ML20210A659
ML20210A659 | |
Person / Time | |
---|---|
Site: | Salem |
Issue date: | 11/13/1986 |
From: | Mirarchi S BISHOP, COOK, PURCELL & REYNOLDS |
To: | Grimsley D NRC OFFICE OF ADMINISTRATION (ADM) |
References | |
FOIA-86-808 NUDOCS 8705050137 | |
Download: ML20210A659 (2) | |
Similar Documents at Salem | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217M2101999-10-19019 October 1999
[Table view]Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates ML18107A5601999-10-18018 October 1999 Submits 30-day Fuel Clad Temp Rept,Iaw 10CFR50.46.Rept Describes Changes to Calculated Peak Clad Temp (PCT) for Salem Generating Station Large & Small Break LOCA Analyses ML18107A5531999-10-0808 October 1999 Forwards Summary Rept of Plant Startup & Power Ascension Testing for Sgs,Unit 2 Cycle 11,per Requirements of TS 6.9.1.1 ML18107A5561999-10-0707 October 1999 Requests Relief Associated with Containment Examinations at Hope Creek & Salem Generating Stations.Attachment 1 Includes Proposed Alternatives & Supporting Justification for Relief Requests ML18107A5591999-10-0505 October 1999 Informs That Nj Dept of Environ Protection Has No Comments on License Change Request S99-07 for Sgs,Units 1 & 2 ML18107A5501999-10-0505 October 1999 Provides Current Status of Pse&G Actions Re GL 98-01, Y2K Readiness of Computer Sys at Npps, for Salem Nuclear Generating Station,Units 1 & 2 & Hope Creek Nuclear Generating Station ML18107A5521999-10-0505 October 1999 Encourages NRC to Support Abb Combustion Engineering Nuclear Power Request for Priority Review of Generic TR Re Crossflow Ultrasonic Flow Measurement Sys IR 05000272/19990071999-09-28028 September 1999 Forwards Insp Repts 50-272/99-07 & 50-306/99-07 on 990721- 0831.One Potentially Safety Significant Issue Identified Dealing with Control Room Special Ventilation System.Four Addl Issues of Low Safety Significance Identified ML18107A5341999-09-22022 September 1999 Provides Data Re Operator Licensing Exam for Salem & Hope Creek Station,In Response to NRC Form 536 (7-1999) ML18107A5421999-09-22022 September 1999 Forwards Discharge Monitoring Rept for Salem Generating Station for Aug 1999.Rept Is Required by & Prepared Specifically for EPA & Nj Dept of Environ Protection ML20212B3631999-09-14014 September 1999 Forwards Rev 13 to Salem - Hope Creek Security Plan,Iaw 10CFR50.54(p).Summary of Proposed Changes to Plan,Encl. Encl Withheld ML18107A5321999-09-13013 September 1999 Forwards Revised 10CFR50.92 Evaluation to Clarify Util Response to Question Number 1 Re Amend to Modify TS 3/4 8.1, AC Power Sources. ML18107A5351999-09-13013 September 1999 Informs That NRC Has Reviewed Pse&G Request Proposing to Modify TS Which Allow EDG to Be Operated for 24 Surveillance Test During Any Mode,Iaw 10CFR50.91(b) & Has No Comments ML18107A5331999-09-13013 September 1999 Provides Notification That PSEG Intends to Utilize ASME Code Case N-481 During Second ISI Interval at Sgs Units 1 & 2 ML18107A5221999-09-0808 September 1999 Requests Approval to Use ASME Code Case N546,which Provides Alternative Qualification Requirements That Allow Personnel Most Familiar with Walkdown of Plant Sys,Like License Operators to Perform VT-2 Examinations ML18107A5231999-09-0808 September 1999 Forwards Salem Generating Station Semiannual Radioactive Effluent Release Rept for Jan-June 1999. Rept Summarizes Liquid & Gaseous Releases & Solid Waste Shipments from Salem Generating Station for Period of Jan-June 1999 ML18107A4981999-08-26026 August 1999 Forwards Response to NOV That Resulted from Predecisional Enforcement Conference Conducted on 990624.Corrective Actions:Communications to Supervisors Reinforced Employee Right & Duty to Raise Nuclear Safety Issues ML18107A5181999-08-26026 August 1999 Forwards Ninety Day Rept for ISI Activities Conducted at Sgs,Unit 2 During Ninth Extended Outage & Tenth Refueling Outage.List of Encl,Provided