August 14, 1997 LICENSEE:
NORTHEAST NUCLEAR ENERGY COMPANY (NNECO)
FACILITY:
M:llstone Nuclear Power Station Unit 2
SUBJECT:
JULY 30,1997, MEETING WITH NORTHEAST UTILITIES AND PARSONS POWER GROUP INC. REGARDING ACCESS TO INFORMATION NECESSARY FOR THE UNIT 2 ICAVP REVIEW On July 30,1997, the Special Projects Office (SPO) staff of the Office of Nuclear Reactor Regulation (NRR) participated in a meetino with representatives of Parsons Power Group Inc.
(Parsons) and Northeast Utilities (NU). Tne purpose of the meeting was to continue the discussion from the July 25,1997, teleconference regarding Parsons' access to NU's databases that are necessary for Parsons to perform the Tier 2 and Tier 3 reviews of the Independent Corrective Action Venfication Program (ICAVP) at Millstone Unit 2. The enclosure provides a !ist of meeting ettendees.
During the meeting, Parsons discussed control of the administrative interface between Parsons and NU's document control staff. Parsons' approved communications protocol provides for direct communication between Parsons' Group Leads and NU's document control staff to facilitate retrieval of records and documents. The SPO staff indicated that it was acceptable for Parsons to modify its communications protocol to allow Parsons staff responsible for conducting the ICAVP to directly interact with NU's document control staff or other NU personnel associated with the retrieval of information. Parsons communications protocol will still require that the administrative discussion between Parsons and NU personnel be limited to the retrieval of specific information or to the methods for retrieving information from NU's database and information management systems.
The meeting focused on the administrative requirements and mechanics of retrieving information from NU's database and information managenient systems. Following the meeting, Parsons' and NU's information management specialists discussed the details of coordinat: q and arranging access to the information necessary for Parsogtgrform its Tier 2 and Tim 3 ICAVP reviews.
OriBW John A. Nakoski, ICAVP Program Coordinator ICAVP Oversight Branch Special Projects Office Office of Nuclear Reactor Regulation Docket No. 50-336
Enclosures:
As Stated cc w/att:
See next page DIETRIBUTION:
pOl
/
HARD COPY Docket Files ~(50-336) SPO reading Elmbro OGC PUBLIC:
JDurr, RI SReynolds RPerch ACRS E-MAIL SCollins RZimmermen WTravers PMcKee WDean FMirnglia DMcDonald -
LBerry Dross DOCUMENT NAME: G:\\NAKOSKl\\TRIPRPT.010 To receive a :opy of th6s document, ind6cate in the bos 'C" = Copy wtthout attacNonct *E" a copy w*th attacNonci *),
.y, OFFICE ICAVP/SPQ E
ICAVP/SPO
[f JANakoskihtk SReynolds NAME DATE h/bl97
'/'7/97 OFFICIAL RECORD COPY 9708290055 970814 PDR ADOCK 05000336 P
POR
l LIST OF ATTENDEES July 30,1997 - 2:30 p.m.
