Discusses Re Consolidation of Station Protected Areas.Due to Unavailability of Long Lead Component & Adverse Weather,Project Will Not Be Completed as Scheduled.Status Rept & Revised Schedule Encl.Encl Withheld
ML20212L911
Person / Time
Site: Salem, Hope Creek, 05000000
Issue date: 01/12/1987
From: Corbin McNeil
Public Service Enterprise Group
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NLR-N87000, NUDOCS 8701290431
Download: ML20212L911 (1)


Text

=

SAFEGUARDS INFORMATION Pubhc Service Electric and Gas Company C rbin A. McNeill, Jr.

Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609 339-4800 Vice President -

Nuclear JAN 121987 NLR-N87000 Dr. Thomas E.

Murley Regional Administrator United States Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA 19406

Dear Dr. Murley:

DOCKET NOS. 50-272, 50-311, 50-354 SALEM AND HOPE CREEK GENERATING STATIONS CONSOLIDATION OF STATION PROTECTED AREAS My letter of September 30, 1986 outlined the project to consolidate Salem and Hope Creek Generating Stations within a single protected area, and provided a four item implementation schedule.

Although three items have been completed, due to unavailability of a long-lead component and adverse weather, we will be unable to totally complete the project as scheduled. is a status report and revised schedule.

It you should have any questions regarding this matter, please feel free to contact myself or P. A.

Moeller (609) 339-4400.