ML18107A5061999-08-26026 August 1999 Provides First Feedback from Observation of NRC Insp Under Pilot Nuclear Power Plant Insp Program.Attached Are Completed Insp Feedback Forms for Procedure 71111, Attachment 21 & Procedure 71151 ML18107A5051999-08-24024 August 1999 Informs That Nj Dept of Environ Protection Bureau of Nuclear Engineering Has Reviewed Request IAW Requirements of 10CFR50.91(b) & Has No Comments Re Amend to FOL Change Request S99-02 to Modify TS Re Penetration Valves ML18107A4921999-08-23023 August 1999 Provides Suppl Info Re 971024 Amend Request to Modify TS 3/4 7.7, Auxiliary Bldg Exhaust Air Filtration Sys. Util Withdraws from Request All Proposed Changes Associated with Filter Testing,Per Issuance of GL 99-02 ML18107A4911999-08-20020 August 1999 Forwards Revised Plant Attribute Libraries for Salem & Hope Creek Generating Stations,Iaw 10CFR50,App E,Vi, Emergency Response Data Sys, 3.b.Changes Are Identified by Rev Bars ML18107A4861999-08-19019 August 1999 Forwards NPDES Discharge Monitoring Rept, for Salem Generating Station for Month of Jul 1999.Rept Required by & Prepared Specifically for EPA & Nj Dept of Environ Protection ML18107A4831999-08-18018 August 1999 Submits Licensee Comments on NRC 990730 Ltr Which Provided Notification of Close Out of TAC Numbers MA0567 & MA0568 Re GL 92-01,Rev 1,Suppl 1 ML18107A4801999-08-13013 August 1999 Requests That Pse&Gs Contact in NUREG-0383, Directory of Compliance for Radioactive Matl Packages, Be Changed ML18107A4751999-08-0505 August 1999 Forwards Fitness for Duty Performance Data Rept for Six Month Period Ending 990630 ML20210M7571999-08-0404 August 1999 Forwards Response to Requesting Addl Info Re Status of Decommissioning Funding for Lgs,Pbaps & Sngs. Attachment Provides Restatement of Questions Followed by Response ML18107A4531999-07-20020 July 1999 Forwards Discharge Monitoring Rept for Salem Generating Station, for June 1999.Rept Is Required by & Prepared for EPA & Nj Dept of Environ Protection ML18107A4431999-07-0606 July 1999 Informs That Nj Dept of Environ Protection Bureau of Nuclear Engineering Has Reviewed Pse&G License Change Request S98-17 Re Permissible Enrichment Values for New Fuel Storage & Has No Comments ML20196J6301999-07-0101 July 1999 Requests Addl Info Re Status of Decommissioning Funding for Limerick Generating Station,Units 1 & 2,Peach Bottom Atomic Power Station,Units 1,2 & 3 & Salem Nuclear Generating Station,Units 1 & 2 ML18107A4181999-06-30030 June 1999 Submits Response to NRC Request for Info Re Y2K Readiness at Npps,Per GL 98-01,suppl 1.Disclosure Encl ML20209B6751999-06-29029 June 1999 Ack Receipt of from Dr Powell in Response to NRC Re Fitness for Duty.Attachment 2 of Will Be Withheld from Public Disclosure,Per 10CFR2.790 ML18107A4131999-06-25025 June 1999 Provides Further Clarification of Licensing & Design Basis for 125 Vdc Battery Margins for Sgs & HCGS for Meeting Station SBO & Loca/Loop Loading Requirements,Per Util 990426 Ltr & Discussion with NRC ML18107A4091999-06-22022 June 1999 Forwards Discharge Monitoring Rept for May 1999,containing Info as Required by Permit NJ0005622.Rept Prepared Specifically for EPA & Nj Dept of Environ Protection ML18107A4061999-06-21021 June 1999 Provides Supplemental Info to Proposed License Amend, Modifying TS 3/4 7.7, Auxiliary Bldg Exhaust Air Filtration Sys. Info Re Acceptance Criterion Discussed ML18107A3691999-06-11011 June 1999 Forwards Corrected Monthly Operating Rept for Apr 1999 for Salem Generating Station,Unit 1.Original Submittal Contained Typo for year-to-date Value for Numbers of Hours Generator Was on Line (Service Hours) ML18107A3641999-06-0404 June 1999 Requests Enforcement Discretion for TS 3/4.6.2.3 Re Containment Cooling Sys for Salem Generating Station,Unit 1 ML18107A3561999-06-0303 June 1999 Informs That Nj Dept of Environ Protection Bureau of Nuclear Engineering Has Reviewed