h Commonwealth Edison
- N s(
. _ _. / 72 West Adams Street, Chicago, Illinois o
\\
7 Address Rrply to: Post Office Box 767
~~
V Chicago, Illinois 60690 0767 October 2, 1986 Mr. James G. Keppler Regional Administrator Region III U.S. Nuclear Regulatory Commission
- 199 Roosevelt Road Glen Ellyn, IL 60137
Subject:
Braidwood Station Units 1 and 2 Supplemental Response to Inspection Report 50-456/86-021 and 50-457/86-019 NRC Docket Nos. 50-456 and 50-457
References:
(a) W.D. Shafer letter to Cordell Reed dated July 22, 1986 (b) D.L. Farrar letter to James G. Keppler dated August 21,1986
Dear Mr. Keppler:
This letter is in response to the follow-up inspection of the subject inspection documented in Reference (a) conducted by Messrs. T.J. Ploski and team on September 15 through 19, 1986 of Emergency Preparedness activities at Braidwood Station. During this follow-up inspection, Mr. T.J. Ploski suggested that the Commonwealth Edison Company response to Open Item #3, as stated in Reference (b), be clarified. The Commonwealth Edison Company response to this concern is provided in the enclosure.
If you have any further questions on this matter, please direct them to this office.
ery truly yours,
- /
8610150145 861002
(
PDR ADOCK 05000456 G
PDR D.L. Farrar Director of Nuclear Licensing DLF/pav Enclosure
/
cc: NRC Resident Inspector - Braidwood g
'00T7 198g 16381
~
'N COOGIDHWEALTH EDISON COMPANY SUPPLEMENTAL RESPONSE IR 456/86-021 and 457/86-019
.Open Item 83 - (456/86-021-03 and 457/86-019-03)
Prior to Fuel Load, the applicant must re-evaluate the Shift Foreman's multiple emergency assignments to ensure manning requirements are met t-during fires and/or other GSEP events which may warrant OSC activation.
(456/86021-03; 457/86019-03) 06/21/86 Response Braidwood Station has assigned three (3) Shift Foremen to each shift.
This helps ensure manning requirements are met in the event of an i
emergency. The Shift Foremen from the unaffected unit are assigned Fire Chief and OSC Director responsibilities.
If a GSEP condition were to occur and a Shift Foreman were unavailable to act as OSC Director, the Rad /Chen Foreman as OSC Supervisor would step in and fulfill the OSC Director responsibilities in accordance with the implementing procedures. All Rad /Chen Foremen have been trained to be OSC Directors in the event the Shift Foreman is unable to fill the position.
Further, there are three fire protection personnel who could be available j
to relieve the shift Foremen at the fire scene. At least one Radwaste Foreman is also available to assist, where needed, in an emergency. This would free the shift Foreman of the inplant duties and allow him to assume OSC responsibilities.
Lastly, if the event were to occur during off-hours, staff augmentation includes Rad / Chem support personnel, 2 at the Alert, 4 at Site or General meergency. This list includes all the Rad /Chen Foremen. Upon their arrival in the OSC, one support person is assigned to assist in the OSC.
Should the Shift Foreman be unavailable, and the on-shift Rad / Chem Foreman be the OSC Director, the support person fulfills the OSC Supervisor responsibilities, thereby ensuring adequate OSC supervision.
Although the Braidwood Technical Specifications and FSAR requirements state only one Shift Foreman, this is the minimum legal manning requirement for operating the unit. To restate, it is the intent of Braidwood to staff three Shift Foremen on each shift to ensure adequate coverage in an emergency.
l 1
i No further actions are warranted at this time. This item is considered complete.
16381 i
1
.N s
w Supplemental Response The scope of the." intent" mentioned in our initial response to ensure adequate Shif t Foreman coverage in an emergency is a formal comunitment'as defined by Braidwood Emergency / Implementing Procedures; SwZP 090-01, Revision 0, " Acting Station Director Implementing Procedure", Bw3P 100-10, Revision 3, " Operational Support Center (OSC) Director
)
Implementing Procedure," and BWZP 300-7, Revision 0, " Fire Fighting".
Within these approved procedures, the emergency duties assigned to the Shift Foreman are defined as set forth in our initial response. If for any reason the Shift Foreman is unable to perform one or more of these assigned duties, an alternate responsible person is designated by the procedure.to assume each of tne Shift Foreman's duties.
16381