP DT: A //3/98 Richard Bangart Dir:ctor, OSP (Of I y) i TO: Paperiello ] I FOR SIGNATURE OF :

    • BLUE **

SECY NO: ASSIGNED TO: CONTACT: f% \\ (I_MNS Goldberg DWM DESC: ROUTING: PROPOSED AGREEMENT WITH STATE OF OHIO Paperiello Kane Linehan Poland l SPECIAL INSTRUCTIONS OR REMARKS: THIS TICKET IS BEING REISSUED AS IMNS (GOLDBERG) REQUESTED DWM'S INPUT ON 3/6/98. DWM - Please provide input to IMNS (Goldberg) b IMNS will consoldiate" inputand' y ~ 3/9/98, cob. p rovideY f inal'"'re spons e

  • for - Pa pe riello 's ~ s ignature by 3/11/98.

Final. response _ is,du,e to,,OSP, by. ~ a 3/13/98/ ( RECEIVED DATE: - 4/7[ A Y"Idh ASSH3NED TO: dMI iMNS DUE DATE: 3l n I 97

e March 13, 1998 MEMORANDUM TO: Richard L. Bangart, Director Office of State Programs FROM: Carl J. Paperiello, Director (ORIGINAL SIGNED BY) Office of Nuclear Material Safety and Safeguards

SUBJECT:

PROPOSED AGREEMENT WITH THE STATE OF OHIO in response to your memorandum of February 27,1998, NMSS expects to be able to meet the schedule you propose for review of the draft application, assuming that it proves to be reasonably complete and that there are no unforeseen questions requiring additional information and review, if NMSS priorities are changed so as to call the schedule into question, we will advise you. We note that the schedule does not include points of contact with the State or the considerable effort that will have to go into transferring documents. CONTACT: Paul F. Goldberg, NMSS/IMNS (301)415-7842 DISTRIBUTION: NMSS9800075 NRC Central File IMNS r/f NMSS r/f CPoland PDR: YES X NO To receive a copy of this document, indicate in the box: "C"a Copy w/o att/ encl. "E" = Copy w/att/ encl."N" = No copy DOC NAME: Gbhu>osp 398

  • SEE PREVIOUS CONCURRENCE oefenoecuormanow a s. so OFC OB*

E MSB* DWM* OB* IMNS* NMSS4 /2 CPaNriello NAME PGoldberg/II SBaggett JGreeves FCombs DCool DATE 3/09/98 3/09/98 3/09/98 3/09/98 3/10/98 3/ J 6 /98 OFFICIAL RECORD COPY IMNS/SEC ce3/10/98

un 4 UNITED STATES g-g j NUCLEAR REGULATORY COMMISSION a WASHINGTON, D.C. 205Sh'1001 February 27, 1998 MEMORANDUM TO: Carl J. Paperiello, Director Office of Nuclear Material Safety and Safeguards Karen D. Cyr, General Counsel Thomas T. Martin, Director Office for Analysis and Evaluation of Operational Data ~ A. Bill Beach, Regional Administrator, Region 111 i Office of State Programs ,'f. 41

  1. '"*hf FROM:

Richard L. Bangart, Director

SUBJECT:

PROPOSED AGREEMENT WITH THE STATE OF OHIO The State of Ohio has submitted a draft request to enter into an Agreement with the Commission under Section 274b of the Atomic Energy Act. The Office of State Programs (OSP) staff has evaluated the request (and supporting documentation) for completeness against the Commission Policy Statement entitled " Criteria for Guidance of States and NRC in Discontinuance of NRC Regulatory Authority and Assumption Thereof by States Through Agreement" (46 FR 7540; January 23,1981), as amended by statements published on July 16, 1981 (46 FR 36969), and on July 21,1983 (48 FR 33376). Based on that review, we have determined that the draft request is ready for technical review and comment by your offices. A copy of the draft request is being provided to your staff. Attached is a proposed schedule for processing the Agreement. In response to a request by the State of Ohio, we seek to complete the processing in time for the A ]reement to be signed b / current Govemor George Voinovich, whose term expires at the end of the year. This schedule was discussed during a meeting with your staff on February 12,1998. During that meeting, staff agreed that to reach the goal of a final Ohio Agreement by December 31,1998, essentially all major milestones must be completed on schedule. At this time, the schedule is theoretically i possible to meet, presuming that no major issue (s) will arise during the review, and that no i extemal event (s) will occur which demand priority attention of the staff, the Commission or the I State. We will closely monitor progress against the schedule and inform you of any changes. We request your office concurrence (e.g., e-mail to RLB2 or memorandum) on the milestones identMed for your office in the proposed schedule. If you are unable to concur with the schedule, we request the identification of revised dates by which you can commit to complete the review milestones. w- , ~(j'y 10 %L,i.< - i