Pse&G License Change Request S99-05 & Has No Comments ML18107A3611999-05-27027 May 1999 Forwards Responses to NRC 990301 & 990323 RAIs for Salem & Hope Creek Generating Stations Relating to GL 96-05 ML18107A3301999-05-24024 May 1999 Forwards Suppl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves. Encl Contains Methodology Used in Determination of Pressure Locking Susceptibility of PORVs Block Valves ML18107A3371999-05-21021 May 1999 Forwards NPDES Discharge Monitoring for Salem Generating Station for Apr 1999, Containing Info as Required by Permit NJ0005622 ML18107A3291999-05-20020 May 1999 Forwards Redacted Response to NRC 990322 RAI Re Notification of Licensed Operator That Tested Positive for Alcohol. Attachment 2 Withheld,Per 10CFR2.790(a)(6) ML18107A3031999-05-18018 May 1999 Provides Summary of Changes to NRC Commitments That Have Been Made But Not Reported by Other Means,Iaw with NEI Process for Managing NRC Commitments ML18107A2891999-05-13013 May 1999 Forwards Rev 36 to Pse&G Nuclear Business Unit Emergency Plan. Rev 36 Incorporates Changes to Section 1-3,6 & 7 & 9-17.Attached Copy Includes All Sections of EP for Completeness ML18107A2951999-05-12012 May 1999 Submits SG Tube Plugging Rept,Per Plant TS 4.4.6.5.a.Total of 47 Tubes Were Plugged During SG Tube Insps,Which Were Completed During Plant Tenth RFO ML18107A2861999-05-11011 May 1999 Forwards Rev 0 to NFS-0174, COLR for Salem Unit 2 Cycle 11. COLR Rept Was Received by Util as Part of Reload SE ML18107A2481999-04-29029 April 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Salem & Hope Creek Generating Stations. Rept Summarizes Results of Radiological Environ Surveillance Program for 1998 ML18107A2511999-04-27027 April 1999 Submits 30-day Fuel Clad Temp Rept for Salem Generating Station,Units 1 & 2.Rept Describes Changes to Calculated Peak Clad Temp (PCT) for Plant Large & Small LOCA & Small Break LOCA Analyses ML18107A2631999-04-26026 April 1999 Provides Clarification on Licensing & Design Basis for 125 Vdc Battery Margins for Sgs & HCGS for Meeting SBO & Loca/ LOOP Loading Requirements ML18107A2371999-04-26026 April 1999 Forwards Corrected Response to NRC RAI Re Licensee Request for Change to TS Permissible Enrichment Values for New Fuel Storage.Incorrect Attachment Was Provided with Util 990412 Ltr to Nrc.Encl Supersedes 990412 Submittal 1999-09-08 Category:INCOMING CORRESPONDENCE MONTHYEARML18107A5601999-10-18018 October 1999
[Table view]Submits 30-day Fuel Clad Temp Rept,Iaw 10CFR50.46.Rept Describes Changes to Calculated Peak Clad Temp (PCT) for Salem Generating Station Large & Small Break LOCA Analyses ML18107A5531999-10-0808 October 1999 Forwards Summary Rept of Plant Startup & Power Ascension Testing for Sgs,Unit 2 Cycle 11,per Requirements of TS 6.9.1.1 ML18107A5561999-10-0707 October 1999 Requests Relief Associated with Containment Examinations at Hope Creek & Salem Generating Stations.Attachment 1 Includes Proposed Alternatives & Supporting Justification for Relief Requests ML18107A5501999-10-0505 October 1999 Provides Current Status of Pse&G Actions Re GL 98-01, Y2K Readiness of Computer Sys at Npps, for Salem Nuclear Generating Station,Units 1 & 2 & Hope Creek Nuclear Generating Station ML18107A5521999-10-0505 October 1999 Encourages NRC to Support Abb Combustion Engineering Nuclear Power Request for Priority Review of Generic TR Re Crossflow Ultrasonic Flow Measurement Sys ML18107A5591999-10-0505 October 1999 Informs That Nj Dept of Environ Protection Has No Comments on License Change Request S99-07 for Sgs,Units 1 & 2 ML18107A5341999-09-22022 September 1999 Provides Data Re Operator Licensing Exam for Salem & Hope Creek Station,In Response to NRC Form 536 (7-1999) ML20212B3631999-09-14014 September 1999 Forwards Rev 13 to Salem - Hope Creek Security Plan,Iaw 10CFR50.54(p).Summary of Proposed Changes to Plan,Encl. Encl Withheld ML18107A5321999-09-13013 