Responds to NRC Ltr Re Violations Noted in Insp Rept 50-416/97-12.Corrective Actions:Promptly Removed Ladder Upon Notification of non-conformance & Generated Deficiency Document to Address Issue
ML20210V124
Person / Time
Site: Grand Gulf 
Issue date: 09/16/1997
From: Hagan J
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
50-416-97-12, GNRO-97-00088, GNRO-97-88, NUDOCS 9709230063
Download: ML20210V124 (3)


Text

-

Ente gy rations, inc.

h Port Gitaon MS 39150 LJ/

Tel 001437 C408 Fax 601437 2795 Joseph J. Hagan W+ hs, oent Ofeatepis September 16, 1997 0'"'d os" "- Sa' U.S. Nuclear Regulatory Commission Mall Station P137 Washington, D.C. 20555 Attention:

Document Control Desk

Subject:

Grand Gulf Nuclear Station L nit 1 Docket No. 50-416 License No. NPF 29 Reply To A Notice Of Violation Failure to Ensure Safe Handling of Loose items inside the Plant Report No. 50-416/9712 (GNRl-97/OO138), dated 08/19/97 GNRO 97/00088 Gentlemen:

Entergy Operations, Inc. hereby submits the Reply to Notice of Violation 50-410/97 12 01.

Yours truly,

(

" h J/A a.

JJH/TMC attachment Response to Notice of Violation 50-416/97 12 01 cc:

Ms. J. L. Dixon Herrity, GGNS Senior Assident (w/a)

Mr. L. J. Smith (Wise Carter) (wla) h Mr. N. S. Reynolds (w/a)

. Ul Mr. H. L. Thomas (w/o)

Mr. J. W. Yelverton (w/a)

Mr. Ellis W. Merschof f (w/a)

Regional Administrator U.S. Nuclear Regulatory Commission l

l Region IV 611 Ryan Plaza Drive Suite 400 Arlington, TX 76011 Mr. J. N. Donohew, Project Manager (w/2)

Office of Nuclear Reactor Rcoulation U.S. Nuclear Regulatory Commission Mail Stop 13H3 Washington, D.C. 20555 IlltEEjiHJtslll 9709230063 970916 PDR ADOCK 05000416 0

PDR

.s

Attachment I to CNRO 97/00088 Page1 Cf 2 Notice of Violation 9712 01 10 CFR Part $0, Appendix B, Criterion V, states, in part, that activities affecting quality shall be prescribed by documented procedures and drawings of a type appropriate to the circumstances and shall be accomplished in accordance with these procedures and drawings.

Procedure 01 S-07-43," Safe llandling of Loose items inside the Plant," Revision

1. Paragraph 5.11, states that equipment; piping; conduit; cable trays; instrumentation; heating, ventilation, and air conditioning; and their associated supports are not considered structural elements and cannot be used for securing loose items without engineering approval.

Contrary to the above, on June 30,1997, the inspectors identified an extension ladder supported on a safety related cable tray and no engineering evaluation had been completed.

This is a Severity Level IV violation (Supplement 1)(50-416/9712 01).

I.

Admission or Denial of the Alleged Violation Entergy Operations, Inc. admits to this violation.

II.

The Reason for the Violation,if Admitted The cause of the violation was plant personnel's insufficient awareness of the impact on safety / reliability when utilizing a ladder. Contrary to procedure, plant personnel assumed an evaluation was only required if the ladder was left in place unattended vice the evaluation required before placing the ladder against a safety related cable run.

111.

Imnsediate Corrective Steps Which llave Hecy,Taken and Results Achieved The ladder was promptly removed upon notification of non-conforniance.

A deficiency document was generated to address the issue.

IV.

Corrective Steps Taken to Pretiude Further Violations Discussed Standard GGNS-CS-17 with maintenance personnel and the importance of procedure adherence in regard to the standard, Tasks associated with this event have had a note added to the cover sheet stating that e

a loose items evaluation is required when performing task.

Attachmsnt I to GNRO 97/00088 Pega 2 of 2 V.

Date When Full Compliance Was Achieved The above actions were cornpleted by August 15,1997.