Forwards Revised Schedule for Implementation of Reg Guide 1.97,per Commitment Made at 860814 Meeting
ML20213G077
Person / Time
Site: Rancho Seco
Issue date: 11/12/1986
From: Julie Ward
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Miraglia F
Office of Nuclear Reactor Regulation
References
RTR-REGGD-01.197, RTR-REGGD-1.197 JEW-86-668, NUDOCS 8611170314
Download: ML20213G077 (2)


Text

r

\\

r

$ SMU =

SACRAMENTO MUNICIPAL UTILITY DISTRICT "

P. O. Box 15830, Sacramento CA 95852-1830,(916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA JEW 86-668 November 12,1986 Director of Nuclear Reactor Regulation Attention:

Frank J. Miraglia, Jr.

Division of PWR Licensing-B U S Nuclear Regulatory Commission Washington D C 20555 Docket 50-312 Rancho Seco Nuclear Generating Station Unit il REGULATORY GUIDE 1.97 IMPLEMENTATION SCHEDULE

Dear Mr. Miraglia:

In an August 14, 1986 meeting with the NRC, the District committed to l

accelerate its schedule for implementation of Regulatory Guide 1.97.

Attached is the District's revised implementation schedule.

If you have any questions, please contact Jerry Delezenski of my staff.

Sincerely,

[

Jo

. Nard Deputy General Manager, Nuclear cc: Sydney Miner, NRC, Bethesda Tony D'Angelo, NRC, Rancho Seco 6611170314 861112 0>

d PDR ADOCK 05000312 n0 P

PDR D

1\\

DISTRICT HEADQUARTERS O 6201 S Street, Socramento CA 95817-1899

t DATE OF ORIGINAL VARIABLE COMMITHENT COMMITMENT NEW

/

NUMBER

  • VARIABLE UPGRADE TO:

LETTER DATE DATE 14 Coolant Inventory (ICC)

New 9/14/84 Cycle 8 Cycle 8 Variable (No change)

(Cat 1) 4 Steam Generator Cat 1 9/14/84 Cycle 9 Restart 87 Level 5

Steam Generator Pressure Cat 1 9/14/84 Cycle 9 Restart 87 1

RCS Hot Leg Temperature Cat 1 9/14/84 Cycle 8 Restart 87 44 Pressurizer Level Cat 1 9/14/84 Cycle 9 Restart 87 Density Compensation N/A SPDS Upgrade Cat 1 9/14/84 Cycle 9 Restart 87 i

(Class 1 redundant indication) 6 Neutron Flux Cat 1 10/31/85 Cycle 9 Cycle 8 35 RHR (Decay Heat) Heat Cat 2 10/31/85 Cycle 9 Cycle 8 Exchanger Outlet 47 Quench Tank (PRT) Temperature Low Range 10/31/85 Cycle 8 Cycle 8 (Remains (No Change) j Cat 3) 57 Containment Atmosphere Cat 2 10/31/85 Cycle 9 Cycle 8 Temperature 62A Component Cooling Water Cat 2 10/31/85 Cycle 9 Cycle 8 Temperature to ESP System (NSCW) 45 Pressurizer Heater Status Direct 1/13/86 Cycle 9 Cycle 8 Indication (Remains Cat 3)

As identified in the District's October 31, 1985 and September 14, 1984 submittals.