JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE SUPNARY OF OPERATIONS -
October, 1986 L
During the month of October, there were no unit shutdowns or significant power reductions.
The following major safety-related maintenance was performed in the month of October:
1.
Miscellaneous 1 corrective and preventive maintenance was performed on diese.1 generators.
"~
8701290442 861031 PDR ADOCK 05000364 R
PDR B&HY-
/
-)
DOCKET NO.
50-364 i
UNIT 2 DATE 11/4/86 COMPLETED BY J. D. Woodard TELEPHONE (205)899-5156
!Cmi October DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (19fe-Net)
(P97e-Net) 1 818 17 839 2
817 18 837 3
818 19 840 4
817 20 841 5
814 21 842 6
822 22 840 7
830 23 833 8
825 24 827 9
823
' 25 826 10 824 26 833 11 829 27 834 12 827 28 836 13 823 29 835 14 828 30 834 15 777 31 833 16 839 INSTRUCTIONS on this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
Form 13/20 i
. :.- :. :. 22 ::.2 ::
OPERATING DATA REPORT DOCKET NO. 50-364 DATE 11/4/86 COMPLETED BY L D. Woodard TELEPHONE (?nsmoo-5156 OPERATING STATUS Notes
- 1. Unit Name:-
Joseph M. Farley - Unit 2
- 2. Reporting Period:
October. 1986 1")
Cdmulative data since
- 3. L4" Thermal Power (MWt):
76s2 7/30/81, date'~of 860 commerMal operatio.n.
- 4. Nameplate Rating (Gross MWe):
829
- 5. Demsn Electncal Rating (Net MWe):
872.2
- 6. Maximum Dependable Capacity (Gross MWe):
829.2
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
N/A N/A
- 9. Power Level To Wluch Restncted,If Any (Net MWe):
N/A
- 10. Reasons For Restrictions. If Any:
O V
s This Month Yr.-to.Dete Cuinulative 745 7,296 46,081
!!. Hours In Reportmg Period
- 12. Number Of Hours Reactor Was Critical 745 6.085.6 44.892.2 0.0 0.0 138.0
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On-Line 745 5,994.4 39,386.8
- 15. Unit Reserve Shutdown Hours 0.0 0.0 -
0.0
- 16. Gross Thermal Energy Generated (MWH) 1,966,262-15,207,791 99,442,341 l
- 17. Gross Electrical Energy Generated (MWH) 646.982 5.007,782 32.730.470
- 18. Net Electrical Energy Generated (MWH) 616,728 4,740,874 31,030,114
[
- 19. Unit Service Factor 100.0 82.2 85.5
- 20. Unit Availability Factor 100.0 82.2 85.5 99.8 78.4 82.8
- 21. Unit Capacity Factor (Using MDC Net) 99.9 78.4 81.2
- 22. Unit Capacity Factor (Using DER Net) 0.0 3.0 4.5 l
- 23. Unit Forced Outage Rate
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date. and Duration.of Ench):
N/A
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
N/A
- 26. Units In Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY 05/06/81 05/08/81 INITIAL ELECTRICITY 05/24/81 05/25/81 COMMERCIAL OPERATION 08/01/81 07/30/81 (W7n
~
o O
O UNIT Silu1 DOWNS AND POWER REDUC 110NS DOCKET NO.
50-364 UNIT NAME J.M. Farley - Unit 2 DATE November 4, 1956 REPORT MONTil October COMPLEYED ay J.D. Woodard TELEPHONE (205)899-5156 i
e.
E u
Licensec Ev, f q, 5 E
}
} Yj Cause & Coneceive No.
Date g
3g
,ye Event uiu?
o3 Acti m to g
g3 $
,U d g Repius #
[u 6
1 p,,,,,,gecogene, d
I THEI E WERE NO UN: T SHI TDOWNS C R SIGl lIFICAN1 POWER REDUCTI< INS DUR ENG THE MO: TH OF OCTOBER.
1 4
1 l
1 i
l l
2 3
4 F: Fo ced Reason:
Method:
Exhibit G Insisuctions S: Stheduled A Equipmens Failure (Explain) 1 -Manual for Preparation of Data Il Maintenance of Test 2-Manual Scram.
Entry Sliccis for I.iccusec 0 Refuchug 3 Automatic Scram.
Event Report li.ER) File (NUREG-D Regulatiny Rest:iction 4 Oshes (Eaplain) 0161)
E Operator Training & t.icense Examination F-Administrative 5
G Ope ational Enror (Expl.iin)
Exhibis 1 - Same Sousee (9/77) 11 Olhe: (Expl.iin) i
i.* :l
' *. Mamng Address Alibim1 Power CompIny
~ 600 North 18th Strett Post Office Box 2641
' Birmingham Alabama 35291 Telephone 205 783-G090 R. P. Mcdonald Senior Wce President Flintridge Building AlabamaPower tne sovrem eec:?-C si s?e" November 7, 1986 Docket No. 50-364 -
Director, Office of Resource Management U. S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Sir:
RE: Joseph M. Farley Nuclear Plant Unit 2 Monthly Operating Data Report Attached are two (2) copies of the October 1986 Monthly Operating Report for Joseph M. Farley Nuclear Plant Unit 2, required by Section 6.9.1.10 of the Technical Specifications.
If you have any questions, please advise.
Yours very uly,
G n-R. P. Mcdonald RPM /BCE:amh/F-2 1
Enclosures xc: Director, IE (10 copies)
Director, RII (1 copy) 7