Informs That Completion Date for Supplemental Response to Violations Noted in Insp Repts 50-373/96-11 & 50-374/96-11 Has Been Extended to 60 Days Following Ack of Review of Data from GE
ML20211P755
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 10/13/1997
From: Subalusky W
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
50-373-96-11, 50-374-96-11, NUDOCS 9710210199
Download: ML20211P755 (2)


Text

.

Q>mmonw calth 141mn Compam IaNiile Generating Marion 2(01 Nonh 21st Road Marseilles, 11.61341-9757 Tel 815-3574761 October 13,1997 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555

Subject:

Supplemental Response to NRC Inspection Report No. 50-373/96011; 50-374/96011 (DRP)

LaSalle County Station, Units 1 and 2 Facility Operating License NPF 11 and NPF-18 NRC Docket Nos. 50-373 and 50-374

Reference:

W. T. Subalusky Letter to U.S. NRC Document Control Desk dated July 3,1997, Transmitting Supplementa; -

Response to inspection Report 373/374 96011 The referenced letter provided a status of our response to the subject inspection report, and provided a resolution date of October 15,1997, foi violation 373/374-96011-18. This violation identified that the LaSalle Updated Final Safety Analysis Report (UFSAR) had not been updated to i

reflect the change in initial and maximum suppression pool temperatures approved by License Amendments 67 (Unit 1) and 49 (Unit 2), issued t

July 1989.

The October 15,1997, completion date was contingent on General Electric (GE) performing a review of their design configuration methods to ensure that margins of safety are not affected by accumulating affects of multiple parameter changes over a period of tinis. The schedule has been impacted by a Comed imposed Stop Work Order (SWO) on GE, and a dats for lifting g

the SWO has not yet been established. Therefore, the completion date for

\\

violation 373/374-96011-18 has been extended to 60 days following receipt

/

of the review data from GE.

/ / g,

\\

9710210199 971013 11,1 !

i A Unicom Compm)

f h

~

If there are any questions or comments concoming this letter, please refer them to me at (815) 357-6761, extension 3600.

Respectfully, _

pn i

W. T. Subalusky Site Vice President LaSalle County Station cc:

A. B. Beach, NRC Region ill Administrator M. P. Huber, NRC Senior Resident inspector - LaSalle D. M. Skay, Project Manager - NRR - LaSalle F. NIziolek, Office of Nuclear Facility Safety - lDNS I