MONTHYEARML20207A7991999-02-25025 February 1999 Forwards non-proprietary & Proprietary Documentation Providing Resolution to Four Remaining Transtor Storage Cask Issues.Proprietary Encls Withheld Project stage: Other ML20216D6611999-07-23023 July 1999 Submits Summary of Proprietary Submittals for Transtor Part 71 & Part 72 & Trojan ISFSI Applications Project stage: Other ML20210U0361999-08-13013 August 1999 Confirms Understanding That Due to Commitments Missed by Bnfl Fuel Solutions (Bfs),Us NRC Must Modify Review Schedules for Transtor Storage Cask & Shipping Cask Applications Project stage: Other 1999-07-23
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20212D3431999-09-14014 September 1999 Informs That Analyses of Transtor Baskets to Successful Results of Impact Limiter Tests Are Ongoing & Bnfl Fuel Solutions Will Not Issue Results of Drop Test by End of Sept 1999.NRC Will Be Informed of Rept Submittal Date ML20211P8351999-09-0303 September 1999 Requests Withdrawal of 990807 Responses to NRC Questions Re Transtor Shipping Cask Sys.Resubmittal,Including Necessary Corrections of responses,non-proprietary & Proprietary SAR Drawings & Calculations,Encl.Proprietary Encls Withheld ML20210U0361999-08-13013 August 1999 Confirms Understanding That Due to Commitments Missed by Bnfl Fuel Solutions (Bfs),Us NRC Must Modify Review Schedules for Transtor Storage Cask & Shipping Cask Applications ML20210S6921999-08-0606 August 1999 Informs That Rev of Transtor Part 71 Application to Incorporate Attributes of Transtor Basket & Internals Used at Trojan Has Been Postponed,As Discussed with T Kobetz.New Schedule Will Be Established at Later Date ML20210S6861999-08-0505 August 1999 Forwards Missing Page E-39 from Calculation BNFL1.10.06.16 & Last Page from Calculations Bnfl 1.10.06.50,1.10.06.68, 1.10.06.69 & 1.10.06.70,not Transmitted in 990212 Response to Rai.Intentionally Removed Pages as All Were Blank ML20216D6611999-07-23023 July 1999 Submits Summary of Proprietary Submittals for Transtor Part 71 & Part 72 & Trojan ISFSI Applications ML20209F7841999-07-0202 July 1999 Forwards redacted/non-proprietary & Proprietary Versions of Rev 3 of Transtor Impact Limiter Test Plan & Rev 0 of Calculation Bnfl 1.10.06.84, Impact Limiter Pretest Predictions,Corner & End Drops. Proprietary Encls Withheld ML20207A3421999-05-21021 May 1999 Discusses Schedules for Listed Transtor Part 71 Submittals, Per 990518 Meeting with NRC ML20204H8971999-03-22022 March 1999 Forwards Proprietary & redacted/non-proprietary Version of Rev 2 to IL-TP-001, Transtor Impact Limiter Test Plan, Which Addresses Testing Element of Validation of Analytical Model.Proprietary Version of Test Plan,Withheld ML20207A7991999-02-25025 February 1999 Forwards non-proprietary & Proprietary Documentation Providing Resolution to Four Remaining Transtor Storage Cask Issues.Proprietary Encls Withheld ML20198N7811998-12-30030 December 1998 Submits Revised Schedule for Completing re-assessment of Second NRC RAI for Transtor Shipping Cask Sys.Revised RAI Response Will Be Submitted by 990216 ML20198E9871998-12-21021 December 1998 Informs That NRC Staff Acks Delay & Understands Bnfl Fuel Solutions Will Submit Revised Schedule for Responding to Second Transtor Shipping Cask RAI No Later than 981231. Current Schedule Last Updated on 981030 ML20198E5951998-12-10010 December 1998 Submits Revised Schedule for Completion of Responses to NRC RAI Re Transtor Shipping Cask Sys ML20236T1271998-07-21021 July 1998 Requests That NRC Review of Transtor 10CFR71 License Application Be Rescheduled.Licensee Chooses to re-review Submitted SAR Revs for Content & Thoroughness of Responses, Given Recent Purchase of Sierra Nuclear Corp by Bnfl,Inc ML20202C1791998-02-0909 February 1998 Returns Responses to 970731 RAI-2 Re 960326 Application for Trojan Isfsi,Due