ML20214B216

From kanterella
Jump to navigation Jump to search
Notification of 860219 Meeting W/Util in Bethesda,Md to Discuss Licensee Response to Request for Info Re Station Blackout
ML20214B216
Person / Time
Site: Millstone Dominion icon.png
Issue date: 02/13/1986
From: Doolittle E
Office of Nuclear Reactor Regulation
To: Noonan V
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-44, REF-GTECI-EL, TASK-A-44, TASK-OR NUDOCS 8602200507
Download: ML20214B216 (4)


Text

r FEB 131986 -

Docket No.:

50-423 MEMORANDUM FOR:

Vincent S..Noonan, Director PWR Project Directorate #5 Division of PWR Licensing-A FROM:

Elizabeth L. Doolittle, Project Manager PWR Project Directorate #5 Division of PWR Licensing-A

SUBJECT:

FORTHCOMING MEETING WITH NORTHEAST UTILITIES TO DISCUSS STATION BLACK 0UT AT MTLLSTONE 3 DATE & TIME:

Wednesday, February 19, 1986 8:30 a.m. - 1 p.m.

LOCATION:

Landow Building, Suite 208 7910 Woodmont Avenue Bethesda, Maryland PURPOSE:

To discuss the licensees' response to the staff's request for information regarding station blackout at Millstone 3.

PARTICIPANTS:

NRC NU V. Noonan J. Opeka E. Doolittle M. Childers and T. Speis

  • J. Bickel A. Rubin A. Buslik G. Kelly Elizabeth L. Doolittle, Project Manager PWR Project Directorate #5-Division of PWR Licensing-A E

ttle 2/G85 h

,/

o,,

UNITED STATES E

o NUCLEAR REGULATORY COMMISSION h

e t WASHINGTON, D. C. 20555 M

q FEB 13 ggs Docket No.:

50-423 MEMORANDUM FOR:

Vincent S. Noonan, Director PWR Project Directorate #5 Division of PWR Licensing-A FROM:

Elizabeth L. Doolittle, Project Manager PWR Project Directorate #5 Division of PWR Licensing-A

SUBJECT:

FORTHCOMING MEETING WITH NORTHEAST UTILITIES TO DISCUSS STATION BLACK 0UT AT MILLSTONE 3 DATE & TIME:

. Wednesday, February 19, 1986 8:30 a.m. - 1 p.m.

LOCATION:

Landow Building, Suite 208 7910 Woodmont Avenue Bethesda, Maryland

)

PURPOSE:

To discuss the licensees' response to the staff's request for infonnation regarding station blackout at Millstone 3.

PARTICIPANTS:

NRC NU V. Noonan J. Opeka E. Doolittle M. Childers and T. Spets J. Bickel A. Rubin A. Buslik G. Kelly

{

Elizabe L. Doolittle, Project Manager PWR Project Directorate #5 Division of PWR Licensing-A 9

5, 4

Mr. J. F. Opeka.

Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. 3 cc:

' Gerald Garfield, Esq.

Ms. Jane Spector Day, Berry & Howard Federal Energy Regulatory Commission City Place 825 N. Capitol Street, NE Hartford, Connecticut 06103-3499 Room 8608C Washington, D.C.

20426 Mr. Maurice R. Scully, Executive Director Mr. Kevin McCarthy, Director Connecticut Municipal Electric Radiation Control Unit Energy Cooperative Department of Environmental Protection 268 Thomas Road State Office Building Groton, Connecticut 06340 Hartford, Connecticut 06115 Robert W. Bishop, Esq.

Corporate Secretary Northeast Utilities Post Office Box 270 Hartford, Connecticut 06141 Mr. T. Rebelowski Senior Resident Inspector Office U. S. Nuclear Regulatory Comission Millstone III P. O. Box 615 Waterford, Connecticut 06385 Mr. Michael L. Jones, Manager Project Management Department Massachusetts Municipal Wholesale Electric Company Post Office Box 426 Ludlow, Massachusetts 01056 Regional Administrator U. S. NRC, Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Mr. Karl Abraham Public Affairs Office, Region I U. S. Nuclear Regulatory Commission, King of Prussia, Pennsylvania 19406

~

MEETING NOTICE DISTRIBUTION

06&ketterCentral File NRC Participants NRC PDR

.v. Noonan Re ding File

[

N**1*

^* *"Di" H. Denton Project Manager E. Doolittle OELD E. Jordan ~

B. Grimes J. Partlow (Emergency Preparedness only)

Receptionist (Bldg. where meeting is being held)

ACRS(10)

OPA

}

'N. Olson

~

Resident Inspector Regional Administrator

h. Rushbrook cc: Licensee / applicant & Service List

~

o