Text
Commonwo:lth ECson c
Brtidwood Nuclair P:wgr Stttion Routs c1. Box 84 1
Braceville, Illinois 60407 Telephone 815/458-2801 October 13, 1986 l
Mr. Harold R. Denton Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555
SUBJECT:
Braidwood Station Unit 1 Deferral of Limited Aspects of the Pre-Operational Test Program NRC Docket No. 50-456
REFERENCE:
(a)
D.
L.
Farrar letter to H.
R.
Denton dated September 19, 1986
Dear Mr. Denton:
In reference (a) above, Commonwealth Edison request.ed schedular relief for a few. items contained in the Braidwood Station Pre-Operational Test Program.
The purpose of this letter is to inform you that the relief requested for certain tests is no longer needed.
Specifically, the following tests have been satisfactorily completed:
VQ-10 Containment Purge VQ-ll Hydrogen Recombiner VA-10 Auxiliary Building Cubicle Coolers Please address further questions regarding this matter to this office.
Very truly yours, MW A. D. M osi Nuclear Licensing Administrator ADM/TWS/ jab cc: