o l
I CONNECTICUT YANKEE ATOMIC POWER COMPANY HADDAM NECK PLANT 36.'lNJUN hot 10W ROAD e EAST HAMPTON. CT 06424-3093 August 22,1997 Docket No. 50-213 CY-97-075.
Re:
10CFR50.82 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 - 0001 lladdam Neck Plant Post Shutdown Decommissioning Activities Renort (PSDAR)
In accordance with 10CFR50.82(a)(4)(i), Connecticut Yankee Atomic Power Company (CYAPCO) hereby submits to the NRC the Post Shutdown Decommissioning Activities Report (PSDAR) for the lladdam Neck Plant (llNP). In accordance with 10CFR50.82, the PSDAR includes:
CYAPCO's selection of the DECON decommissioning option; a description of planned C commissioning activities; e
a schedule for those planned activities; e
an estimate of currently expected costs; and g
e a discussion of the reasons for CYAPCO's conclusion that the environmental g\\
e impacts associated with the planned activities are bounded by appropriate j\\
previously issued environmental impact statements.
I Should plans further develop or change, CYAPCO will inform the NRC of changes in t
accordance with 10CFR50.82(a)(7).
In addition,10CFR50.82(a)(8)(iii) requires that CYAPCO submit, within 2 years following permanent cessation of operations, an updated site-specific decommissioning cost estimate. CYAPCO intends tc submit the site-specific estimate under separate cover on a schedule consistent with the rule. At that time, and in light of the rate case currently pending before the Federal Energy Regulatory Commission, CYAPCO intends to address the decommissioning funding issues identified in 10CFR50.82(c).
Similarly,10CFR50.54(bb) equires that CYAPCO submit, within 2 years following permanent cessation of operations, a spent fuel management program dcscribing 9708270377'[O822
~
9
-PD ADOCK 05000213
!,h.h..
U. S. Nuclear Regulatory Comminion CY-97-075/Page 2 its management and funding plans of the CYAPCO spent fuel until title and possession of the fuel is transferred to the Secretary of Energy for its ultimate disposal in a repository.
CYAPCO intends to submit this plan under separate cover on a schedule consistent with the regulation.
If you should have any questions, please contact hir. G. P. van Noordennen at (860) 267-3938.
Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY d
T.'C. Feigenbaun/
lixecutive Vice President and Chief Nuclear Officer Enclosure cc:
11 J. h1 iller, Region 1 Administrator hl. B. Fairtile, NRC Senior Project hianager, NRR W. J Raymond, Senior Resident inspector, lladdam Neck Plant K. T. A. AlcCarthy, Director, CT DEP hionitoring and Radiation Division m
- - _