Text
$bQ, o
/NEA r, woo Neuenar sne mek a Laoreewy a
March 4, 1987 isk (u
Mr. M. Carrington, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 TRANSMITTAL OF FINAL REPORT, "CONFORMANCE TO GENERIC LETTER 83-28, ITEM 2.2.2, VENDOR INTERFACE PROGRAMS (ALL OTHER SAFETY-RELATED COMPONENTS), CALLAWAY PLANT," EGG-NTA-7553, FEBRUARY 1987 (FIN 06001) -
EWR-42-87 Ref: NRC Form 189, " Evaluation of Conformance to Generic Lotter 83-28 For ors (Project 2)" (06001)
Dear Mr. Carrington:
Transmitted herewith is tho above subject report.
The report documents INEL's ovaluation of the licensco actions in response to NRC Generic Letter 83-28, item 2.2.2, Vendor Interfaco Programs (All other Safety-Related Components).
Based on the licensoo submittal, we conclude that the plant conforms to the generic letter on this item.
Very truly you s, h
d E. W. Roberts, Manager NRC Headquarters Support ACU:gp Enclosuro:
As Stated G
cc:
G. L. Jones, 00E-10 A Toalston, NRR-PAEl (2)
F. Rosa, NRC 0PWR-A J, O. Zane, EGF.G Idaho, Inc. (w/o Encl.)
0706050349 070304 PDH ADOCK 05000403 Y