to Overall Poor Quality.Proprietary Documents Are Being Returned Under Separate Cover as Required Affidavits Were Not Provided ML20203A8361997-12-0505 December 1997 Informs That Listed Documents Will Be Withheld from Public Disclosure,Per 10CFR2.790,as Requested by ML20212C3991997-10-15015 October 1997 Forwards Proprietary Rev 3 to BNFL1.10.06.02,rev 3 to BNFL1.10.06.01,rev 2 to BNFL1-10.06.60 & Rev 0 to IL-TP-001 Which Reflects Impact Limiter Mod Company Decided to Make After Consulting W/Aluminum Honeycomb Vendor ML20217K1901997-10-15015 October 1997 Forwards non-proprietary Replacement Pages for Rev 3 of Transtor Shipping Cask Sys Sar. Rev Incorporates Impact Limiter Mod Sierra Nuclear Corp Decided to Make After Consulting W/Aluminum Honeycomb Vendor ML20217J6301997-08-0505 August 1997 Forwards Page II of Corrected List of Active Pages to Be Inserted in Rev 2 to Transtor Shipping Cask Sar,Submitted on 970702 ML20149J3701997-07-24024 July 1997 Informs That Detailed Sys Component Drawings & Calculations That Support Info in Sierra Nuclear Corp Transtor Shipping Cask Sys Sar,Discussed in 970702 Affidavit,Will Be Withheld from Public Disclosure,Per 10CFR2.790 ML20149E1071997-07-14014 July 1997 Forwards Title Page for Rev 2 to Transtor Shipping Cask Sys Sar.Submittals Were Inadvertently Omitted from Nine Copies of SAR on 970702 ML20140F6501997-04-29029 April 1997 Responds to 970415 Request That Wj Sinclair & D Chancellor of Utah Attorney General Ofc Be Placed on Svc List of Docket 71-9268 (Sierra Nuclear Corp Application for Certificate of Transtor Shipping Cask & 72-1023 (Transtor Storage Cask) ML20138D2121997-03-24024 March 1997 Forwards RAI to Complete Review Re Transtor Shipping Cask Sys.Response Requested within 60 Days from Date of Ltr ML20134P3101996-11-20020 November 1996 Forwards Two Copies of Scientific Ecology Group Drawings for Fuel Debris Process Can & Fuel Debris Process Can Capsule ML20129D9911996-09-26026 September 1996 Approves Request to Withhold Info from Public Disclosure Re Transtor Shipping Cask Sys Safety Analysis Rept 1999-09-03
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20210U0361999-08-13013 August 1999 Confirms Understanding That Due to Commitments Missed by Bnfl Fuel Solutions (Bfs),Us NRC Must Modify Review Schedules for Transtor Storage Cask & Shipping Cask Applications ML20198E9871998-12-21021 December 1998 Informs That NRC Staff Acks Delay & Understands Bnfl Fuel Solutions Will Submit Revised Schedule for Responding to Second Transtor Shipping Cask RAI No Later than 981231. Current Schedule Last Updated on 981030 ML20202C1791998-02-0909 February 1998 Returns Responses to 970731 RAI-2 Re 960326 Application for Trojan Isfsi,Due to Overall Poor Quality.Proprietary Documents Are Being Returned Under Separate Cover as Required Affidavits Were Not Provided ML20203A8361997-12-0505 December 1997 Informs That Listed Documents Will Be Withheld from Public Disclosure,Per 10CFR2.790,as Requested by ML20149J3701997-07-24024 July 1997 Informs That Detailed Sys Component Drawings & Calculations That Support Info in Sierra Nuclear Corp Transtor Shipping Cask Sys Sar,Discussed in 970702 Affidavit,Will Be Withheld from Public Disclosure,Per 10CFR2.790 ML20140F6501997-04-29029 April 1997 Responds to 970415 Request That Wj Sinclair & D Chancellor of Utah Attorney General Ofc Be Placed on Svc List of Docket 71-9268 (Sierra Nuclear Corp Application for Certificate of Transtor Shipping Cask & 72-1023 (Transtor Storage Cask) ML20138D2121997-03-24024 March 1997 Forwards RAI to Complete Review Re Transtor Shipping Cask Sys.Response Requested within 60 Days from Date of Ltr ML20129D9911996-09-26026 September 1996 Approves Request to Withhold Info from Public Disclosure Re Transtor Shipping Cask Sys Safety Analysis Rept 1999-08-13
[Table view] |
Text
.
