Requests Meeting to Discuss Util Use of 860722 Update to Unit 1 FSAR as Basis for Unit 2 FSAR Rev Re Mgt & Organization (SER Open Item 6)
ML20210F926
Person / Time
Site: Beaver Valley
Issue date: 09/18/1986
From: Carey J
DUQUESNE LIGHT CO.
To: Harold Denton, Tam P
Office of Nuclear Reactor Regulation
References
2NRC-6-097, 2NRC-6-97, TAC-62875, NUDOCS 8609250304
Download: ML20210F926 (1)


Text

,glV,

4

'A@

g 2NRC-6-097 Beaver Vaney No. 2 Unit Project Organization Telecopy ( 2) 64 Ext.160 II."s'o",""2$"'

Sept. I8, 1986 Shippingport, PA 15077 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation United States Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Mr. Peter Tam, Project Manager Division of PWR Licensing - A Office of Nuclear Reactor Regulation

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 SER Open Iten 6, Management and Organization

REFERENCE:

a) Letter to H. R. Denton, dated July 22, 1986 Transmitting an Update to the BVPS-1 FSAR Gentlemen:

Reference (a) provided a revised description of management and orga-nization for the BVPS-1 FSAR.

Since this organization serves the BVPS site including BVPS-2, the staff should use it as the basis for their review at BVPS-2. DLC proposes that a meeting be held as soon as possible to discuss preliminary staff findings and to respond to any questions regarding this submittal.

DUQUESNE LIGHT COMPANY By j

J. J.VCarey Sr. Vice President l

l GLB/ijr-NR/01/6 l

AR/NAR l

cc:

Mr. P. Tam, Project Manager Mr. L. Prividy, NRC Resident Inspector l

Mr. W. Troskoski, Sr. Resident Inspector V

0 B609250304 860918 PDR ADOCK 05000334 P

PDR