Notice of Violation from Insp on 860915-1030
ML20214P105
Person / Time
Site: Byron  Constellation icon.png
Issue date: 11/28/1986
From: Harrison J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20214P058 List:
References
50-455-86-30, NUDOCS 8612040077
Download: ML20214P105 (1)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ ____ -

l I

NOTICE OF VIOLATION Commonwealth Edison Company Docket No. 50-455 As a reruit of the inspection conducted on September 15 through October 30, 1986, and in accordance with the " General Policy ar.d Procedures for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1985), the following violation was identified:

10 CFR 50, Appendix B, Criterion XVI, as implemented by Ceco Topical Report CE-1-A, " Quality Assurance Program for Nuclear Generating Stations,"

[ and CECO Corporate Quality Assurance Manual, Nuclear Generating Stations, I

(

" Quality Requirements," requires that measures shall be established to t assure that conditions adverse to quality, such as deficiencies and l nonconformances are promptly identified and corrected.

Contrary to the above, on September 17, 1986, five pipe hangers were found to have loose nuts on the hanger connections although they had received final inspection by the licensee's QC personnel prior'to September 1985. These nonconformances were observed on five safety-related pipe hangers which were not identified and corrected as required by Hunter Site Implementation Procedure SIP No. 4.201.

This is a Severity Level V violation (Supplement II).

The inspection showed that action had been taken to correct the identified violation and to prevent recurrence. Consequently, no reply to the violation is required and we have no further questions regarding this matter.

f oAg/u Dated '

h~&

J. J. Harrison, Chief Engineering Branch 1

8612040077 861128 PDR ADOCK 05000454 G PDR