ML20214T403
ML20214T403 | |
Person / Time | |
---|---|
Site: | Davis Besse |
Issue date: | 09/12/1986 |
From: | Hoyt H Atomic Safety and Licensing Board Panel |
To: | TOLEDO EDISON CO. |
Shared Package | |
ML20214T386 | List: |
References | |
86-525-01-ML, 86-525-1-ML, ML, NUDOCS 8609300286 | |
Download: ML20214T403 (1) | |
Similar Documents at Davis Besse | |
---|---|
Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20198L1911998-12-21021 December 1998
[Table view]Submits Comments Re Proposed Rule to Revise 10CFR50.59, Changes,Tests & Experiments ML20198L1361998-12-15015 December 1998 Comment Opposing Proposed Rule 10CFR50.65 Re Requirements for Monitoring Effectiveness of Maint of NPP ML20217J2161998-03-27027 March 1998 Comment on Proposed Generic Communication Re Lab Testing of nuclear-grade Activated Charcoal ML20217F5361998-03-25025 March 1998 Comment Opposing Draft Regulatory Guide DG-1071, Std Format & Content for Post-Shutdown Decommissioning Activities Rept ML20199J4651998-01-22022 January 1998 Comment Opposing Draft RG-1070, Sampling Plans Used for Dedicating Simple Metallic Commercial Grade Items for Use in Npps. RG Unnecessary Based on Use of EPRI Guideline & Excellent Past History of Commercial Grade Items at DBNPS ML20148M6421997-06-17017 June 1997 Comment on Proposed NRC Bulletin 96-001,suppl 1 Re Control Rod Insertion Problems.Nrc Should Review Info Provided in Licensee 970130 Submittal & Remove Statements of Applicability to B&W Reactors from Suppl Before Final Form ML20134L3401997-01-22022 January 1997 Resolution 96-R-85, Resolution Supporting Merger of Centerior Energy Corp & Ohio Edison Under New Holding Co Called Firstenergy ML20133B6941996-12-18018 December 1996 Submits Ordinance 850-96 Re Approval of Merger of Centerior & Oh Edison Into Firstenergy ML20132A8461996-12-0202 December 1996 Resolution 20-1996 Supporting Merger of Ohio Edison & Centerior Corp Under New Holding Company Called Firstenergy ML20134M6191996-10-28028 October 1996 Proclamation of Support by City of Sandusky,Oh Re Merger of Ohio Edison and Centerior Energy Corp ML20108D9571996-05-0303 May 1996 CEI Response to City of Cleveland 2.206 Petition.Nrc Should Deny Petition ML20097G5731996-02-13013 February 1996 Comment Supporting Petition for Rulemaking PRM-50-63 Re Use of Potassium Iodide ML20097B8721996-01-23023 January 1996 Petition of City of Cleveland,Oh for Expedited Issuance of Nov,Enforcement of License Conditions & Imposition of Appropriate Fines,Per 10CFR2.201,2.202,2.205 & 2.206 ML20101B5841996-01-23023 January 1996 Motion of City of Cleveland,Oh for Partial Summary Judgement Or,In Alternative,For Severance of Issue & Expedited Hearing Procedures.W/Certificate of Svc ML20097B8911996-01-23023 January 1996 Motion of City of Cleveland,Oh for Partial Summary Judgement or in Alternative,For Severance of Issue & Expedited Hearing Procedures ML20096E9781996-01-0808 January 1996 Comment on Proposed Suppl to GL 83-11, Licensee Qualification for Performing Safety Analyses in Support of Licensing Actions ML20087J3611995-08-14014 August 1995 Comment Opposing Proposed Rule 10CFR2 Re Rev of NRC Enforcement Policy ML20086M8241995-06-29029 June 1995 Comment on Proposed Review of NRC Insp Rept Content,Format & Style ML20083M8701995-05-10010 May 1995 Comment on Proposed Rule 10CFR50 Re Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactor ML20081C8841995-03-0303 March 1995 Comment Re NRC Proposed Generic Communication Suppl 5 to GL 88-20, IPEEE for Severe Accident Vulnerabilities. Util Ack NRC Efforts to Reduce Scope of GL 88-20,but Believes That Proposed Changes Still Overly Restrictive ML20077M5831995-01-0404 January 1995 Comment Opposing Proposed Rule 10CFR50 Re Shutdown & low-power Operations for Nuclear Power Reactors ML20072K3611994-08-16016 August 1994 Comment Opposing Proposed Rule 10CFR72 Re Plans for Storage of Sf at Davis Besse NPP ML20072K4411994-08-14014 August 1994 Comment Opposing Proposed Rule 10CFR72 Re Dry Storage of Nuclear Waste at Facility in Toledo,Oh ML20072K5261994-08-12012 August 1994 Comment Supporting Proposed Rule 10CFR72 Re Addition of Standardized NUHOMS Horizontal Modular Storage Sys to List of Approved Sf Storage Casks ML20072B1581994-08-0909 August 1994 Comment Opposing Proposed Rule 10CFR72 on List of Approved Spent Fuel Storage Casks:Addition ML20029D8221994-04-19019 April 1994 Comments on Proposed