Forwards Addl Info Re Items 3.1.1,3.1.2,3.2.1,3.2.2 & 4.5.1 of Generic Ltr 83-28,per SER Open Item 5 & Miller 861231 Request on post-maint Testing
ML20212K762
Person / Time
Site: Vogtle  
Issue date: 01/15/1987
From: Bailey J
GEORGIA POWER CO.
To: Youngblood B
Office of Nuclear Reactor Regulation
References
GL-83-28, GN-1329, NUDOCS 8701290185
Download: ML20212K762 (3)


Text

e GeorCia Power Company Routa 2. Box 299A Waynisboro. Georgis 30830 Telephone 404 554-9961 404 724 8114 Southem Company Services, Inc.

Post Ot%e Box 2625 Birmingham, Alabama 35202

. Telephone 205 8704011 January 15, 1987 Director of Nuclear Reactor Regulation File: X7BC35 Attention: Mr. B. J. Youngblood Log:

GN-1329 PWR Project Directorate #4 Division of PWR Licensing A U. S. Nuclear Regulatory Comrission Washington, D.C.

20555 Ref: Miller to O'Reilly dated 12/31/86 NRC DOCKET NUMBER 50-424 AND 50-425 CONSTRUCTION PERMIT NUMBERS CPPR-108 AND CPPR-109 V0GTLE ELECTRIC GENERATING PLANT - UNITS 1 AND 2 SER OPEN ITEM 5: GENERIC LETTER 83-28 4

Dear Mr. Denton:

The referenced letter requested additional information on items 3.1.1, 3.1.2, 3.2.1, 3.2.2, and 4.5.1 of Generic Letter 83-28.

Attached for your staff's review is the VEGP response to this information request.

If your staff requires any additional information, please do not hesitate to contact me.

Sincerely, a

J. A. Bailey Project Licensing Manager DH:rbs Attachment xc:

R. E. Conway NRC Regional Administrator R. A. Thomas NRC Resident Inspector J. E. Joiner, Esquire D. Feig B. W. Churchill, Esquire R. A. McManus M. A. Miller L. T. Gucwa B. Jones, Esquire Vogtle Project File G. Bockhold, Jr.

8701290185 870115 PDR ADOCK 05000424 gg E

PDR ll1

s.

Item 3.1.1 Georgia Power Company (GPC) needs to submit an unambiguous statement confiming that post-maintenance testing of reactor trip system components is required and that the test procedures were reviewed to ensure that the testing ~ demonstrates that the equipment is capable of performing its intended safety function.

If not, a schedule should be submitted for when the review will'be completed.

RESPONSE

Maintenance of_ the reactor trip switchgear is controlled and processed via Maintenance Work Orders- (WO) procedures.

These-procedures establish controls _which require post-maintenance testing-of the reactor trip switchgear to prove its operability.

VEGP has developed test procedures which utilize the solid state protection system (SSPS) panel or the main control board trip - handswitch to demonstrate -operability of the reactor trip switchgear.

These test procedures will demonstrate the operability of the undervoltage (UV) trip attachment and shunt trip attachment.

Item 3.1.2 GPC indicated that when procedures are reviewed at Vogtle, part of the review criteria is to review the ' procedure against the applicable vendor manuals.

However, it is not quite clear from GPC's response whether this review entailed a ' check of vendor and engineering recommendations to ensure that appropriate test guidance is included in the test and maintenance procedures or the Technical Specifications.

If GPC's program for reviewing procedures does adequately verify that ' appropriate vendor and engineering test guidance have-been incorporated into these procedures, then GPC should provide ~a statement confirming that the requirements of Item 3.1.2 have been completed.

If not, GPC should submit a schedule for when this review will be completed.

RESPONSE

At_ VEGP, procedures are written referencing vendor manuals, if applicable.

When procedures are reviewed, part of the review criteria is to review the procedure against the applicable vendor manuals.

This review includes a review of the vendor and engineering recommendations to ensure' that appropriate test guidance is included in the test and maintenance procedures or Technical Specifications.

Vendor manuals are controlled at the site in accordance with Administrative Procedure 00108-C " Control, Approval and Use of Vendor Manuals and Revisions".

Item 3.2.1 GPC needs to submit a unambiguous statement confirming that post-maintenance testing is required for all other safety-related components and that a review of test and maintenance procedures and Technical Specifications was performed to assure that the testing demonstrates that the equipment is capable of performing its safety function.

If not, GPC should submit a schedule for when this review will be completed.

e 9

RESPONSE

Maintenance of safety-related systems / components is controlled and processed via Maintenance Work Orders (MW0's) procedures.

These procedures establish controls which require post-maintenance testing of safety-related systems / components to prove their operability.

A review of the test and maintenance procedures and the appropriate Technical Specification has been completed to assure that the testing demonstrates that the equipment is capable of performing its safety function.

Item 3.2.2 GPC needs to provide a statement confirming that its program for reviewing procedures did adequately verify that appropriate vendor and engineering test guidance were included in the test and maintenance procedures or the Technical Specifications.

If not, GPC should submit a schedule for when this review will be completed.

RESPONSE

At VEGP, procedures are written referencing vendor manuals, if applicable.

When procedures are reviewed, part of the review criteria is to review the procedure against the applicable vendor manuals.

This review includes a review of the vendor and engineering recommendations to ensure that appropriate test guidance is included in the test and maintenance procedure or Technical Specification.

Vendor manuals are controlled at the site in accordance with Administrative Procedure 00108-C " Control, Approval and Use of Vendor Manuals and Revisions.

Item 4.5.1 GPC needs to provide an unambiguous statement confirming that on-line functional testing of the reactor trip system, including the Reactor Trip Breakers (RTB), will be performed and that such testing will independently verify the operability of the RTB undervoltage and shunt trip features.

RESPONSE

VEGP has developed a Surveillance Procedure which verifies the capability of the Undervoltage and Shunt trip features to independently trip the Reactor Trip Breakers each month.

Each train is tested a least once every 62 days on a staggered test basis.

A Westinghouse Automatic Shunt Trip Panel was added to the Reactor Trip Switchgear Cabinets and provides the capability j

to independently test the Undervoltage and Shunt Trip devices as follows:

Undervoltage trip - the Shunt trip feature is blocked using a shunt trip block pushbutton and the breaker is tripped from the SSPS test panel.

UV coil voltage is verified at zero and breaker verified open proving trip through UV trip device only.

Shunt Trip the automatic shunt trip pushbutton is depressed, UV coil voltage is verified to be normal and breaker verified open proving trip through shunt trip device only.