c NAME ORGANIZATION POSITION Steve Reynolds NRC Branch Chief, ICAVP Oversight, SPO, NRR Ralph Architzel NRC ICAVP Oversight Team Leader - Unit 2, SPO, NRR John Nakoski NRC ICAVP Oversight Program Coordinator, SPO, NRR Paul Narbut NRC ICAVP Oversight System Lead - Team 2A, SPO, NRR Dan Curry Parsons Project Director Eric Blocher Parsons Deputy Director William Meeks Parsons Chair, Technical Advisory Group John lornnidi Parsons Tier 1 Group Lead Greg Cranston Parsons System Team Lead - HPSI Ed Toll Parsons Mechanical Lead / AFW Lead Ken Mayers Parsons I&C Lead Tom Klein Parsons Electrical Lead Derek Garrett Parsons Project Information Specialist Dennis Yoder Parsons Site Walkdown Specialist Joseph Fougere Northeast Utilities Manager, ICAVP Tom Paulantonio Northeast Utilities ICAVP Project Assistant Randy Brumbaugh Northeast Utilities Nuclear inforrr.ation Technology, Supervisor Marjorie Rau:ra Northeast Utilities Nuclear Document Services Enclosure l
1 Northeast Nuclear Energy Company Millstone Nuclear Power Station
{
Unit 2 cc:
Lillian M. Cuoco, Esquire Mr. Wayne D. Lanning Senior Nuclear Counsel Deputy Director of Inspections Northeast Utilities Service Company Special Projects Office P. O. Box 270 475 Allendale Road Hartford, CT 06141-0270 King of Prussia, PA 19406-1415 Mr. Kevin T. A. McCarthy, Director Mr. F. C. Rothen Monitoring and Radiation Division Vice President - Nuclear Work Services Department of Environmental Northeast Nuclear Energy Company Protection P.O. Box 128 79 Elm Street Waterford, CT 06385 Hartford, CT 06106-5127 Charles Brinkman, Manager Mr. Allan Johanson, Assistant Director Washington Nuclear Operations, Office of Policy and Management ABB Combustion Engineering Policy Development and Planning 12300 Twinbrook Pkwy, Suite 330 Division Rockville, MD 20852 450 Capitol Avenue - MS 52ERN P. O. Box 341441 Mr. D. M. Goebel Hartford, CT 06134-1441 Vice President - Nuclear Oversight Northeast Nuclear Energy Company Regional Administrator, Region i P. O. Box 128 U.S. Nuclear Regulatory Commission Waterford, CT 06385 475 Allendale Road King of Prussia, PA 19406 Mr. M. L. Bowling, Jr.
Millstone Unit No. 2 Nuclear First Selectmen Recovery Officer Town of Waterford Northeast Nuclear Energy Company Hall of Records P. O. Box 128 200 Boston Post Road Waterford, CT 06385 Waterford, CT 06385 Senior Resident inspector Mr. J. P. McElwain Millstone Nuclear Power Station Mi;istone Unit No.1 Nuclear clo U.S. Nuclear Regulatory Commission Recovery Officer P. O. Box 513 Natheast Nuclear Energy Company Niantic, CT 08357 P. O. Box 128 Waterford, CT 06385 tw. J. K. Thayer Recovery Officer-Nuclear Deborah Katz, President Engineering and Support Citizens Awareness Network Northeast Nuclear Energy Company P. O. Box 83 P. O. Box 128 Shelburne Falls, MA 03170 Waterford, CT 06385
Northeast Nuclear Energy Company Millstone Nuclear Power Station Units 1,2, and 3 cc:
Burlington Electric Department Ms. P. Loftus clo Robert E. Fletcher, Esq.
Director - Regulatory Affairs for 271 South Union Street Millstone Station Burlington, VT 05402 Northeast Nuclear Energy Company P. O. Box 128 Mr. M. R. Scully, Exocutive Director Waterford, CT 06385 Connecticut Munleipal Electric Energy Cooperative Mr. N. S. Cams 30 Stott Avenue Senior Vice President and Norwich, CT 06360 Chief Nuclear Officer Northeast Nuclear Energy Company Mr. William D. Meinert P. O. Box 128 Nuclear Engineer Waterford, CT 06385 4
Masst.chusetts Municipal Wholesale Electric Company Mr. Don K. Schopfer P. O. Box 426 Vice President and ICAVP Manager Ludlow, MA 01056 Sargent & Lundy LLC 55 East Monroe Street Ernest C. Hadley, Esq.
Chicago, IL 60603-5780 1040 B Main Street P. O. Box 549 Mr. Daniel L. Curry West Wareham, MA 02576 Project Director Millstone Project Joseph R. Egan, Esq.
Parsons Power Group Inc.
Egan & Associates, P.C.
2675 Morgantown Road 2300 N Street, NW Reading, PA 19607 Washington, D.C. 20037 Citizens Regulatory Commiss!on ATTN: Ms. Susan Perry Luxton 180 Great Neck Road Waterford, Connecticut 06385 The Honorable Terry Concannon Co-Chair Nuclear Energy Advisory Council Room 4035 Legislative Office Building Capitol Avenue Hartford, Connecticut 06106 Mr. Evan Woolacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 1