ML20210D860
| ML20210D860 | |
| Person / Time | |
|---|---|
| Site: | Satsop, Washington Public Power Supply System |
| Issue date: | 01/23/1987 |
| From: | Sorensen G WASHINGTON PUBLIC POWER SUPPLY SYSTEM |
| To: | Johnson G NRC OFFICE OF RESOURCE MANAGEMENT (ORM) |
| Shared Package | |
| ML20210D848 | List: |
| References | |
| GO1-87-0009, GO1-87-9, GO3-87-017, GO3-87-17, NUDOCS 8702100181 | |
| Download: ML20210D860 (2) | |
Text
O washington Public Power Supply System Box 1223 Elma, Washington 98541 (206)482 4428 G01-87-0009 G03-87-017 January 23, 1987 i.ECE: ! E Docket Numbers: 50-460 & 50-508
'87 FE0 -2 P5:13 Mr. Graham D. Johnson, Director Division of Accounting and Finance g c. n [ i-
- ;.t Office of Resource Management U.S. Nuclear Regulatory Commission Washington, D.C. 20555
Subject:
SUPPLY SYSTEM NUCLEAR PROJECTS WNP-1 AND WWP-3 U.S. NRC BILLINGS FOR OPERATING LICENSE REVIEWS AND INSPECTION FEES
References:
Letter (G01-86-0002/G03-86-004),
G.C. Sorensen to William 0. Miller, t
same subject, dated January 6, 1986, 1
i The referenced letter indicated that we had reviewed your supporting documentation for the initial billings (December 28, 1984) for the accumulated Operating License review costs for WNP-1 and WNP-3.
These bills were paid by the Supply System in January 1985.
We found what we considered to be an error in the billing for WNP-3.
We also had several questions regarding the details of the billings for both WNP-1 and WNP-3.
l The amount of the WNP-3 billing that we believed to be in error represents several hundred thousand dollars of potential overpayment.
l It has now been more than one year since we transmitted our questions and request for reimbursement (should you find merit in our claim regarding the l
WNP-3 billing).
It has also been more than two years since the billings were paid.
We have not yet received a response from the NRC regarding our concerns.
We again ask that you reimburse the Supply System for any overpayment should you find merit in our claim.
We also ask that you respond to our questions regarding those initial billings.
1
[
A l
l
/*
Mr. Graham D. Johnson, Director e
l Page Two GU1-87-0009 G03-87-017 January 23, 1987 Should you have any questions regarding this matter, you may contact Mr. D.W. Coleman, WNP-3 Project Licensing Manager at (206) 482-4428 Ext. S436.
gbh
.-sl
/d"G.C. Sorensen Manager Regulatory Programs DWC/st cc: Mr. J. A. Adams, NESCO Mr. M. F. Barnoski, Combustion Engineering Mr. R. M. Boucher, Pacific Power & Light Co.
Mr. W. L. Bryan, Washington Water Power Co.
Mr. R. E. Dyer, Portland General Electric Co.
Mr. W. J. Finnegan, Puget Sound Power & Light Co.
Mr. G. W. Knighton, U.S. Nuclear Regulatory Commission Mr. R. S. Lee, U.S. Nuclear Regulatory Commission Mr. J. R. Lewis, BPA Mr. N. S. Reynolds, Bishop, Liberman, Cook, Purcell & Reynolds Mr. D. Smithpeter, BPA Mr. V. Stello Jr., U.S. Nuclear Regulatory Commission Ms. R. M. Taylor, Ebasco - Elna Document Control Desk - U. S. NRC I