h Public Service ~
- =g;&,
2420 W. 26th Avenue, Suite 1000, Denver, Colorado 80211 December 2, 1986 Fort St. Vrain Unit No.1 P-86653 Regional Administrator a @ 3 OW B_ %
Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 DEC - 5 M Arlington, Texas 76011 O
Attention: Mr. J. E. Gagliardo, Chief Reactor Projects Branch Docket No. 50-267
SUBJECT:
Use of AC and DC for Testing Breakers
REFERENCE:
PSC Letter Gahm to Gagliardo dated November 14, 1986
~
Dear Mr. Gagliardo:
~
In the reference letter PSC indicated that a procedure review was initiated to confirm that electrical breakers are being tested in an appropriate manner.
That procedure review has been completed and confirmed that the PSC practices for testing breakers using AC or DC power is correct.
As stated in the reference letter, DC power is used to test DC parts and AC power is used to test AC parts.
The review of our procedures found that the appropriate ANSI Standards, IEEE Standards, Manufacturer recommendations and PSC Corporate Standard Practices were used in the preparation of those procedures. No procedure changes are recommended as a result of this review.
If you have any concerns with this item, please contact Mr. M. H. Holmes at (303) 480-6960.
Very truly yours, A0 W-TLnfo D. W. Warembourg,3 nager Nuclear Engineering Division DWW/JRR:pa 8612160419 861202
[