Submits Supplemental Info Re 851217 Request for Amends to Licenses DPR-53 & DPR-69,providing Increased Flexibility for Unit 1 Cycle 8 & Operation W/Respect to Acceptable Number of Failed in-core Detector Strings
ML20211N479
Person / Time
Site: Calvert Cliffs  
Issue date: 12/05/1986
From: Mihalcik J
BALTIMORE GAS & ELECTRIC CO.
To: Thadani A
Office of Nuclear Reactor Regulation
References
NUDOCS 8612180232
Download: ML20211N479 (2)


Text

.. _,..

BALTIMORE OAS AND ELECTRIC CHARLES CENTER. P.O. BOX 1475 BALTIMORE, MARYLAND 21203 NUCLEAR ENGINEERING SERVICES DEPARTMENT CALVERT CUFFS NUCLEAR POWER PLANT LUSOY, MARYLAND 20657 December 5,1986 U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D. C. 20555 ATTENTION:

Mr. Ashok C. Thadani, Director PWR Project Directorate #8 Division of PWR Licensing-B

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 SupplementalInformation for Request for Amend nt

REFERENCES:

(a)

Letter from Mr. A. E. Lundvall, Jr. (BG& ), to Mr. E. 3. Butcher (NRC), dated December 17,1985 (b)

Letter from Mr. M. E. Bowman (BG&E), to Mr. D. H. Jaffe (NRC),

dated January 16,1986, Supplemental Information (c)

Letter from Mr. D. H. Jaffe (NRC), to Mr. 3. A. Tiernan (BG&E),

dated March 31,1986, License Amendment 116 Gentlemen:

References (a) and (b) proposed a change to our Technical Specifications to provide increased flexibility for Unit 1 Cycle 8 operation with respect to the acceptable number of failed incore detector strings. An unexpectedly large number of detectors were found f ailed during the Unit 1 Cycle 8 startup, necessitating this change to Technical Specification 3/4 3.3.2.

The NRC approved this request per Reference (c), issuing a Technical Specification that was valid only for Unit 1 Cycle 8.

A review of Technical Specifications during the current refueling outage, prior to Unit 1 Cycle 9 startup, identified the fact that Technical Specification 3/4 3.3.2 was technically only valid for Unit 1 Cycle 8, thus leaving us without an OPERABILITY requirement for Incore Detectors. Discussions with your staff have resulted in the following actions to correct this discrepancy:

1.

BG&E commits to the operation of Unit I under the " older", more restrictive Technical Specification 3/4 3.3.2 which existed prior to Reference (c). As such, we have replaced Unit 1 Technical Specification page 3/4 3-29, Amendment 116, with page 3/4 3-29, Amendment 34.

Bo,\\

8612180232 861205 I

PDR ADOCK 05000317 P

PDR

r e.....

Mr. Ashok C. Thadani December 5,1986 Page 2 2.

We will submit a License Amendment change request which reinstates the requirements as stated in Amendment 34 for Unit I page 3/4 3-29.

We currently expect to submit this License Amendment change by January 16,1987.

Should you have further questions regarding this reply, I can be reached at (301) 260-4780.

Very truly yours, wLLL i 3. A. Mihalcik Principal Engineer Fuel Cycle Management 3AM/BEH/dtm cc:

D. A. Brune, Esquire

3. E. Silberg, Esquire S. A. McNeil, NRC T. Foley, NRC T. Magette, DNR