Rule 10CFR50 Re Codes & Stds for Nuclear Power Plants;Subsection IWE & Subsection Iwl ML20062M4011993-12-28028 December 1993 Comment Supporting Petition for Rulemaking PRM-21-2 Re Commercial Grade Item Dedication ML20046A9561993-07-19019 July 1993 Comment on Proposed Rules 10CFR170 & 171, FY91 & 92 Proposed Rule Implementing Us Court of Appeals Decision & Rev of Fee Schedules;100% Fee Recovery,FY93. ML20056C8951993-07-19019 July 1993 Order Extending Time within Which Commission May Rule on Petitions for Review of LBP-92-32.W/Certificate of Svc. Served on 930720 ML20045F8321993-06-22022 June 1993 Comment on Proposed Rule 10CFR26 Re Mods to fitness-for-duty Program Requirements.Concurs W/Proposed Rule in Reducing Random Testing Rate of Licensees to 50% & Disagrees W/ Maintaining Random Testing Rate of 100% for Vendors ML20044E2781993-05-13013 May 1993 Comment Supporting Petition for Rulemaking PRM-50-58 Re VEPCO Petition to Change Frequency of Emergency Planning Exercise from Annual to Biennial ML20044E1561993-04-29029 April 1993 Comment Supporting Petition for Rulemaking PRM-50-58 Re Frequency Change of Emergency Planning Exercises ML20127L8781993-01-19019 January 1993 Comment Supporting Comments Submitted by NUMARC Re Draft Reg Guide DG-1020 ML20127A6171993-01-0606 January 1993 Order.* Time within Which Commission May Rule on Petitions for Review of Board Order LBP-92-32,dtd 921118,extended Until 930208.W/Certificate of Svc.Served on 930106 ML20126D5801992-12-23023 December 1992 NRC Staff Answer in Response to Petitions for Review Filed by Oh Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & City of Cleveland.* W/Certificate of Svc ML20126F6501992-12-23023 December 1992 Answer of City of Cleveland,Oh,Intervenor,In Opposition to Petitions for Review of 921118 Decision of Aslb.* Petitioners Petitions for Review Should Be Denied. Certificate of Svc Encl ML20126D5171992-12-23023 December 1992 City of Brook Park Answer to Petitions for Review.* Opposes Applicants 921208 Petitions for Review Based on Fact That ASLB Decision in proceeding,LBP-92-32,adequately Addressed Issues Raised in Petitions.W/Certificate of Svc ML20126D5461992-12-23023 December 1992 Answer of Cleveland Electric Illuminating Co & Toledo Edison Co to Limited Petition for Review of City of Cleveland,Oh of 921118 Decision of Aslb.* Commission Should Deny City of Cleveland Petition.W/Certificate of Svc ML20126D5781992-12-23023 December 1992 Answer of American Municipal Power-OH,Inc in Opposition to Petitions for Review of Oh Edison Co & Cleveland Electric Illuminating Co/Toledo Edison Co.* W/Certificate of Svc ML20126D4761992-12-22022 December 1992 Alabama Electric Cooperative Answer to Applicants Petitions for Review.* Applicants 921208 Petitions for Review Should Be Denied.W/Certificate of Svc ML20126A5461992-12-10010 December 1992 Order.* Requests That Answers to Petition for Review Be Filed No Later than 921223.W/Certificate of Svc.Served on 921210 ML20126A5751992-12-0808 December 1992 Petition for Review.* Requests That NRC Review LBP-92-32, 921118 Board Decision in Proceeding.Board Erroneously Interpreted Section 105(c) of AEA by Ignoring Fundamental Underpinning of Statute.W/Certificate of Svc ML20126A5871992-12-0808 December 1992 Petition for Review.* Requests That NRC Review ASLB 921118 decision,LBP-92-32.Board Erroneously Interpreted Section 105(c) of AEA by Ignoring Fundamental Underplanning of Statute.Certificate of Svc Encl ML20126A7651992-11-18018 November 1992 Limited Petition for Review of City of Cleveland,Oh of 921118 Decision of Aslb.* City of Cleveland Petition for Review Should Be Granted.W/Certificate of Svc ML20115E1771992-10-0808 October 1992 Comment Supporting Draft Mgt Directive 8.6,GL 92-05 ML20105C8971992-09-16016 September 1992 Comment Opposing Proposed Generic Communication Re Generic Ltr Concerning analog-to-digital Replacements Under 10CFR50.59 ML20114A8841992-08-17017 August 1992 Designation of City of Brook Park,Oh of Adopted Portions of Summary Disposition Pleadings.* Brook Park Not Advancing Any Addl Argument or Analysis in Connection W/Designation,Per 920806 Memorandum & Order.W/Certificate of Svc ML20099E1821992-07-28028 July 1992 Comment Supporting Proposed Rules 10CFR20 & 61 Re LLW Shipment Manifest Info & Reporting ML20099A4051992-07-17017 July 1992 Comment on Proposed Rules 10CFR20 & 50 Re Reducing Regulatory Burden on Nuclear Licensees.Supports Rules ML20101R4831992-07-0808 July 1992 Comment Supporting Proposed Rule 10CFR50 Re Receipt of Byproduct & Special Nuclear Matl 1998-03-27 Category:ORDERS MONTHYEARML20056C8951993-07-19019 July 1993
