ML20215F479
| ML20215F479 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 10/06/1986 |
| From: | Fay C WISCONSIN ELECTRIC POWER CO. |
| To: | Harold Denton, Lear G Office of Nuclear Reactor Regulation |
| References | |
| CON-NRC-86-93, TASK-***, TASK-OR VPNPD-86-416, NUDOCS 8610160232 | |
| Download: ML20215F479 (3) | |
Text
._
l Wisconsin Electnc eowca couesur 231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 (414)277-2345 VPNPD-86-416 NRC-86-93 October 6, 1986 Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U. S. NUCLEAR REGULATORY COMMISSION Washington, D.
C.
20555 Attention:
Mr. George Lear, Director PWR Project Directorate 1 Gentlemen:
DOCKETS 50-266 AND 50-301 LICENSEE'S IMPLEMENTATION OF GENERIC REQUIREMENTS POINT BEACH NUCLEAR PLANT Our letter to you dated May 30, 1986 provided Wisconsin Electric's response to your letter dated April 30, 1986 regarding a plant-specific listing of generic multi-plant issues.
The attachment to our letter listed completion dates or projected completion dates for those multi-plant issues which we were able to identify.
A number of issues remained open either because we could not identify the subject or because we had insufficient information to project a completion date.
Our letter to you dated July 11, 1986 provided projected completion dates for issues in the latter category based on your instructions that estimates for completion dates should be made assuming our present understanding of the issues.
Subsequently Mr. Colburn of your staff provided us with clarifying information relative to most of the multi-plant issues which we previously could not identify.
The enclosure to this letter lists these issues and their respective completion dates or notes the issues as not applicable to our operations.
This information was obtained through review of associated correspondence and is correct to the best of our knowledge.
8610160232 861006 f
PDR ADOCK 05000266 I (dy P
PDR i
a Mr. H. R. Denton October 6, 1986 Page 2 Please contact us if you have any questions concerning this information.
Very truly yours,
&Y C. W. Fay Vice President Nuclear Power Copy to Resident Inspector e
~.
' MULTI-PLAY. r ISSUE STATUS POINT BEACH NUCLEAR PLANT LIC ACT LICENSEE TAC MPA TITLE COMPLETE STATUS DATE M10560 A-12 Vital Area Analysis 04/13/82 NA' M12632 B-16 Emergency Planning'and. Revisions 04/01/81 Complete 1981 M10267 B-20 Containment Leakage Due to Seal Deterioration 01/01/70(1)
Complete 9/86.
M49427 B-32 Blocked SI' Signal During Cooldown 02/10/83 NA' M43145 B-43 PWR Feedwater Line Cracks 05/25/87 Complete 1980 M12399 B-44 Lessons Learned: Implementation 06/02/80( )
Complete 1980
~
M42697 B-61 Loss of Non-Class lE I & C Power.
07/28/82(3)
Complete 1980 M08473 C-09 PWR Auxiliary Feedwater Pumps 08/01/80 NA M07725 D-11 Fission Gas Release 02/22/80 Complete 1980 M12271 D-15 High Energy Line Break and Consequential System Failure 01/31/84 NA M49656 G-01 Reactor Coolant Pump Trip (D660-II.K 3.5) 02/28/86(4)
Complete
'12/85 Notes:
(1)
Licensee records indicate licensee action complete date'for this item is 9/26/86.
(2)
Licensee records indicate licensee action complete date for this item is 5/02/80.
(3)
Licensee records indicate licensee action complete date for this item is 2/29/80.
(4) Licensee records indicate licensee action complete date for this item is 12/4/85.
,