Discusses Documents Re Ambrosia Lake Remedial Action Plan Received on 861008.Documents Denoted as Preliminary Design Documents & Review Not Useful.Requests Future Correspondence Be Signed by Recipient or Designated Staff Member
ML20214J407
Person / Time
Issue date: 11/13/1986
From: Hawkins E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Themelis J
ENERGY, DEPT. OF
References
REF-WM-67 NUDOCS 8612010292
Download: ML20214J407 (2)


Text

_ _ _ _ _..

DISTRIBUTION H

Docket file WM-067

PDR/DCS b WM-067/EFH/86/11/05/0

, RIV LLW Branch, WMLU URF0 r/f NOV 131986 URF0:EFH Docket File WM-067 040WM067 E CE"Fr Mr. John G. Themelis U.S. Department of Energy

'86 NOV 24 f00:34 Albuquerque Operations Office P.o. Box 5400 87J15d.krm Albuquerque, New Mexico F

110 U

Dear Mr. Themelis:

On October 8, 1986, we received three sets of the following documents concerning the Ambrosia Lake RAP from Mr. J. G. Oldham of MK-Ferguson Company:

1.

Main Construction Subcontract Documents, AMB-4.

2.

Calculations Documents, Volumes I, II, and III.

They are denoted as Preliminary Design Documents, with final designs to

]

be forthcoming in the future.

We do not consider the review of these documents to be useful to DOE or NRC at this time.

Instead, we will review the final design in detail when it is submitted with the Final Remedial Action Plan (RAP). This g

determination is based on our review of the Draft RAP that did not

~

identify any r,ajor flaws with the conceptual design upon which this preliminary design is based, and on our understanding that the final design details may be significantly different from the preliminary design because of actual field data and testing currently underway (rather than assumed parameters).

In addition, review of this type of intermediate and preliminary information at this time is not considered to be the n.ost efficient use of our limited resources.

I have, however, asked the staff to perform a cursory review of the preliminary design as time permits.

Any major flaws will be noted and you will be informed.

In the future, documents should not be routinely transmitted for our review before they have been reviewed and approved by DOE.

Therefore, we OFC :

NAME :

DATE :86/11/13 861201029286111b PDR WASTE WM-67 PDR

s WM-067/EFH/86/11/05/0 NOV 131986 request that such correspondence and documents be signed by you or a designated member of your staff. We look forward to meeting with you and your contractors on December 4, 1986. Hopefully, we will be able to develop more efficient and effective ways to interact on this project and still perform our respective assignments.

Sincerely,

/3 Edward F. Hawkins, Chief Licensing Branch 1 Uranium Recovery Field Office Region IV g