7-7/-- 9/%2-904 Ethan Allen Hwy ANEFCO !NC. IJL J/fome 0e877 203 4ai33s8 October 3, 1985 RETURN TO 396-SS gjt U.S. Nuclear Regulatory Commission Transportation Certification Branch Division of Fuel Cycle and Material Supply Washington, D.C.
20555 Attention: Charles E. MacDonald.
Mail Stop 396 SS
Subject:
Model AP-300 Type A Package Docket No. 71-9192 Gentlemen:
Attached are revisions to the SAR for our AP-300 shipping container which has been submitted to you with our application for a Certificate of Compliance. The revisions have beeg made to provide the additional information requested in your Jetter of Septembejr 24, 1985.
The responses are related to the dra.ings provided in the report and have beeAt marked as revision 8 in the text for easy identification.
In conformance with your request, we are submitting the appropriate revisions as part of a consolidated applicatio including. drawings.
We hope that these revisions clarify the design of-the cask and meet with your approval, so that we may be granted a Certificate of Compliance at your earliest convenience.
Very truly yours,
~~
s, Ly ANEFC0 IJ s
Of occMIED g n D. Murphy g.
resident OCT 6
-3 gt$hoM JDM/ja 9
pocgtctEM Encl.
\\,
I d, f I f f M
]
G Ls c. iv;DT o>
LLMtsp C2: IN L-100 59.
foal
- fr$xy $
2
- 29M, e
e REVISION 8 - 10/2/85 Remove Pages Insert Pages 1.2-4 7.3-1 1.2-4 7.3-1 7.1-2 8.1-1 7.1-2 8.1-1 7.1-5 8.2-1 7.1-5 8.2-1 Drawings:
Drawings:
133-1 133-1 134-1 134-1 135-1 134-la 136-1 135-1 138-1 136-1 138-1 143-1 138-la 144-1 143-1 145-1 144-1 145-1
7 Dockst # 71-9192 q
Page 1 Responses to Letter Dated 9/24/85 l
Drawing No. 133-1, Rev. 6 1.
The drawing should show the 1-inch thick x 24-inch square plate which is part of the lift / tie-down arrangement. The plate should be given a part number and listed in the Material List giving the number required and the material s,pecification.
The lift / tie-down pad has been renumbered as part no. 10a and.the pad m enting plate has been given part no. 10b and is listed in the parts list together with dimensions, material specifications and number required.
2.
The toroidal ring is not correctly shown in the half elevation of the cask. The picture should be corrected.
The drawing has been revised to show that toroidal ring obscures topof cask.
3.
The picture of the lift / tie-down lug does not agree with.the lug shown on-Drawing No. 138-1, Rev. 7 in that the lug appears to be thicker at one end chan the other. This discrepancy should be cc-rected.
~
The lift / tie-down lug is 4" thick for its entire length. The' detail-in Drawing No. 138-1 shows this fact more accurately.. Drawing No.
133-1 has been revised to show the correct attachment;of the lug to 5
the mounting plate and should show no discrepancy..
4.
Show that a shackle having a 2.75-inch screw pin, as called for on page 2.4-3, is dimensionally compatible with the. lift / tie-down. lug design
- considering the hole location relative to the 1-inch thick pad and the 1-inch fillet weld which joins the lug to the pad.
A nominal shackle size of 2 " will be used to lift the cask using a~2.75 inch pin., The outside diameter of.the shackle eye is Sh"...The 1 inch fillet veld willnot interfere with the shackle as shown on Drawing 138-la, a new dsawing, which is presented ~to show the shackle attachment..
-5.
The lid gasket dimensions (haterial List, Part No. 11) do not agree with the dimensions 'shown on Drawing No. 139-1.
Thelidgasket.dimensionshavebeenrevisedtoshowthefollow'ing, dimensions'-76.125" 1.D. x 80.875" 0.D. -x 1/8" thick. which agrees '
with the dimensions shown on Drawing;139-1.
5 s
.a
.al y.
~
l 1
Page 2
~l 6.
In the' Material List, Part No. L-4, delete the word " Ring" and the letter "H".
Also, delete the letters "S.S." part.No. B-3 and the letter "H" Part No. B-5.
The wor'd " Ring" and letter "H" have been-deleted from Part L-4,.the letters "S.S." have been deleted from Part B-3, and the letter "H" has been deleted from part B-5.
7.
In the Material List, Part No. B-9, the 82.4 inch dimension is not in agreement with the radius dimension given on page 2.6-15.
The ditmeter dimension of part no. B-9 has been revised to 82.375 inches to reflect the dimensions, given on page 2.6-15, accurately.
Drawing No. 134-1, Rev. 6 1.
The detail of the bottom corner should be identified.as Detail "A" as
. referenced by Drawing No.133-1.
This revision of Drawing No. 134-1 identifies this section as Detail "A".
2.
Part Nos. 41 and 34 should appear in_the Material List indicating the
~
number required and the material specification.
The parts identified as Nos. 41 and 34 Rev. 6 of this. drawing are-the same part which is actually part no. 43.-. This part is listed in the Parts list of Drawing No. 146-1 where it-is shown as a plug. 1.50"'
dia. x 1.25" 1 fabricated from A-516 Gr-70, three of which are required. This revision of the drawing identifies-this part correctly.
3.
Show where Part No. 34 is used.
