Responds to Request for Addl Info Re Alternate Radwaste Bldg (ARB) Preoperational Tests.Waste Water Demineralization, Resin Dewatering & Dry Active Waste Compaction Sys Constitute Three Operating Sys in ARB
ML20215F448
Person / Time
Site: Vogtle  
Issue date: 12/17/1986
From: Bailey J
GEORGIA POWER CO.
To: Youngblood B
Office of Nuclear Reactor Regulation
References
GN-1243, NUDOCS 8612230400
Download: ML20215F448 (2)


Text

--

^

Georgia Pbwer Company Post Offica Bcx 282

+-

Wayrtsborg Georgia 30830 Telephone 404 554-9961 404 724 8114 Southern Company Services, Inc.

Post Office Box 2625 Birmingham, Alabama 35202 Telephone 205 870-6011 VOgtle Project i

December 17, 1986 Director of Nuclear Reactor Regulation File: X7BC35 Attention:

Mr. B. J. Youngblood Log:

GN-1243 PWR Project Directorate #4 Division of PWR Licensing A U. S. Nuclear Regulatory Commission Washington, D.C.

20555 NRC DOCKET NUMBERS 50-424 AND 50-425 CONSTRUCTION PERMIT NUMBERS CPPR-108 AND CPPR-109 V0GTLE ELECTRIC GENERATING PLANT - UNITS 1 AND 2 REQUEST FOR ADDITIONAL INFORMATION:

ALTERNATE RADWASTE BUILDING PREOPERATIONAL TESTS

Dear Mr. Denton:

In recent discussions, your staff requested information concerning the preoperational testing of systems associated with the Alternate Radwaste Building (ARB). Information concerning ARB systems is provided herein.

The waste water demineralization system, the resin dewatering system and the dry active waste compaction system are the three temporary operating systems located in the ARB. The first two systems were supplied by NuPac Services.

These systems were designed, assembled, installed, calibrated as appropriate, hydroed, flushed and test operated, at the site, by NuPac. All maintenance, including annual instrument recalibrations, is to be provided on an as required and/or preventive basis.

The compactor was transferred from Plant Hatch where it was in operation until earlier this year. The manufacturer of the compactor checked its operability before shipment to Plant Vogtle and will check the unit again before it is placed in routine operation.

The described activities are considered to be the preoperational testing inside of the ARB. Other radwaste system piping was or is being tested as part of permanent systems.

Ohi22MAh ho 0424 PDR PDR

^

9P%'0 i

t

a^

Director of Nuclear Reactor Regulation December 17, 1986 Page 2 If you staff requires any additional information, please do not hesitate to contact me.

S

.e rely, t

' t-aly J. A. Bailey Project Licensing Manager JAB /caa xc:

R. E. Conway NRC Regional Administrator R. A. Thomas NRC Resident Inspector J. E. Joiner, Esquire D. Feig B. W. Churchill, Esquire R. W. McManus M. A. Miller (2)

L. T. Gucwa B. Jones, Esquire Vogtle Project File G. Bockhold, Jr.