NARRATIVE
SUMMARY
OF MONTHLY OPERATING EXPERIENCE DECEMBER 1985
-December 1 The Station was in Operational Mode 1 with reactor through power at a nominal 100 percent with the Reactor December 14 Coolant System at a normal operating pressure and tempe rature.
December 15 At 1200 hours0.0139 days <br />0.333 hours <br />0.00198 weeks <br />4.566e-4 months <br />' Rod Position Indicator (RPI) C-9 had a greater than 12-Step deviation from the Group Demand Counte r.
The indicator was decla red out-of-service until 1551 hours0.018 days <br />0.431 hours <br />0.00256 weeks <br />5.901555e-4 months <br /> at which time trouble shooting was complete and C-9's RPI was within 12-Steps of the Group Demand Counter.
Plant power output remained at a nominal 100 percent throughout the day.
December 16 The Station was in Operational Mode 1 with reactor through power at a nominal 100 percent with the Reactor Coolant December 31 System at a normal operating pressure and temperature.
8604020609 851231 PDR ADOCK 05000334 R
OPERATING DATA REPORT DOCKET NO. 50-334 DATE I/7/86 COMPLETED BY Paul A. Smith TELEPHONE. 41? '41-1825 OPERATING STATUS
- 1. Unit Name: Beaver Valley Power Station, Unit #1 Notes December 1985
- 2. Reporting Period:
- 3. Licensed Thermal Power (MWt):
M 923
- 4. Nameplate Rating (Gross MWe):
835
- 5. Design Electrical Rating (Net MWe):
- 6. Maximum Dependable Capacity (Gross MWe):
860 810
- 7. Maximum Dependable Capacity (Net MWe):
~
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Gin Reasons:
- 9. Power Level To Which Restricted. If Any (Net MWe):
None
- 10. Reasons For Restrictions. lf Any:
N/A This Month Yr..to-Oste Cumulative 744.0 8,760.0 84,768.0
- 11. Hours in Reporting Period
'12. Number Of Hours Reactor Was Critical 744.0 8,245.3 45,601.0
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 4,482.8
- 14. Hours Generator On-Line 744.0 8,051.9 44,134.8
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Ene _ty Generated (MWH) l.951.848.0 19,624,917.I 103.023,431.I
- 17. Gross Electrical Energy Generated (MWH) 634,000.0 6,287,000.0 32,781,400.0
- 18. Net Electrical Energy Generated (MWH) 599.820.0 5.901.460.0 30,526,303.0
- 19. Unit Service Factor 100.0 91.9 54.5
- 20. Ur.it Availability Factor 100.0 91.9 54.5
- 21. Unit Capacity Factor IUsing MDC Net) 99.5 83.2 48.0 96.6 80.7 46.6
- 22. Unit Capacity FactorIUsing DER Net)
- 23. Unit Forced Outage Rate 0.0 7.1 23.9
- 24. Shutdowns Scheduled Over Next 6 Months ! Type.Date.and Duration of Eacht:
Fifth Refuelin9, May 19, 1986 Scheduled 93 days
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status IPrior to Commercial Operationi:
Forecast Achieved INITIA L CRITICA LITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPER ATION N/A N/A (9/77)
AVERACE DAILi UNIT POWER LEVEL DOCKET NO.
50-334 UNIT BV?S Uni: #1 DATE 1/7/86 P.A. Smfth COMPLk~.TED BY TELEPHONE (412) 643-1825 DECEMBER 1985 MONTH DAY AVERACE DAILY POWER LEVEL DAY AVERACE DAILY POWER LEVEL (MWe-Net)
(MWe Net) 829 829 j
37 787 788 2
gg 829 3
3, '
791 788 830 4
g
~
787 829 S
gg 829 786 6
~
787 7
23 787 829
-829 g
9 787 25 789 788 829 in 26 f
II 27 788 828 l
788 826 I,-
23 828 787 13 788 788 Id 3a 830 31 828 786 16 INSTRUCTIONS On this formst.!ist the average daily unit power !=se!in MWe. Net for esch cisy in the reputtine month. Compute to the ne: rest whole mepwait.
(9/77)
I f'
l' MAJOR MAINTENANCE i
c 1.
Tube shooting of Primary Plant Component Cooling Water Heat j
Exchange'rs (CC-E-1A & IB).
1 2.
Maintenance of Diesel Driven Air Compressor (EE-C-1A).
I' 1
3.
Maintenance of Rod Drive Motor Generator (RD-MG-01).
i i
l i
f' I
I i
f e
i 4
t
,~e.
,---.,_,-~..,_
......u.__,_
G p
}Vg 7YAb M
Tetepnene (452) 393400o "3 ??*
Shippingport, PA 15077-0004 January 7, 1986 Beaver Valley Power Station, Unit No.1 Docket No. 50-334, License No. DPR-66 Monthly Operating Report U. S. Nuclear Regulatory Commission Director, Office of Management Information & Program Control Washington, D. C. 20555 Gentlemen:
In accorda nce with Appendix A,
Technical Specifications, the Monthly Operating Report is submitted for the month of December,1985.
Very, yruly yours,
h
. Carey Vice President Nuclear Group rw Enclosures cc: NRC Regional Office King of Prussia, PA I