Text
e February 11, 1987 t-b Docket No. 50-184 Dr. R. S. Carter, Chief x
Reactor Radiation Division National Bureau of Standards U. S. Department of Commerce Washington, D. C.
20234
Dear Dr. Carter:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION We are continuing our review of your application, dated September 19, 1986, for a unique purpose exemption pursuant to 10 CFR 50.64(c)(1) for your reactor facility and find we require additional information.
Please provide a written l-response to the enclosed question no later than thirty days from the date of this letter.
Following receipt of this information we will continue our review.
i If you have any questions concerning this request, please contact me at (301) 492-8259.
I 1
The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
l
' Sincerely, l
original signed by John J. Dosa, Project Manager Standardization and Special Projects Directorate.
Division of PWR Licensing-B Office of Nuclear Recctor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page DISTRIBUTION:
IDettetc F11e..a TDorian, 0GC-BETH Local PDR NRC PDR PBSS Reading 8702180064 870211 PNoonan PDR ADOCK 05000184 JDosa P
an
.cw ch Be ow
/87 0 /*/ /87 02/g\\ /87 02/(/87
[
UNITED STATES o
E NUCLEAR REGULATORY COMMISSION o
f,.
f I'
wAsHaworow, o. c. zosas.
,/
February 11, 1987 Docket No.'50-184 Dr. R. S. Carter, Chief Reactor-Radiation Division National Bureau of Standards U. S. Department of Comerce Washington, D. C.
20234
Dear Dr. Carter:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION We are continuing our review of your application, dated September 19, 1986, for a unique purpose exemption pursuant to 10 CFR 50.64(c)(1) for your reactor facility and find we require additional information.
Please provide a written response to the enclosed question no later than thirty days from the date of this letter.
Following receipt of this information we will continue our review.
If you have any questions concerning this request, please contact me at (301) 492-8259.
The reporting and/or recordkeepir.g requirements contained in this letter 4
affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, l
ohn J. Dosa, Project Manager Standardization and Special Projects Directorate Division of PWR Licensing-B Office of Nuclear Reactor Regulation
Enclosure:
i l
As stated cc w/ enclosure:
See next page l
l l
l
~
ii I
National Bureau of Standards Docket No. 50-184 cc: Montgomery County Executive County Office Building Rockville, Maryland 20858 Director Department of State Planning 301 West Preston Street Baltimore, Maryland 21201 Director Department of Natural Resources Power Plant Siting Program Energy & Coastal Zone Administration Tawes State Office Building Annapolis, Maryland 21401
~
Mr. Tawfik Raby Reactor Supervisor Reactor Radiation Division National Bureau of Standards U.S. Department of Commerce Washington, D.C.
20234 Attorney General 1 South Calvert Street Baltimore, Maryland 21202 Mr. Thomas Magette - Administrator Nuclear Evaluation - Power Plant Siting Program Department of Natural Resources
~Tawes State Office Building Annapolis, Maryland 21401
o Lv i
Enclosure National Bureau of Standards Docket No. 50-184 Unique Purpose Exemption Request Request for Additional Information 10 CFR 550.64(b)(3) requires that any licensee granted a unique purpose exemption from the use of LEU fuel must use HEU fuel of enrichment as close to 20% as is available and acceptable to the Commission.
If fuel of any enrichment from 20% to 93% were available and you were granted a unique purpose exemption, what would be the lowest enrichment fuel that your reactor could use and still reasonably accomplish its primary projects, programs, or commercial activities? In your answer, please justify your final choice of enrichment based upon the physical and technical limitations of your reactor and its supporting programs.
.