As indicated above,part No. 34 shown in Rev.-6 of this drawing is in error.
4.
Clarify the' note.which states, "3 Req'd. - See Drwg. No.133-1".
As noted above in response to question 2, this error has..been deleted. The reference of " 3 Reg'd" refers to part no. 43.
5.
Consideration'should be given in the size of the fillet veld which joins Part No. B-9, square tube, to Part No. B-1, outer shell. The relatively large fillet weld against the thin wall tube could cause unacceptable distortion in the tube cross-section, y
-The fillet weld requirement has been reduced to 1/8" in consideration of the thin wall of the tube. ~
?'c
's
~
_e.-
p.
.e
' *L.;
p,.
s j
g.,--_ - -. -- -
L'
-Pzg2 3 6.~' Detail "B" must provide the dimensional information needed to support the condition stated on page 1.2-4, second paragraph, first sentence.
Drawing number 134-la, a new drawing is presented to show-lid and cask sections with clearanc'es, nominal.
Drawing No. 136-1, Rev. 3 1.
The drawing refers to a Detail "A" and the plan view of the closure lid indicates there is a Section A-A.
The drawing should cite the drawing numbers where these' details can be found.
Detail "A" and Section a-A of the lid closure are found in Drawing No. 135-1 and are so noted in this revision of Dwg.
136-1.
- 2. 'The eye bolt specifications on page 2.~4-6 should app' ear on the drawing.
It should be noted that a part number has not been assigned to this item and the number of eye bolts required has not been stated. Also, the locaticn of Detail "D" should be given.
The part number of the eye bolt 57 is listed in Dwg. No. 151-1 revision 1 which lists the dimensions as 1k" D x 3"1 and indicates that 4-ere required fabricated of drop forged steel.
The location of Detail "D" has been indicated on this-revision.
3.
It is noted that a Part No. 34 is called for..however, this item is different than the Part No. 34 shown on Drawing No. 134-1.
The part no. 34 shown in this drawing is correct. The descripcion of this part is found in the parts list shown in Drawing 146-1.
Drawing No. 138-1, Rev. 7 1.
The drawing should note the number of 24-inch x 24-inch pads' required and the material specification.
The number of-pads, although indicated in drawing title, has been-added. The material specification, A516 Gr 70, is noted in the parts list of Drawing 133-1.
2.
Correct the discrepancy between the descriptica of the lifting. pad eyes on page 1.2-4 and the drawing dimensions.'
The drawing dimensions are correct and the description on page
-1.2-4 has been revised.
~ _--- -
y:n Pe g2. 4.-
5 Drawing No.'143-1 Rev. 1
.It is'noted that Part No. 41 is'also' called for on Drawing No. 134-1, however the material thickness and the material. specifications of.the
~
plates _into which Part No. 41 is installed are different.
' Part No. 41: shown in-this drawing is correct. As shown in our comments. to. Drawing No. L134-1, the part.there was identifed in error.--Material specifications for this part are detailed in Drawing No.1 146-1.
~
Material Lists-Part< numbers and part' identifications need clarification. There are part numbers shown-_on the' drawings with no indication as to where they are used,-
how many are required, or the material. specification.
In some cases, the
~
same part number is used for different. items and there are items shown with no part number given.
1 There are three drawings which comprise the total materials list. They are drawing numbers 133-1, 146-1 and 151-1.
All parts shown.on the drawf.ngs are identified in these lists as to their dimensions, material ofjfabrication and numbers required.
l Operating Procedures 1.
Loading Procedure, Operation No. 10.
Does a 2-inch shackle' provide a-2.75 -inch minimum pin as called, for on page 2.4-3.
7 Operation-No.10 has been revised to show the use. of a' 2 "
nominal shackle.
2.
Loading Procedure, Operations Nos.139 and 40.- Prior to placing cask in
~
transport ring, the 2 "' square tube, Part No. B-9, Drawing No. 134-1, should be inspected. Establish minimum. acceptable tube. conditions and~
corrective action to be taken if' tube dondition does not. meet the acceptance; criteria.-
~
'/
Minimum tube conditions havelbeen established so that repairs must be' instituted or the tube replaced if the tube is cracked or deformed to a height of 2-1/8".-
3.
Under7.3.2, General ~Preparationsfor.Em,pty.PackageTransport.-
. Reference should' be made to;the requirements.of;49.CFRT 173.4271
" Empty Radioactive Materials Packaging".
p
-Stepf4 in Section 7.3.2 is. revised-to. read:
~ " The _ requirements of.49 CFR 173.427 " Empty' Radioactive
~
Materials Packaging" shall be complied 01th where applicable."
1 P
S
w-jf.
'il*
- c Pcgs 5
~ Acceptance Tests The pressure test and leak test procedures should cite a single specific test pressure.
The text has been revised so that the pressure test will be conducted at 10 psig-and the leak test at 7h psig.
Maintenance Program 1.. Under 8.2.1.1, Structural, inspection of the square tube, Part No. B-9, Drawing No. 134-1 should be listed as a required inspection.
See discussion under Operating Procedures, Item 2.
An annual inspection of structural condition of the square tube has been added to Section 8.2.1.1.
2.
The pressure test and leak test procedures should citc a single specific test pressure.
The pressure and leak tests have been specified and will be carried out at a pressure of 10 psig.
9 x
.