Forwards NRC Quarterly Rept to Congress on Emergency Preparedness,Apr-June 1986
ML20212M080
Person / Time
Issue date: 08/12/1986
From: Roberts T
NRC COMMISSION (OCM)
To: Simpson A
SENATE, ENVIRONMENT & PUBLIC WORKS
Shared Package
ML20212M083 List:
References
NUDOCS 8608250369
Download: ML20212M080 (7)


Text

'

PDFL

.m k

/

g o

UNITED STATES NUCLEAR REGULATORY COMMISSION s

e o

,I WASHINGTON, D. C. 20565 k,,.....,o#

August 12, 1986 CHAIRMAN The Honorable Alan K. Simpson, Chairman Subcommittee on Nuclear Regulation Committee on Environment and Public Works United States Senate Washington, D.C.

20510

Dear Mr. Chairman:

The NRC quarterly status report on emergency preparedness for nuclear power plants is enclosed. The report, our 28th, covers the period from April 1 to June 30, 1986.

In the Shoreham case, the Commission is unable to forecast realistically the licensing schedule because of the emergency preparedness issues.

In the Seabrook case, offsite emergency preparedness issues have the potential to delay the licensing schedule; however, the length of any such delay cannot be estimated at this time.

In the Hope Creek case, an operating license restricted to five percent power was issued in April 1986. On July 25, the staff issued a license authorizing full-power following Commission approval on July 21, 1986.

Minor revisions, as noted in Table 1, have occurred in other operating license review schedule dates since our last report to Congress; none of these revisions are projected to result in any delays in the licensing process.

Please notify us if you desire additional information.

Sincerely,

.I omas M.

oberts Acting Chairman

Enclosure:

NRC Quarterly Status Report cc: The Honorable Gary Hart 8608250369 860312

~

PDR COMM3 74pcc CORRESPONDENCE'PDR