September 1999 Forwards Revised 10CFR50.92 Evaluation to Clarify Util Response to Question Number 1 Re Amend to Modify TS 3/4 8.1, AC Power Sources. ML18107A5331999-09-13013 September 1999 Provides Notification That PSEG Intends to Utilize ASME Code Case N-481 During Second ISI Interval at Sgs Units 1 & 2 ML18107A5351999-09-13013 September 1999 Informs That NRC Has Reviewed Pse&G Request Proposing to Modify TS Which Allow EDG to Be Operated for 24 Surveillance Test During Any Mode,Iaw 10CFR50.91(b) & Has No Comments ML18107A5231999-09-0808 September 1999 Forwards Salem Generating Station Semiannual Radioactive Effluent Release Rept for Jan-June 1999. Rept Summarizes Liquid & Gaseous Releases & Solid Waste Shipments from Salem Generating Station for Period of Jan-June 1999 ML18107A5221999-09-0808 September 1999 Requests Approval to Use ASME Code Case N546,which Provides Alternative Qualification Requirements That Allow Personnel Most Familiar with Walkdown of Plant Sys,Like License Operators to Perform VT-2 Examinations ML18107A5061999-08-26026 August 1999 Provides First Feedback from Observation of NRC Insp Under Pilot Nuclear Power Plant Insp Program.Attached Are Completed Insp Feedback Forms for Procedure 71111, Attachment 21 & Procedure 71151 ML18107A5181999-08-26026 August 1999 Forwards Ninety Day Rept for ISI Activities Conducted at Sgs,Unit 2 During Ninth Extended Outage & Tenth Refueling Outage.List of Encl,Provided ML18107A4981999-08-26026 August 1999 Forwards Response to NOV That Resulted from Predecisional Enforcement Conference Conducted on 990624.Corrective Actions:Communications to Supervisors Reinforced Employee Right & Duty to Raise Nuclear Safety Issues ML18107A5051999-08-24024 August 1999 Informs That Nj Dept of Environ Protection Bureau of Nuclear Engineering Has Reviewed Request IAW Requirements of 10CFR50.91(b) & Has No Comments Re Amend to FOL Change Request S99-02 to Modify TS Re Penetration Valves ML18107A4921999-08-23023 August 1999 Provides Suppl Info Re 971024 Amend Request to Modify TS 3/4 7.7, Auxiliary Bldg Exhaust Air Filtration Sys. Util Withdraws from Request All Proposed Changes Associated with Filter Testing,Per Issuance of GL 99-02 ML18107A4911999-08-20020 August 1999 Forwards Revised Plant Attribute Libraries for Salem & Hope Creek Generating Stations,Iaw 10CFR50,App E,Vi, Emergency Response Data Sys, 3.b.Changes Are Identified by Rev Bars ML18107A4831999-08-18018 August 1999 Submits Licensee Comments on NRC 990730 Ltr Which Provided Notification of Close Out of TAC Numbers MA0567 & MA0568 Re GL 92-01,Rev 1,Suppl 1 ML18107A4801999-08-13013 August 1999 Requests That Pse&Gs Contact in NUREG-0383, Directory of Compliance for Radioactive Matl Packages, Be Changed ML18107A4751999-08-0505 August 1999 Forwards Fitness for Duty Performance Data Rept for Six Month Period Ending 990630 ML20210M7571999-08-0404 August 1999 Forwards Response to Requesting Addl Info Re Status of Decommissioning Funding for Lgs,Pbaps & Sngs. Attachment Provides Restatement of Questions Followed by Response ML18107A4431999-07-0606 July 1999 Informs That Nj Dept of Environ Protection Bureau of Nuclear Engineering Has Reviewed Pse&G License Change Request S98-17 Re Permissible Enrichment Values for New Fuel Storage & Has No Comments ML18107A4181999-06-30030 June 1999 Submits Response to NRC Request for Info Re Y2K Readiness at Npps,Per GL 98-01,suppl 1.Disclosure Encl ML18107A4131999-06-25025 June 1999 Provides Further Clarification of Licensing & Design Basis for 125 Vdc Battery Margins for Sgs & HCGS for Meeting Station SBO & Loca/Loop Loading Requirements,Per Util 990426 Ltr & Discussion with NRC ML18107A4061999-06-21021 June 1999 Provides Supplemental Info to Proposed License Amend, Modifying TS 3/4 7.7, Auxiliary Bldg Exhaust Air Filtration Sys. Info Re Acceptance Criterion Discussed ML18107A3691999-06-11011 June 