ML20216H466

From kanterella
Jump to navigation Jump to search

Refers to NRC Bulletin (NRCB)96-002, Movement of Heavy Loads Over Sf,Over Fuel in Reactor Core or Over Safety- Related Equipment, Issued on 960411.Finds Responses to Bulletin Acceptable & Closes TAC M95567 & TAC M95568
ML20216H466
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 04/16/1998
From: Dromerick A
NRC (Affiliation Not Assigned)
To: Cruse C
BALTIMORE GAS & ELECTRIC CO.
References
IEB-96-002, IEB-96-2, TAC-M95567, TAC-M95568, NUDOCS 9804210145
Download: ML20216H466 (5)


Text

. .

Co-3t7 anco O *t UNITED STATES

, s g NUCLEAR REGULATORY COMMISSION "o e WASHINGTON. D.C. 20565-0001 8 April 16, 1998 k . . . . . ,o Mr. Charles H. Cruse Vice President - Nuclear Energy Baltimore Gas and Electric Company Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 l

SUBJECT:

COMPLETION OF LICENSING ACTION FOR NRC BULLETIN 96-02, " MOVEMENT l OF HEAVY LOADS OVER SPENT FUEL, OVER FUEL IN THE REACTOR CORE, OR OVER SAFETY-RELATED EQUIPMENT," DATED APRIL 11,1996, FOR CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS.1 AND 2 (TAC NOS. M95567 AND M95568)

Dear Mr. Cruse:

On April 11,1996, the U.S. Nuclear Regulatory Comrnission (NRC) issued NRC Bulletin (NRCB) 96-02, " Movement of Heavy Loads Over Spent Fuel, Over Fuel in the Reactor Core, or Over Safety-Related Equipment," to all holders of operating licenses. The NRC issued NRCB 96-02' for three principal reasons:

1. Alert addressees to the importance of complying with existing regulatory guidelines associated with the control and handling of heavy loads at nuclear power plants,
2. Request that all addressees review their plans and capabilities for handling heavy loads in accordance with existing regulatory guidelines and within their licensing basis as previously analyzed in the final safety analysis report, and
3. Rsquire addressees to report to the NRC whether and to what extent they have complied j with the actions requested in this bulletin. 1 Also the bulletin requested that Baltimore Gas and Electric Company determine whether current activities were within the licensing basis and to submit a license amendment request as necessary, i in response to NRCB 96-02, you provided a letter dated May 13,1996, for Calvert Cliffs Nuclear Power Plant, Unit Nos.1 and 2. This submittal provided both the information requested and the responses required by NRCB 96-02. NRC staff review of the responses to NRCB 96-02 finds that, overall, the responses are acceptable; therefore, TAC Nos. M95567 and M95568 are closed.

9 s

.~

)

~ %3 NE CENTER Copy 9804210145 980416 PDR ADOCK 05000317 G PDR

o C. H. Crure The NRC staff will continue to review the issue of heavy loads through an ongoing Task Action Plan for heavy loads. Any additionalinformation required for the completion of the Task Action Plan will be obtained on a plant-specific basis.

If you have any questions regarding this matter, please contact me at (301) 415-3473.

Sincerely, Alexander W. Dromenck, Senior Projece Manager Project Directorate 1-1 Division of Reactor Projects - 1/II Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 cc: See next page I

1 I

l i

i April 16, 1998 C. H. Cruse The NRC staff will continue to review the issue of heavy loads through an ongoing Task Action Plan for heavy loads. Any additionalinformation required for she completion of the Task Action Plan will be obtained on a plant-specific basis.

If you have any questions regarding this matter, please contan me at (301) 415-3473.

Sincerely, Original Signed by:

Alexander W. Dromerick, Senior Projece Manager Project Directorate 1-1 Division of Reactor Projects - 1/Il Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 cc: See next page

+

l DISTRIBUTION: '

I . Docket File: P. Ray PUBLIC ACRS PDI-1 Reading File B. Thomas J. Zwolinski (A)

S.' Bajwa l A. Dromerick S. Little C. Hehl, Region i l

OGC DOCUMENT NAME: G:\CC1-2\9602CLO1.MEM To receive a copy of this document, indicate in the box: "C" = Copy without attachment / enclosure "E" = Copy with Ettichment/ enclosure "N" = No copy 0FFICE PM PQJ kj// ) lE LA:PDI-1.0Q_ l D:PDI-1 , , /) l l l j

?'AME ADMrickOfc SLittle' F $8ajwa M 'Ol DATE 04//t /98 04/ l(p/98 04/(fd/98 04/ /98 04/ /98 Official Record Copy

.m.m

J April 16, 1998 l

C. H. Cruse l The NRC staff will continue to review the issue of heavy loads through an ongoing Task Action i

Plan for heavy loads. Any additional information required for the completion of the Task Action Plan will be obtained on a plant-specific basis, if you have any questions regarding this matter, please contact me at (301) 415-3473.

Sincerely, Original Signed by:

Alexander W. Dromerick, Senior Projece Manager l Project Directorate 1-1 Division of Reactor Projects - 1/ll Office of Nuclear Reactor Regulation Docket Nos. 50-317

and 50-318 l

cc See next page ,

l DISTRIBUTION:

l Docket File P. Ray l PUBLIC ACRS l PDI-1 Reading File B. Thomas J. Zwolinski (A) l S. Bajwa l l A. Dromerick l l S. Little l C. Hehl, Region I i i: OGC i

DOCUMENT NAME: G:\CC1-2\9602CLO1.MEM To receive a copy of this document, indicate in the box: "C" = Copy without attachment / enclosure ' "E" = Copy with rttrchment/ enclosure "N" = No copy l OFFICE PM:Ppj-)v/ j j lE LAIPDI 1 A V l D POI 1 , ,/) l l l j NAME ADMrfikOfc SLittle' F SBelue M'd DATE 04NI, /M 04/l(s/M 04/ ifs /M 04/ /M 04/ /98 )

Official Record Copy t .

Mr. Charles H. Cruse Baltimore Gas & Electric Company Calvert Cliffs Nuclear Power Plant cc:

President Mr. Joseph H. Walter, Chief Engineer Calvert County Board of Public Service Commission of Commissioners Maryland 175 Main Street Engineering Division

. Prince Frederick, MD 20678 6 St. Paul Centre Baltimore, MD 21202-6806 James P. Bennett, Esquire Counsel Kristen A. Burger, Esquire Baltimore Gas and Electric Company Maryland People's Counsel P.O. Box 1475 6 St. Paul Centre Baltimore, MD 21203 Suite 2102 Baltimore, MD 21202-1631 Jay E. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge Patricia T. Bimie, Esquire 2300 N Street, NW Co-Director Washington, DC 20037 Maryland Safe Energy Coalition P.O. Bor33111 Mr. Thomas N. Pritchett, Director Baltimore, MD 21218 i NRM I Calvert Cliffs Nuclear Power Plant Mr. Loren F. Donatelt 1650 Calvert Cliffs Parkway NRC Technical Training Center Lusby, MD 20657-4702 5700 Breinord Road Chattanooga, TN 37411-4017 Resident inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. Richard I. McLean, Manager Nuclear Programs Power Plant Research Program Maryland Dept. of Natural Resources Tawes State Office Building, B3 Annapolis, MD 21401 Regional Administrator, Region i U.S. Nuclear Regulatory Commission 475 Alendale Road i King of Prussia, PA 19406

,