Forwards Bechtel-generated Artificial Time History for SSE Horizontal Component Used in Analysis of Main Steam Dump Sys,Per 861211 Meeting.Bechtel Review of SRP 3.7.1 Also Discussed.W/O Encls
ML20209J496
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/16/1986
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Degrassi G
BROOKHAVEN NATIONAL LABORATORY
References
VPNPD-86-510, NUDOCS 8702060329
Download: ML20209J496 (1)


Text

c Wisconsin Electnc eom couem 231 W. MICHIGAN,P.O BOX 2046. MILWAUKEE,W153201 (414)277-2345 VPNPD-86-510 December 16, 1986 Mr. Giuliano DeGrassi Department of Nuclear Energy BROOKHAVEN NATIONAL LABORATORY Building 129, 60 Cornell Street Upton, New York 11973

Dear Mr. DeGrassi:

SEISMIC TIME HISTORY DATA ENERGY ABSORBER APPLICATION POINT BEACH NUCLEAR PLANT As agreed to in our meeting on December 11, 1986, we are transmitting another Bechtel generated artificial time history for the SSE horizontal component to be used in the analysis of the main steam dump system for Point Beach Nuclear Plant.

Attached are an IBM PC compatible floppy diskette which contains the digitized data in ASCII format, and a hard copy and plot of the time history.

Additionally, Bechtel has reviewed Standard Review Plan 3.7.1 and determined that there are no specific power spectrum density requirements for a synthesized time history. Dr. Hou had requested that both BNL and Bechtel review this SRP to aid in determining that a 15 second duration time history was adequate for the analysis.

If you require further information, please notify us.

Very truly yours,

, /

, c:

l Ngf.

V ce Pre ident Md d Nuclear Power dgl  :

Enclosure Copy to Mr. George Lear, Project Director (w/o/e)

PWR Project Di. rectorate 1 702060329 B61216 C'PDRADOCK 05000266 p PDR

.