1999 Forwards Corrected Monthly Operating Rept for Apr 1999 for Salem Generating Station,Unit 1.Original Submittal Contained Typo for year-to-date Value for Numbers of Hours Generator Was on Line (Service Hours) ML18107A3641999-06-0404 June 1999 Requests Enforcement Discretion for TS 3/4.6.2.3 Re Containment Cooling Sys for Salem Generating Station,Unit 1 ML18107A3561999-06-0303 June 1999 Informs That Nj Dept of Environ Protection Bureau of Nuclear Engineering Has Reviewed Pse&G License Change Request S99-05 & Has No Comments ML18107A3611999-05-27027 May 1999 Forwards Responses to NRC 990301 & 990323 RAIs for Salem & Hope Creek Generating Stations Relating to GL 96-05 ML18107A3301999-05-24024 May 1999 Forwards Suppl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves. Encl Contains Methodology Used in Determination of Pressure Locking Susceptibility of PORVs Block Valves ML18107A3291999-05-20020 May 1999 Forwards Redacted Response to NRC 990322 RAI Re Notification of Licensed Operator That Tested Positive for Alcohol. Attachment 2 Withheld,Per 10CFR2.790(a)(6) ML18107A3031999-05-18018 May 1999 Provides Summary of Changes to NRC Commitments That Have Been Made But Not Reported by Other Means,Iaw with NEI Process for Managing NRC Commitments ML18107A2891999-05-13013 May 1999 Forwards Rev 36 to Pse&G Nuclear Business Unit Emergency Plan. Rev 36 Incorporates Changes to Section 1-3,6 & 7 & 9-17.Attached Copy Includes All Sections of EP for Completeness ML18107A2951999-05-12012 May 1999 Submits SG Tube Plugging Rept,Per Plant TS 4.4.6.5.a.Total of 47 Tubes Were Plugged During SG Tube Insps,Which Were Completed During Plant Tenth RFO ML18107A2861999-05-11011 May 1999 Forwards Rev 0 to NFS-0174, COLR for Salem Unit 2 Cycle 11. COLR Rept Was Received by Util as Part of Reload SE ML18107A2481999-04-29029 April 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Salem & Hope Creek Generating Stations. Rept Summarizes Results of Radiological Environ Surveillance Program for 1998 ML18107A2511999-04-27027 April 1999 Submits 30-day Fuel Clad Temp Rept for Salem Generating Station,Units 1 & 2.Rept Describes Changes to Calculated Peak Clad Temp (PCT) for Plant Large & Small LOCA & Small Break LOCA Analyses ML18107A2371999-04-26026 April 1999 Forwards Corrected Response to NRC RAI Re Licensee Request for Change to TS Permissible Enrichment Values for New Fuel Storage.Incorrect Attachment Was Provided with Util 990412 Ltr to Nrc.Encl Supersedes 990412 Submittal ML18107A2631999-04-26026 April 1999 Provides Clarification on Licensing & Design Basis for 125 Vdc Battery Margins for Sgs & HCGS for Meeting SBO & Loca/ LOOP Loading Requirements ML18107A2411999-04-22022 April 1999 Forwards Draft Revised Pages 4.1 & 4.2 of Nuclear Business Unit Emergency Plan for Hope Creek & Salem Generating Stations.Changes Are Noted in Italics ML18107A1841999-04-14014 April 1999 Forwards PSEG Annual Rept for 1998, & PECO Annual Rept for 1998. Stockholders Annual Rept of Each Owner & Cash Flow Statements Showing 1998 Actual & 1999 Projected Cash Flow with Explanation Encl ML18107A1981999-04-12012 April 1999 Responds to 990312 RAI Re Request for Change to TSs Permissible Enrichment Values for New Fuel Storage,Which Was Submitted on 990202 ML18107A1691999-04-12012 April 1999 Forwards Proprietary & non-proprietary Epips,Including Rev 17 to EPIP 807,rev 1 to NC.EP-EP.ZZ-0801(Q) & Rev 2 to NC.EP-EP.ZZ-0806(Q) & Revised EPIPs Table of Contents. Proprietary Info Withheld ML20205K4541999-04-0808 April 1999 Forwards Revised Info Re 990330 NRC Nuclear Power Reactor Licensee Financial Qualifications & Decommissioning Funding Assurance Status Rept ML18106B1491999-04-0505 April 1999 Forwards Drafts of Proposed Changes to Pages 4.1 & 4.2 of Emergency Plan,Which Are Contained on Page 4.2 & Noted in Italics & Underlined ML20205F8981999-03-31031 March 1999 Provides Info Re Status of