Notice of Violation from Insp on 870106-0202
ML20212J392
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 03/02/1987
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20212J368 List:
References
50-247-87-01, 50-247-87-1, NUDOCS 8703090018
Download: ML20212J392 (1)


Text

{{#Wiki_filter:.. APPENDIX A NOTICE OF VIOLATION Consolidated Edison Company Docket No. 50-247 Indian Point Unit 2 License No. DPR-26 As a result of the inspection performed from January 6 to February 2, 1987, and in accordance with the General Statement of Policy and Procedure for NRC Enforcement Actions, 10 CFR Part 2, Appendix C (Enforcement Policy 1986), the following violation was identified: A. 10 CFR 50, Appendix B, Criterion XI _ requires, in part, that a test program be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily is identi-fied and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. Test results shall be documented and evaluated to assure that test requirements have been satisfied. Technical Specification 6.8.1.a requires, in part, that the requirements and recommendations of Section 5.1 and 5.3 of ANSI N18.7-1972 shall be established, implemented, and maintained. Section 5.3.5 (1) of ANSI N18.7-1972 states, in part, instructions shall be included, or referenced, for returning equipment to its normal operating status. Operating personnel shall place the equipment in operation and verify and document its functional acceptability. Contrary to the above, as of January 29, 1987, no post-maintenance (modification) test was performed that verified and documented the functional acceptability of differential pressure instruments FIC 1136 and DPC 1134S in the Emergency Diesel Generator Water System. The instruments were relocated during the 1986 refueling outage per Modifi-cation 85-20836-02. This is a Severity Level IV Violation (Supplement II). Pursuant to the provisions of 10 CFR 2.201, Consolidated Edison Company of New York, Inc., is hereby required to submit to this office within thirty days of i the date of the letter which transmitted this Notice, a written statement or -{ explanation in reply, including: (1) the corrective steps which have been taken 1 and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time.

                               ~

8703090018 870302 {DR ADOCK 05000247 PDR l 0FFICIAL RECORD COPY IR IP2 87 0003.0.0 02/25/87 L}}