[Table view]Order Extending Time within Which Commission May Rule on Petitions for Review of LBP-92-32.W/Certificate of Svc. Served on 930720 ML20127A6171993-01-0606 January 1993 Order.* Time within Which Commission May Rule on Petitions for Review of Board Order LBP-92-32,dtd 921118,extended Until 930208.W/Certificate of Svc.Served on 930106 ML20126A5461992-12-10010 December 1992 Order.* Requests That Answers to Petition for Review Be Filed No Later than 921223.W/Certificate of Svc.Served on 921210 ML20195F9591988-11-21021 November 1988 Order Modifying License NPF-3 Re Allegation Identified from 880504-0902 Insp Concerning Discriminatory Layoff by Former QC Manager of QC Inspector at Plant.Notice of Violation & Proposed Imposition of Civil Penalty Issued ML20214W5151987-06-0909 June 1987 Order.* Order Extending Time Until 870622 for Commission to Determine Whether to Review Administrative Judge 870415 Decision Affirming,Prior to NRC Approval,Disposal of Mixed Water Treatment Waste by Land Burial ML20210B7361987-04-29029 April 1987 Order.* Extends Time for Commission to Determine Whether to Review 870415 Decision Affirming Prior NRC Approval of Disposal of Mixed Water Treatment Waste & Slightly Radioactive Ion Exchange Resins on Site.Served on 870430 ML20210J1591986-09-29029 September 1986 Order Advising Parties That Comments on Applicant Project Plan/Conceptual Design Disposal of Very Low Level Radwaste at Davis-Besse Site Must Be Submitted by 861015.Served on 860930 ML20214T3841986-09-26026 September 1986 Order Directing That Incorrect Title Page on 860912 Order Be Withdrawn & Encl Corrected Page Substituted for Original. Served on 860929 ML20214T4031986-09-12012 September 1986 Corrected Order Granting Licensee 860908 Motion to Correct Transcript of 860805-07 Proceeding.Corrections Listed ML20209J5561986-09-12012 September 1986 Order Granting Licensee 860908 Motion to Correct Transcript of 860805-07 Proceeding.Corrections Listed.Served on 860916 ML20214K0211986-08-11011 August 1986 Order Stating That Filings of Findings of Fact & Conclusions of Law Ordered at 860807 Hearing Constitute Simultaneous Filings by All Parties for in-hand Delivery on 860908.Served on 860813 ML20202F8771986-07-10010 July 1986 Order Setting New Hearing on 860721 & 0804-06 in Sandusky,Oh to Hear Testimony & to Take Limited Appearances.Served on 860711 ML20206P6441986-06-25025 June 1986 Memorandum Correcting 860605 Fr Notice Re Reason for Ohio Radioactive Matls Users Group 860420 Petition to Intervene. Group Intends to Perform Analysis of Possible Impact of Action.Served on 860626 ML20198J5691986-05-29029 May 1986 Memorandum & Order Granting Listed Petitions to Intervene Re 851015 Approval of Util Request for Onsite Disposal of Byproduct Matl & Delineating Order of Presentation for 860619 & 23-26 Hearings.Served on 860530 ML20138A2111986-03-10010 March 1986 Memorandum & Order Directing That Petition to Participate in Hearing Re Licensee Request for Onsite Disposal of Product Matl Be Filed by SA Carter & Other Parties by 860414.Notice of NRC Participation Required by 860428.Served on 860311 ML20062B8141978-10-20020 October 1978 Orders ASLB to Issue Initial Decision Upon Completion of Hearings on Radiological Health & Safety Issues Remaining in Proceedings.Review of Issuance of LWA-2 on 780830 Deferred Until ASLB Issues Decision 1993-07-19 |
Text
,
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before Helen F. Hoyt Administrative Judge
)
In the Matter of ) Docket No. 50-346-ML
)
TOLEDO EDIS0N COMPANY, ET AL. ASLBP No. 86-525-01-ML (Davis-Besse Nuclear Power Station, Unit No. 1 September 12, 1986
)
ORDER On September 8, 1986, Toledo Edison Company, et al. (Licensee) filed Motion for Transcript Corrections. A review of these corrections has resulted in several corrections. As corrected, the Licensee's motion is granted and the following corrections in the transcript of this proceeding conducted from August 5 to August 7,1986 will be made in accordance with the provisions of 10 C.F.R. 2.750(b).
Page Line Correction 31 Exhibits A through M should be attached to Licensee's testimony 8609300206 860926 PDR ADOCK 05000346 0 PDR