Decommissioning Funding for LGS, Units 1 & 2,PBAPS,Units 1,2 & 3 & Sgs,Units 1 & 2,per Requirements of 10CFR50.75(f)(1) ML18106B1431999-03-31031 March 1999 Forwards Pse&G Rept on Financial Min Assurance for Period Ending 981231 for Hope Creek,Salem,Units 1 & 2 & Pbaps,Units 2 & 3,IAW 10CFR50.75 ML18107A2201999-03-30030 March 1999 Forwards Final Exercise Rept for 980303,full-participation Plume Exposure Pathway Exercise & 980505-07, full-participation Ingestion Pathway Exercise of Offsite Radiological Emergency Response for Salem & Hope Creek 1999-09-08 Category:LEGAL/LAW FIRM TO NRC MONTHYEARML18095A2851990-06-14014 June 1990
[Table view]Advises That Licensee in Captioned Docket Now Represented by Firm of Bishop,Cook,Purcell & Reynolds.Further Correspondence to Counsel for Licensee Should Be Forwarded to Address Indicated on Letterhead ML20043G2461990-06-14014 June 1990 Advises That Licensee in Captioned Docket 50-311 Now Represented by Firm of Bishop,Cook,Purcell & Reynolds. Further Correspondence to Counsel for Licensee Should Now Be Forwarded to Author at Address Indicated on Letterhead ML18095A2541990-05-29029 May 1990 Forwards Endorsements 118-120 & 122-127 to Nelia Policy NF-208,Endorsements 105-107 & 109-114 to Maelu Policy MF-77 & Endorsements 13-14 to Certificates N-7/M-7 & N-47/M-47 ML18094A6521989-08-24024 August 1989 Forwards Endorsements 140 & 141 to Nelia Policy NF-164, Endorsements 117 & 118 to Maelu Policy MF-44,Endorsements 115 & 116 to Nelia Policy NF-208 & Endorsements 102 & 103 to Maelu Policy MF-77 ML20245D3421989-03-20020 March 1989 Forwards Listed Endorsements,Including Endorsements 14,163, 144,94,75,39 & 31 to Nelia Policies NF-295,NF-100,MAELU Policy MF-29,NELIA Policy NF-182,MAELU Policy MF-61,NELIA Policy NF-281 & Maelu Policy MF-112,respectively ML18093A9831988-07-19019 July 1988 Advises of Suit Filed by RW & Hw Bey Against Public Svc Electric & Gas,Et Al,Alleging Excessive Exposure to Radiation of Undetermined Nature Due to Six Incidents Between 1979 & 1986.No Prior Records of Allegations on File ML18093A8111988-04-28028 April 1988 Forwards Endorsements 102 & 103 to Nelia Policy NF-208, Endorsements 89 & 90 to Maelu Policy MF-77,Endorsements 100 & 101 to Nelia Policy NF-230 & Endorsements 84 & 85 to Maelu Policy MF-90 ML20148K1111988-03-22022 March 1988 Forwards Listed Endorsements to Listed Policies,Including Endorsement 102 to Maelu Policy MF-26,Endorsement 123 to Nelia Policy NF-76,Endorsement 71 to Maelu Policy MF-56 & Endorsement 89 to Nelia Policy NF-189 ML18093A3581987-09-10010 September 1987 Forwards Endorsements 97 & 96 to Nelia Policy NF-230 & Endorsements 80 & 81 to Maelu Policy MF-90 ML18093A1291987-05-11011 May 1987 Forwards Endorsement 94 to Nelia Policy NF-230 & Endorsement 78 to Maelu Policy MF-90 ML18092B5061987-03-31031 March 1987 Forwards Endorsements 92 & 93 to Nelia Policy NF-230 & Endorsements 76 & 77 to Maelu Policy MF-90 ML20205S4231987-03-12012 March 1987 FOIA Request for Records of Safety Review Committee & IE Group Re DB-50 Circuit Breaker Failures at Facility on 830225 & NRC Insps or Audits of Westinghouse During 780101 to Date,Including QA Program Insp Rept 99900404/83-03 ML18092B4271987-02-0303 February 1987 Forwards Endorsements 90 & 75 to Nelia Policy NF-230 & Maelu Policy MF-90,respectively ML20210A6591986-11-13013 November 1986 FOIA Request for Documents Re Alleged Transmittal or Delivery of Westinghouse Nsd Technical Bulletin 74-1 &/Or Westinghouse Nsd Data Ltr 74-2 Concerning Trip Breaker Failures Occurring After 830225 Failures ML20209H6291986-11-0505 November 1986 FOIA Request for Matls Re Interview W/Util Employee H Chomiak Concerning ATWS Events on 830222 & 25 ML20215N9781986-10-10010 October 1986 FOIA Request for All Records Re Computerized Turnstile Access Gate at Plant from 830601-841231 ML18092B2741986-09-0404 September 1986 Forwards Endorsements to Nelia & Maelu Policies,Including Endorsements 57,20 & 72/73 to Maelu Policies MF-91,MF-112 & MF-90,respectively & Endorsements 73,7,27 & 87/88 to Nelia Policies NF-195,NF-302,NF-281 & NF-230,respectively IR 05000272/19860061986-05-13013 May 1986 Requests Insp Rept 50-272/86-06 Re Exposure of Catalytic Const Co Employees to Excessive Radiation on Various Dates in 1986 Be Forwarded.Law Firm Represents D Lewis,Former Employee ML18092B1731986-05-13013 May 1986 Requests Insp Rept 50-272/86-06 Re Exposure of Catalytic Const Co Employees to Excessive Radiation on Various Dates in 1986 Be Forwarded.Law Firm Represents D Lewis,Former Employee ML18092B1331986-04-0808 April 1986 Forwards Endorsements 23 & 24 to Nelia Policy NF-281, Endorsements 16 & 17 to Maelu Policy MF-112,Endorsement 1 to Maelu Certificate M-106 & Endorsement 1 to Nelia Certificate N-106 ML18092B1321986-03-26026 March 1986 Forwards Endorsements 69 & 68 to Maelu Policy MF-90 & Endorsements 84 & 83 to Nelia Policy NF-230 ML17346B1681986-01-0606 January 1986 Forwards Endorsements to Nelia & Maelu Policies,Including Endorsement 22 to Nelia Policy NF-281,Endorsement 15 to Maelu Policy MF-112 & Endorsements 6 to Nelia & Maelu Certificates N-97 & M-97 ML18092A8391985-10-0808 October 1985 Forwards Secondary Financial Protection Certificates Nelia N-104 & Maelu M-104 ML18092A8251985-10-0303 October 1985 Forwards Endorsement 80 to Nelia Policy NF-230 & Endorsement 65 to Maelu Policy MF-90 ML18092A7661985-09-0606 September 1985 Forwards Endorsements 78 & 79 to Nelia Policy NF-230 & Endorsements 63 & 64 to Maelu Policy MF-90 ML20099M4351985-03-15015 March 1985 Forwards Endorsements 102,36,18 & 74 to Nelia Policies NF-164,NF-252,NF-281 & NF-230,respectively ML18092A4471984-12-21021 December 1984 Forwards Endorsement 73 to Nelia Policy NF-230,Endorsement 59 to Maelu Policy MF-90 & Endorsement 5 to Nelia Policies N-60 & N-72 & Maelu Policies M-60 & M-72 ML18092A2951984-09-28028 September 1984 Forwards Endorsements 71 & 72 to Nelia Policy NF-230 & Endorsements 57 & 58 to Maelu Policy MF-90 ML18092A1691984-05-0707 May 1984 Forwards Endorsement 70 to Nelia Policy NF-230 & Endorsement 56 to Maelu Policy MF-90 ML18089A5511984-03-21021 March 1984 Forwards Endorsements 68 & 69 to Nelia Policy NF-230 & Endorsements 54 & 55 to Maelu Policy MF-90 ML18089A5241984-02-0808 February 1984 Forwards Endorsement 63 to Nelia Policy NF-230 & Endorsement 53 to Maelu Policy MF-90 ML18089A4741983-12-21021 December 1983 Forwards Endorsements 64 & 65 to Nelia Policy NF-230, Endorsements 51 & 52 to Maelu Policy MF-90,Endorsement 4 to Nelia Certificates N-60 & N-72 & Endorsement 4 to Maelu Certificates M-60 & M-72 ML18089A3791983-09-26026 September 1983 Forwards Endorsements 62 & 63 to Nelia Policy NF-230 & Endorsements 49 & 50 to Maelu Policy MF-90 ML18089A2561983-07-20020 July 1983 Forwards Endorsements 61 & 48 to Nelia Policy NF-230 & Maelu Policy MF-90,respectively ML18089A2251983-07-0606 July 1983 Forwards Endorsements 59 & 60 to Nelia Policy NF-230 & Endorsements 46 & 47 to Maelu Policy MF-90 ML18087A9021983-05-0202 May 1983 Forwards Endorsements 58 & 45 to Nelia Policy NF-230 & Maelu Policy MF-90,respectively ML18087A8361983-04-0707 April 1983 Forwards Endorsement 57 to Nelia Policy NF-230 ML18087A6781983-02-18018 February 1983 Forwards Endorsements 44 & 56 to Ani/Maelu Policies MF-90 & NF-230,respectively ML20073D6281983-01-20020 January 1983 FOIA Request for Health & Safety Insp Repts Re 6-inch Gaps Between Airlock & Platform on 100-ft & 130-ft Elevations & Repts Concerning Injuries Sustained by Employees/Contractors Prior to 791010 ML20028D4991983-01-17017 January 1983 Requests Svc Lists Be Changed & Correspondence Be Addressed to R Fryling Due to Retirement of F Broadfoot ML18087A6281983-01-17017 January 1983 Requests All Svc Lists & Correspondence to F Broadfoot Be Now Sent to R Fryling.Change Requested Due to Retirement of F Broadfoot ML18087A6171983-01-0404 January 1983 Forwards Nelia Certificates of Insurance N-60,M-60,N-72 & M-72 & Endorsements 1,2 & 3 to Maelu & Nelia Policies N-60,M-60,N-72 & M-72,respectively,Endorsement 55 to Nelia Policy NF-230 & Endorsement 43 to Maelu Policy MF-90 ML18086B4951982-05-17017 May 1982 Forwards Endorsement 42 to Maelu Policy MF-90 ML18086B4761982-05-0404 May 1982 Forwards Endorsement 54 to Nelia Policy NF-230 ML18086B3861982-03-19019 March 1982 Forwards Endorsement 53 to Nelia Policy NF-230,Endorsement 10 to Nelia Binder EB-60 & Endorsement 8 to Nelia Binder EB-72 ML18086B3821982-03-0909 March 1982 Forwards Endorsements 8 & 6 to Maelu Binders XB-60 & XB-72, Respectively ML18086B3341982-02-25025 February 1982 Forwards Endorsements 51 & 52 to Nelia Policy NF-230, Endorsement 41 to Maelu Policy MF-90,Endorsements 8 & 9 to ANI Binder EB-60 & Endorsements 6 & 7 to ANI Binder EB-72 ML18086B2801982-01-25025 January 1982 Forwards Endorsement 49 to ANI Policy NF-230 & Endorsements 40,7 & 5 to Maelu Policies MF-90,XB-60 & XB-72, Respectively ML18086B0091981-11-0303 November 1981 Forwards Endorsement 39 to Maelu Policy MF-90 ML18086A9251981-09-0909 September 1981 Forwards Endorsement 38 to Maelu Policy MF-90 1990-06-14 |
Text
-
BISHOF. LIBERMAN & COOK
& PARTh(R$attp tieCLgCygg P90FtS5soesaL C0aponatioses 1855 AVENUE oF THE AMERICAS N EW YORK. NEW YORK too36 ...-o u.ca....co... .eeu ..c, . .
eaoo sava. var =va statet. se =
r212) 704 0800 CA B LE: e ERiLie wa -.=stom.o c. aoose a.a ......oo TELECopiER: s212) 704 0196 TELEX: 222767 j
November 13, 1986 FREEDOM OF INFORMATION I
Donnie H. Grimsley, Director ACI REQUEST Division of Rules and Records Office of Administration h/A (( -8d j U.S. Nuclear Regulatory Commission #
N .(d ((
Washington, D.C. 20555 Re: Freedom of Information Act Request
Dear Mr. Grimsley:
5 552) andPursuant to the the NRC's Freedominof10 regulations Information C.F.R. Part Act (5 U.S.C.
9, we hereby request copies of all transcripts, minutes, memoranda, notes, or other documents in any form that purport to quote, paraphrase, or reflect any information obtained by the NRC or any agency or instrumentality of the Federal government from or regarding (a) Mr. Harry Chomiak, formerly Maintenance Foreman, Public Service Electric and Gas Co., (b) Mr. Howard W. Masquelier, formerly Electrical Engineer or Electrical Start-Up Engineer, Westinghouse Electric Corporation, and/or (c) Mr. Robert A. Stokes, formerly Manager of Projects Log-istics, Westinghouse Electric Corporation, concerning an alleged transmittal or delivery in 1974 or any time thereafter of Westinghouse NSD Technical Bulletin 74-1 [or 74-01) and/or Westinghouse NSD Data Letter 74-2 [or 74-02] by Mr. Howard Masqueller to Mr. Harry Chomiak, during the period from Feb-ruary 25, 1983 to the present time, including but not limited to information obtained during the NRC investigation into trip breaker f ailures at the Salem Nuclear Generating Station, Artificial Island, New Jersey, after the trip breaker failures which occurred on February 25, 1983. This request includes, but is not limited to, documents in any of the NRC's offices in the Washington, D.C. a rea , in its Region I offices at King of Prussia, Pennsylvania, and in its Resident Inspector's office at the Salem Nuclear Generating Station.
31 )
- T-G
( 7 Q,
+,p 8705050137 861113 (O PDR FOIA >
MIR ARCH (86-BOB PDR ,
Donnie H. Grimsley, Director November 13, 1986 Page 2 I
We would appreciate your prompt response to this request
$ 9.9. within the ten working day period provided in 10 C.F.R.
These documents we are requesting could prove to .lue significant ' to ongoing litigation and are needed promptly.
Accordingly, expeditiously aswepossible.
trust that this request will be fulfilled as.
Thank you.
Very truly yours, BISHOP, LIBERMAN & COOK By: ~ f/h ,[MId
' ~ Saverio Mirarchi
- ~
. . .