Monthly Operating Rept for Nov 1986
ML20211Q068
Person / Time
Site: Seabrook 
Issue date: 11/30/1986
From: Couture R, George Thomas
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
SBN-1253, NUDOCS 8703030009
Download: ML20211Q068 (6)


Text

.

.di OPERATING DATA REPORT DOCKET NO.

50-443 DATE 12/05/86 COHPLETED BY R. Couture TELEPHONE (603) 474-9521 (Ext. 4077)

OPERATING STATUS 1.

Unit Name:

Seabrook Station Unit 1 2.

Reporting Period:

November 1986 3.

Licensed Thermal Power (MWt):

3411 4.

Nameplate Rating (Gross MWe):

1197 5.

Design Electrical Rating (Net MWe):

1148 6.

Maximum Dependable Capacity (Gross MWe):

1197 (Initial design value) 7.

Maximum Dependable Capacity (Net MWe):

1148 (Initial design value) 8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

Not Applicable 9.

Power Level To Which Restricted, If Any (Net MWe):

Zero power

10. Reasons For Restrictions, If Any:

License issued on 10/17/86 is a zero power license which allows fuel loading and performance of non-nuclear testing.

This Month Y r. - to-Da te Cumulative

11. Hours In Reporting Period 720.0 1081.0 1081.0
12. Number Of Hours Reactor Was Critical 0.0 0.0 0.0
13. Reactor Reserve ' Shutdown flours 0.0 0.0 0.0
14. Hours Generator On-Line 0.0 0.0 0.0
15. Unit Reserve Shutdown llours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 0 0

0

17. Gross Elec. Energy Generated (MWH) 0 0

0

18. Net Electrical Energy Generated (MWH) 0 0

0

19. Unit Service Factor 0.0 0.0 0.0
20. Unit Availability Factor 0.0 0.0 0.0
21. Unit capacity Factor (Using MDC Net) 0.0 0.0 0.0
22. Unit Capacity Factor (Using DER Net) 0.0 0.0 0.0
23. Unit Forced Ourage Rate 0.0 0.0 0.0
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Not Scheduled

25. If Shut Down At End Of Report Period, Estimated Date Of Startup: Not Applicable
26. Units In Test Status (Prior to Commercial Operation):

Forecas t Ac hieved INITIAL CRITICALITY

__1987 Not Applicable INITIAL ELECTRICITY 1987 Not Applicable COMMERCIAL OPERATION 1987 Not Applicable

\\\\

0703030009 061130 PDR ADOCK 05000443 p

PDR i

.m_.

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-443 UNIT Seabrook 1 DATE 12/05/86 COMPLETED BY R. Couture TELEPHONE (603) 474-9521 (Ext. 4077)

MONTH NOVEMBER, 1986 DAY AVERAGE DAILY POWER LEVEL DAY AVERACE DAILY POWER LEVEL (MWe-Ne t)

(MWe-Ne t) i 1

0 16 0

2 0

17 0

3 0

18 0

4 0

19 0

5 0

20 0

6 0

21 0

2 7

0 22 0

8 0

23 0

9 0

24 0

}

10 0

25 0

l 11 0

26 0

j 12 0

27 0

13 0

28 0

14 0

29 0

15 0

30 0

4 INSTRUCTIONS l

On this format, list the average daily unit power level in MWe-Net for each day in tle reporting month.

Compute to the nearest w}nle megawatt.

i t

DOCKET NO.

50-443 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Seabrook 1

'j DATE 12/05/86 I

COMPLETED BY R. Couture REPORT ENTH NOVEMBER, 1986 TELEPHONE (603) 474-9521 (Ext. 4077) l Duration Reason 2 Method of Licensee Cause & Corrective 1

No. Date Type (Hours)

Shutting Event Action to Down Reactor 3 Report #

Prevent Recurrence

~

NO ENTRIES FOR THIS ENTH I

2 3

F:

Forced Reason:

Method:

S: Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Re fueling 3-Automatic Scram D-Regulatory Restriction 4-Continued from E-Operator Training &. License Examination

. previous month F-Administrative 5-Power Reduction G-Operational Error (Explain)

(Duration = 0)

H-Other (Explain) 9-Other (Explain)

Docket No.

50-443 Dato 12/05/86 Unit N;me Serbrook 1 Completed By R. Couture Te lephone (603) 474-9521 (Ext. 4077)

CORRECTIVE MAINTENANCE

SUMMARY

FOR SAFETY REIATED EQUIPMENT Page 1 of 1 REPORT MONTH NOV EMBER, 1986 DATE SYSTEM COMPONENT MAINTENANCE ACTION 11/05/86 Main Steam MS-PY-3002-5 Torqued valve seats and replaced gaskets Solenoid valve control-to correct air leakage.

ling B SG Atmosp1wric Steam Dump Valve.

I1/05/86 Nitrogen Gas NG-FV-4610 Repaired defective solenoid operator.

Solenoid operated containment isola-tion valve.

11/10/86 Service Water SW-V-140 Dried out and relubricated motor Motor operated cooling operator to correct electrical ground.

tower Train A basin valve.

11/18/86 Solid State Train B time delay Adjusted out-of-tolerance time delay Protection relay controlling relay.

System safety injection Manual Reset capability.

Docke t No.

50-443' Date:

12/05/86 Completed By:

R. Couture Telephone:

(603) 474-9521-(Ext. 4077)

REFUELING INFORMATION REQUEST

1. Name of facility:

Seabrook Unit 1

2. Scheduled date for next refueling shutdown: Not Scheduled
3. Scheduled date for restart following refueling: Not Scheduled
4. Will refueling or resumption of operation thereaf ter require a technical specification change or other license amendment?

Unknown at this time.

5. Scheduled date(s) for submitting licensing action and supporting informa tion:

Not Applicable

6. Important licensing considerations associated with refueling, e.g.,

new or dif ferent fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

None

7. The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:

(a)

In Core:

193 (b) 0

8. The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

Present licensed capacity:

1236 i

No increase in storage capacity requested or planned.

9. The projected date of the lar' refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:

Licensed capacity of 1236 fuel assemblies based on sixteen refuelings and full core of fload capability.

The current licensed capacity is adequate until at leas t the year 2007.

8 George S. Thomas UI vice PropdwW Nuclear Produckm PLesc Service of New Hampshire New Hampshire Yankee Division December 8, 1986 SBN-1253 T.F. B.7.1.2 United States Nuclear Regulatory Commission Washington, D.C.

20555 Attention: Director, Office of Resource Management

Reference:

(a) Facility Operating License No. NPF-56, Docket No. 50-443 Subj ect: Monthly Operating Report

Dear Sir:

In accordance with Technical Specification Section 6.8 1.5, enclo' sed please find Monthly Operating Report 86-11 covering the operation and shutdown experience relating to Seabrook Station Unit 1.

Very truly yours, eo

. Thomas Enclosure cc: Regional Administrator U. S. Nuclear Regulatory Commission - Region 1 631 Park Avenue King of Prussia, PA 19406

\\

P.O. Box 300. Seabrook, NH 03874. Telephone (603) 474 9574 j