Summary of 861104 Meeting W/Util in Bethesda,Md to Discuss Units 1 & 2 Licensing Activities.Principal Topics Included Unit 2 Outage Status,Unit 1 Schedule & Plans for Next Outage.List of Attendees Encl
ML20212H627
Person / Time
Site: Hatch  
Issue date: 01/21/1987
From: Rivenbark G
Office of Nuclear Reactor Regulation
To: Muller D
Office of Nuclear Reactor Regulation
References
NUDOCS 8701270389
Download: ML20212H627 (4)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _. _ - _ _ _ _

January 21, 1987 Dockets Nos. 50-321/366 DISTRIBUTION Docket File NRC PDR/L PDR MEMORANDUM FOR: Daniel R. Muller, Director PD#2 Memo l

BWR Project Directorate #2 OGC-Bethesda Division of BWR Licensing DRMuller/GRivenbark EJordan/BGrimes FROM:

George Rivenbark, Project Manager ACRS (10)

BWR Project Directorate #2 NRC Participants i

Division of BWR Licensing

SUBJECT:

SUMMARY

OF MEETING WITH GEORGIA POWER COMPANY, HATCH UNITS 1 AND 2 A meeting with representatives of Georgia Power Company (GPC) and personnel from the NRC was held at the NRC's offices in Bethesda, Maryland on November 4, 1986.

It was the sixth, of a series of quarterly meetings that GPC and the NRC have agreed to hold to discuss Hatch Uni: 1 and 2 licensing activities.

Principal topics discussed were: a) the Hatch Unit 2 outage status, b) the Hatch Unit I schedule and plans for its next outage, c) the status of NRC review of GPC requests for amendments and other submittals, d) the status of GPC commitments and responses to NRC requests, e) the status of the Hatch Technical Specification improvemant program, f))the status of implementation of emergency operation facility requirements, g the status of GPC's requested code interpretation of hydrostatic testing requirements, h) the Hatch procedure upgrade program and i) a GPC activity directed at clarifying Appendix J valve test requirements. A list of meeting attendees is enclosed.

GPC stated that Unit 2, currently in a maintenance and refueling outage is 12 days behind schedule.

(November 9,1986 is the original completion schedule) The next Unit I refueling outage is scheduled for March or April 1987. The outage is scheduled for an 8 week duration and will include and inservice inspection of welds in addition to refueling. GPC stated that industry is looking for a policy statement or criteria from the NRC concerning i

Technical Specification Improvements. GPC would expect to submit its improved Technical Specifications in June or July 1987, and implement them about 9 months af ter approval. GPC says its cost of implementation of these improved Technical Specifications will be about 5 million dollars.

1 hed I

. GPC expects to submit its valve testing paper in mid 1987 or later. GPC stated is Technical Support Center, Operations Support Center and Emergency Operations Facility are complete.

It will notify the NRC of this completion by letter. GPC agreed to provide a special briefing on its procedure upgrade program in the near future.

M99? Syd by George' Rivenbark, Project Manager BWR Project Directorate #2 Division of BWR Licensing

Enclosures:

As stated cc w/ enclosures:

See next page DBL 2

DB Af GRiv nbark/cd Dit or

) / 0 /87

/ /2/ /87 9

0FFICIAL RECORD COPY

Mr. J. P. O'Reilly

.Edwin I. Hatch Nuclear Plant, Georgia Power Company Units Nos. I and 2 f.

I g

cc:

Bruce W. Chruchill, Esquire Shaw, Pittman, Potts & Trowbridge 2300 N Street, N.W.

Washington, D.C.

20037 i

Mr. L. T. Gucwa Engineering Department Georgia Power Company Post Office Box 4545 Atlanta, Georgia 30302 Mr. H. C. Nix, Jr., General Manager Edwin I. Hatch Nuclear Plant Georgia Power Company Post Office Box 442 Baxley, Georgia 31513 Mr. Louis B. Long Southern Company Services, Inc.

Post Office Box 2625 Birmingham, Alabama 35202 Resident inspector U.S. Nuclear Regulatory Commission Routi 1. Post Office Box 279 Daxley, Georgia 31513 Regional Administrator, Region !!

U.S. Nuclear Regulatory Commission, 101 Marietta Street, Suite 2900 Atlanta, Georgia 30303 j

Mr. Charles H. Badger Office of Planning and Budget i

Room 610 270 Washington Street, S.W.

Atlanta, Georgia 30334 f

Mr. J. Leonard Ledbetter, Commissioner Department of Natural Resources 270 Washington Street, N.W.

Atlanta, Georgia 30334 Chairman Appling County Connissioners County Courthouse Baxley, Georgia 31513 r

i

'I

__.._,-__.-,---___.,....~._.,_-__,._m_,.

_-m..

~

ATTENDANCE LIST NRC/GPC QUARTERLY MEETING ON HATCH NbVEMBER4,1986 NAME ORGANIZATION l

G. Rivenbark NRC/NRR D. Muller NRC/NRR J. Heidt GPC R. Baker GPC L. Gucwa GPC l

1 1

6 l

I i

l l

l l

t

(

-