Text
_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _
GPU Nuclear Corporation
- NggIgf Post Office Box 480 Route 441 South Middletown, Pennsylvania 17057 0191 717 944 7621 TELEX 84 2386 Writer's Direct Dial Number:
February 18, 1987 5211-87-2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk
~
Washington, DC 20555
Dear Sir:
Three Mile Island Nuclear Station Unit 1 (TMI-1)
)
Operating License No. DPR-50 Docket No. 50-289 Anticipated Transient Without SCRAM (ATWS) Implementation Your letter of October 7,1986 on Schedule for Anticipated Transient Without SCRAM (ATWS) for THI-l provided approval of THI-1 to complete ATWS i
l modification requirements (10 CFR 50.62) by the completion of the Cycle 8 refueling outage (8R). GPUN is a participant in the B&W Owners Group l
which has identified a preferred approach for compliance with NRC requirements. The B&W Owners Group submitted a description of this technical approach on October 8,1985. The Owners Group is waiting for approval (Safety Evaluation Report) of this approach. We understand that there have been delays in the issuance of the SER. GPUN does not intend to commence engineering and design work associated with ATWS until technical approval of the approach is received and reviewed by the B&W Owners Group. This has been previously communicated to your staff.
In order to complete this work by the end of the 8R Outage GPUN needs lead time for engineering, procurement and construction work.
GPUN will need issuance of the Safety Evaluation Report by June 1,1987 to ensure sufficient lead time exists.
If the SER is not issued by June 1,1987 then TMI will be unable to complete ATWS requirements by the end of the 8R outage in a manner consistent with GPUN typical standard project duration time frames. This letter can be considered a request for schedule change should the June 1987 SER issuance not occur. Therefore a response is not requested unless this SER is not issued by the date needed.
0702260258 870218 PDR ADOCK 05000289 PDR P
ld GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation
~
5211-87-2015 February 18, 1987 This letter is written to give you early notification of our needs and limitations in order to facilitate mutual prioritization and scheduling.
H. D. Hukill Vice President & Director, TMI-l HDH:RJM:jh cc: