Delays 861015 Estimated Fuel Load Date Until 861031.Addl 2 Wks Required to Complete Final Const Activities
ML20215F647
Person / Time
Site: Byron Constellation icon.png
Issue date: 10/02/1986
From: Reed C
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
2204K, NUDOCS 8610160303
Download: ML20215F647 (1)


Text

_ . . . ,

ommonwealth Edison c_

%}= 72CWest Adams Street Chicago, Illinois V

Address Rep ly to: Post Office Box 767 N -

Chicago, Illinois 60690 - 0767 October 2, 1986 I Mr. Harold R. Denton, Director

! Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Byron Station Unit 2 Revision to Expected Fuel Load Date NRC Docket No. 50-455 Reference (a): November 18, 1985 letter from Cordell Reed to H. R. Denton

Dear Mr. Denton:

Reference (a) provided Commonwealth Edison's best estimate of the fuel load schedule for Byron Unit 2. It stated that the unit would be ready to load fuel no later than October 15, 1986. We have completed a detailed review of the activities remaining to support fuel load which indicates that an additional two weeks will be required to complete final construction activities. Thus, we estimate that Byron Unit 2 will be ready to load fuel on or about October 31, 1986.

Should any contingencies arise to cause fuel load to occur later than this date, I will keep you advised.

Very truly yours, Cordell Reed Vice President la cc: J. G. Keppler - RIII 2204K 8610160303 861002 PDR ADOCK 05000455 A PDR