o TENNESSEE VALLEY AUTHORITY CH ATTANOOG A. TENNESSEE 37401 SN 157B Lookout Place APR 171987 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C. 20555 centlemen:
In the Matter of
)
Docket Nos. 50-327 Tennessee Valley Authority
)
50-328 SEQUOYAH NUCLEAR PLANT (SQN) UNIT 2 - RESTART HOLDPOINTS Establishment of holdpoints for SQN unit 2 restart was discussed with members of the NRC staff during the meetings held February 5 and 6, 1987, at SQN.
The holdpoints that will be utilized in the unit 2 restart effort are as follows:
1.
Before entry into mode 4 (HOT SHUTDOWN) 2.
Before entry into mode 2 (STARTUP) 3.
Before entry into mode 1 (POWER OPERATION) 4.
Before exceeding 30-percent Rated Thermal Power 5.
Before exceeding 75-percent Rated Thermal Power A formal restart procedure is presently being drafted.
This procedure will outline the sequence in which events are to occur during the restart effort.
This sequence will include a management assessment of activities and plant status before proceeding beyond each of the above holdpoints. Under the present schedule, this procedure is expected to be issued and available for review by June 1, 1987.
Very truly yours, TENNESSEE VALLEY AUTHORITY
. h.
. Gridley, Director Nuclear Safety and Licensing cc:
See page 2 l
t 8704230014 870417 DR ADOCK 05000328 PDR An Equal Opportunity Employer
e I U.S. Nuclear Regulatory Commission
{fQ] cc: Mr. G. G. Zech, Assistant Director for Inspection Programs Office of Special Projects U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Sequoyah Resident Inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road Soddy Daisy Tennessee 37379 l l -}}