  • c s
  • Y a

Multiple Addressees 2 FEB 2 7 ss Please note that one in-depth review of the Ohio request should be conducted by NRC offices other than OSP. That complete review should be of the draft request. Comments developed based on the review will be forwarded to Ohio for incorporation into the Governor's formal request to the Chairman. Subsequently, OSP staff plans to review all differences between the draft request and the Governor's formal request, including the State's responses to the NRC comments. Assuming no outstanding issue remains unresolved at that point, OSP will provide you an analysis of the changes and responses to the NRC comments reflected in the Govemor's formal submittal. This will be accompanied by a Commission paper requesting consent to publish the proposed Agreement for public comment. Your office will not be required to review the entire voluminous Ohio request a second time. After your staff agrees that your comments have been satisfactorily resolved, your concurrence on the paper to the Commission will indicate that you agree the Ohio program, if implemented as described, will be adequate to protect public health and safety and will be compatible with NRC's materials program. If you have any qt 'stions regarding the Ohio request 'or an Agreement or the proposed schedule for processing, please contact Mr. Dennis Sollenberger at 415-2819, or Mr. Richard I Blanton at 415-2322.

Attachment:

As stated

s v Ohio Agreement Application Processing Schedule Action Start Date End Date Actual Date o Draft request package received by NRC 01/26/98 01/26/98 Completeness review of draft package 01/26/98 02/06/98 02/06/98 (2 weeks) OSP, NMSS, OGC, AEOD, Rlli concur on schedule 02/12/98 OSP comments on completeness to Ohio 02/13/98 02/13/98 1 - verbal -wntten (confirmation) Ohio completes request package 02/17/98 02/27/98 02/25/98 (2 weeks) o Complete draft request received by NRC 03/02/98 02/25/98 NRC technical review of draft request 03/09/98 05,01/98 (8 weeks) OSP compiles technical review comments 05/04/98 05/22/98 (3 weeks) o NRC comments to Ohio 05/25/98 i Ohio prepares Govemor's Request package 05/25/98 06/19/98 OSP prepares Commission Paper / staff assessment (4 weeks) o-Govemor's Request package received by NRC 06/22/98 NRC review of changes to request package, and office 06/22/98 07/17/98 concurrence on Commission Paper / staff e:sessment (4 weeks) ' Paper with staff assessmentto Commission EDO > 07/20/98 - (2 weeks) Comm > 07/31/98 Commission consideration of the proposal to 08/03/98 08/28/98 publish the Agreement in the FR (4 weeks) o Commissiot approval of publication in FR 08/28/98 o indicates milestone

n. 2 Ohio Agreement Application Processing Schedule - cont. Action Start Date End Date Actual Date Publication of proposed Agreement in FR 09/07/98 09/28/98 (4 weeks) Public comment period 09/07/98 10/05/98 (30 days) Response to comments and preparation of final 10/05/98 10/16/98 Commission Paper (2 weeks) NRC office concurrence on final Commission Paper 10/16/98 10/30/98 w/ attachments (2 weeks) Final Paper w!th staff assessment to Commission EDO > 10/30/98 (2 weeks) Comm >11/13/98 i Commission consideration of Agreement 11/13/98 12/11/98 (4 weeks) o Commission approval of Agreement 12/11/08 Signing of Agreement Ceremony NLT 12/31/98 (requested by Ohio before Gov. leaves office) 01/30/98 o FR notice of effective Agreement (within 30 days after signing) 1}}