Text
_
4 L
l g
GPU Nucleer. Inc.
uuctsen Route 441 south 0;'l,"L';g,o,s,,,,
toim444 nn 6710-97 2330 July 21, 1997 Mr. Hubert J. Miller USNRC Region i Aeministrator 475 Allendale Road King of Prussia, PA 19406 1415
Subject:
Three Mile Island Nuclear Station, Unit I (TMI 1)
DPR 50/ Docket No. 50 289 Completion Response to Confirmatory Action Letter 197-008 Actions 4
Regard!r.g the Classification of Selected Plant Components at TMI-l
Dear Mr. Miller:
The purpose of this letter is to provide notification in wdting of the completion of the four actions
- addressed in Confirmatory Action Letter (CAL) 1-97-008. Actions one and two, which included initiation ofimmediate corrective actions and a determination of the impact of the equipment classification downgrade program, were documented in a GPUN letter to the Regional Administrator, NRC Region I, dated April 30,1997.
Actions three and four, performance of an assessment of the equipment classification downgrading process and a determination of what assessments and changes to other engineering processes are needed, were completed by July 1 1997 A management meeting with Region I staff was held on July 16,1997, dunng which we discussed our evaluation of the assessment.
Sincerely, ames W. Langenb h Vice President and Director, TMI AWM cc:
Document Control Desk TM1 Senior Resi, dent inspector TMI Senior Project Manager File 97047 9709040190 970820
)
PDR ADOCK 05000289 G
,