i o org g t UNITED STATES i NUCLEAR REGULATORY COMMISSION U , WASHINGTON, D.C. 20566 0001
- Md* b k ,,,,, +#[ August 13, 1999 Mr. Edward Fuller, President and Chief Executive Officer BNFL Fuel Solutions One Victor Square
- Scotts Valley, CA 95066
SUBJECT:
TRANSTOR STORAGE AND SHIPPING APPLICATIONS (TAC NOS. L22307 AND L22232)
Dear Mr. Fuller:
The purpose of this letter is to confirm your understanding that, due to commitments missed by BNFL Fuel Solutions (BFS), the U.S. Nuclear Regulatory Commission (NRC) must modify its review schedules for the TranStor Storage Cask and Shipping Cask applications.
On July 1,1999. BFS notified the NRC that it would not be able to meet certain commitments to supply information required by the staff to complete their review of the TranStor Storage and Shipping applications. BFS stated that the delay was required to allow it to commit sufficient resources to support Portland General Electric. On July 9,1999, BFS submitted revised dates for submitting the required information. At that time, the staff notified BFS that the revised dates would not support the NRC review schedule for those applications. On August 3,1999, BFS notified NRC in writing, that based on discussions with the staff, it understood that not providing the staff with the above mentioned information on the original schedule has adversely impacted the TranStor Storage and Shipping Cask review schedules.
In addition, BFS has not provided NRC with a completion date to resolve current issues involving the use of coatings on interior surfaces of the site-specific TranStor design cask to be utilized at Trojan Nuclear Plant. Closure of these issues is essential for the staff to assess the effects of any chemical, galvanic or other reaction between the shipping and storage cask components and contents of the general TranStor design. Therefore, the staff must also receive updates to the TranStor Storage and Shipping applications reflecting the resolution of the coatings issues.
BFS must also address other changes made to the Trojan specific TranStor design which relate to the generic TranStor design. Several design issues arose during the final months prior to issuing a 10 CFR Part 72 license to Portland General Electric. Examples of these changes include but are not limited to the hydrogen content of the neutron absorber materialin the Transfer Cask, descriptions of control components to be stored with spent fuel, and blockage of the Concrete Cask air inlets during cask movement operations. The staff expects BFS to review the final Trojan safety analysis report (SAR), the safety evaluation report and other l documents as applicable and incorporate changes as necessary into the generic TranStor design. As noted in the August 3,1999, letter, this includes technical specifications.
t
^~
U jh 9908190213 990813 PDR ADOCK 07109268 k
l L
r-E. Full,er The staff will notify you in writing of the new schedules once the above informadon, including all necessary updates to the SAR, have been received from BFS, As I discussed with Mike Lalor of your staff, we encourage BFS to schedule a meeting with NRC prior to submitting the updated licensing information. The meeting should be scheduled far enough in advance to allow BFS to update the licensing information based on the discussions at the meeting.
If you have any questions, please contact me at (301) 415-8538.
Sincerely, original /s/ by Timothy J. Kobetz, Project Manager Spent Fuel Licensing Section Licensing and Inspection Directorate Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards Docket Nos.: 71-9268,72-1023 cc: S. Mirsky, SAIC -
DISTRIBUTION:
Dockets NRC File Center PUBLIC NMSSr# SFPO rM MRoss-Lee WBrach WHodges EEaston SO'Connor PEng NJensen, OGC l STurk, OGC MDelhgatti MBailey ELeeds l 1