Forwards Discharge Monitoring Rept for Oct 1986.Settling Basins Isolated from Station Discharge Following 860821 Incident.Sampling at Station Discharge Continued Until 860917 to Verify That No Pcb Discharged Into Lake Erie
ML20214D249
Person / Time
Site: Davis Besse 
Issue date: 11/11/1986
From: Gephart A, Storz L
TOLEDO EDISON CO.
To: Fenner K
ENVIRONMENTAL PROTECTION AGENCY
Shared Package
ML20214D252 List:
References
GA86-0619L, GA86-619L, NUDOCS 8611210434
Download: ML20214D249 (2)


Text

.

TOLEDO

% EDISON EDISON RA2A 300 MADISON AVENUE TREDO. OHIO 43652 RR 2 P-12-86-10 E 2.40.1.1.2 GA86-0619L November 11, 1086 U.S. EPA - Region V (5WQP)

Water Quality Branch 230 S. Dearborn Street Chicago, Illinois 60604 ATTENTION:

Kenneth Fenner, Chief

Dear Mr. Fenner:

Attached is a copy of the October, 1986, Ohio EPA Discharge Monitor-ing Report for Davis-Besse Nuclear Power Station, Permit Number 21B00011*DD.

Immediately following the PCB incident on August 21, 1986 the settling basins were isolated from the station discharge (0utfall

  1. 001). Sampling at the station discharge continued until September 17, 1986, to verify that no PCB's were discharged to Lake Erie.

Throughout September, the settling basins were isolated and there was no discharge to Outfall #001. Therefore, no PCB analyses were reported.

Starting October 3, 1986, the north settling basin was dewatered, as recommended by the Northwest District Office of the Ohio EPA, through a bed of activated carbon.

From filtration efficiency tests performed the adsorptien of PCB onto the carbon ensured that at no time during the dewatering process was the PCB concentration at Outfall #001 greater than 1 part per trillion.

Sampling of discharge from the south settling basin was performed in accordance with permit requirements with results from the analysis at Outfall

  1. 602 being recorded on the enclosed monthly reports.

Normal operation of the Water Treatment Facility and the settling basins commenced on November 6, 1986.

It will take approximately three weeks to fill the north settling basin and subsequently discharge to Outfall #001. During this period, effluent from the Water Treatment Facility will be sampled to ensure there is no further PCB discharge from the affected sumps.

8611210434 861111 PDR ADOCK 05000346 1

g R

PDR

U.S. EPA November 11, 1986 Page 2 Once discharge is established from the north settling basin, ad-ditional sampling will be done at Outfall #001 for some period of time to ensure that the discharge meets Lake Erie Water Quality Standards.

Yours truly.

[N

/

L. F. Storz

((,4 Plant Manager, Davis-Besse A. Pf. Gephart Davis-Besse Nuclear Power Station 3-84-58 (419) 249-5000 Extension 7589 Class III Operator, Wastewater Treatment LFS/PJM/jjh Attachments cc:

P. Byron, NRC Resident Inspector A. F. Gephart J. L. Scott-Wasilk J. F. Stolz, NRC /

J. E. Sullivan bec:

D. B. Amerine D. W. Briden R. K. Flood R. J. Scott i

-.. ~.

.