Ameren MISSOIJRI Callaway Plant July 28, 2020 ULNRC-06594 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-000 1 40 CFR 190 10 CFR 72.44(d)(3)

Ladies and Gentlemen:

DOCKET NUMBERS 50-483 AND 72-1045 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.

RENEWED FACILITY OPERATING LICENSE NPF-30 SUPPLEMENT TO 2019 ANNUAL RADIOACTIVE EFFLUENT RELEASE REPORT

1) Ameren Missouri letter ULNRC-06577, 2019 Annual Radioactive Effluent Release Report, dated April 30, 2020 (AccessionNo. ML19120A271).

Per the letter identified as Reference 1, Union Electric Company (Ameren Missouri) submitted the 2019 Annual Radioactive Effluent Release Report (ARERR) for the Callaway Plant. However, as noted in Reference 1, due to extenuating circumstances, several data tables within the report were noted as being incomplete. It was stated that the information needed to complete the tables would be submitted within 90 days, in accordance with the guidance of Regulatory Guide 1.2 1 (revision 2). The tables have now been completed and incorporated into the report. The completed ARERR is therefore being provided per this submittal (as enclosed), which supersedes the previously submitted report.

The ARERR is submitted in accordance with Section 5.6.3 ofthe Callaway Plant Technical Specifications and Section 5. 1.c of Appendix A to the HI-STORM UMAX Certificate of Compliance.

This letter does not contain new commitments.

8315 Country Road 459 Steedman, MO 65077 AmerenMissouri.com

ULNRC-06594 July 28, 2020 Page 2 Ifthere are any questions, please contact Johann S. Geyer at (314) 225-1589.

Sincerely 4

Fred Bianco Senior Director, Nuclear Operations Enclosure

ULNRC-06594 July 28, 2020 Page 3 cc:

Mr. Scott A. Morris Regional Administrator U. S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Mahesh Chawla Project Manager, Callaway Plant Office ofNuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop O8B1A Washington, DC 20555-0001

ULNRC-06594 July 28, 2020 Page 4 Index and send hardcopy to QA File A160.0761 Hardcopy:

Certrec Corporation 6100 Western Place, Suite 1050 FortWorth,TX 76107 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)

Electronic distribution for the following can be made via Responses and Reports ULNRC Distribution:

F. M. Diya T. E. Herrmann B. L. Cox F. J. Bianco S. P. Banker J. S. Geyer R. C. Wink T. B. Elwood F. J. Beckfield C. C. Graham M. Kohlbusch C. J. Giesmann (Ameren Missouri Senior Manager Environmental Services)

NSRB Secretary Ms. Melissa Friel, REP Manager (SEMA)

STARS Regulatory Affairs Mr. Jay Silberg (Pillsbury Winthrop Shaw Pittman LLP)

Mr. Chris Wieberg (DNR)

Mr. Steve Feeler (DNR)

Ms. Katie Jo Wheeler (DNR)