J. Barnie Beasley. Jr., P.E.

Southsrn Nuclear Vice President Operating Compa.1y, Inc.

Vogtle Project 40 invemess Center Parkway P0 Box 1295 -

Birmingham, Alabama 35201 Tel 205 992 7110

- Fax 205 992 0403 SOUTHERN COMPANY

' July 14, 1999 Energy to Serve nur trbrid" LCV-1306-F Docket Nos. 50-424 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Gentlemen:

VOGTLE ELECTRIC GENERATING PLANT MONTHLY OPERATING REPORT - JUNE 1999 i

Enclosed are the June 1999, monthly operating reports for Vogtle Electric Generating Plant (VEGP) Units 1 and 2. These reports are submitted in accordance with the Technical Specification 5.6.4.

Sincerely, i

r 4v

. B. Beas ey, JBB/JLL Enclosures El-VEGP Unit 1 Monthly Operating Report - June 1999 E2-VEGP Unit 2 Monthly Operating Report - June 1999 cc

Southern Nuclear Operating Company Mr. J. T. Gasser Mr. M. Sheibani SNC Document Management

)

j' hf) Q l l

.f U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. R. R. Assa, Project Manager, NRR Mr. J. Zeiler, Senior Resident Inspector, Vogtle 9907200137 990630 PDR ADOCK 05000424 R

PDR

- u r ij -

a

ENCLOSURE 1 VOGTLE ELECTRIC GENERATING PLANT - UNIT 1 MONTHL'Y OPERATING REPORT FOR JUNE 1999 TABLE OF CONTENTS

. OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES Page El-1 UNIT SHUTDOWNS and NARRATIVE REPORT ~

Page El-2 i

1 OPERATING DATA REPORT Docket No.:

50-424 Unit Name:

VEGP UNIT 1 i

Date:

July 1.1999 Completed By:

C.S. Myers, Jr.

Telephone:

(706) 826-3122 1

DDetallogjtatus l

1, Reporting Period:

June 1999

2. Design Electrical Rating (Net MWe):

1169

3. Maximum Dependable Capacity (Net MWe):

1151 1

Tbjg Month Year-To-Date farnpl.ajiyc

4. Number Of Hours Reactor Was Cntical:

720.0 3714.6 93,446.6 j

5. Hours Generator On Line; 720.G 3692.3 92.105.6 l
6. Unit Reserve Shutdown Hours:

0.0 0.0 0.0 I

7. Net Electrical Energy Generated (MWHe):

839,297 4,257,353 101,936.612 I

CHALLENGES TO PRESSURIZFR PORV AND PRESSUR:ZER SAFETY VALVES i

Date Tag No.

Event Desenption l

N/A N/A N/A l

l 1

ll 1

4 E11 1

d i

UNIT SHUTDOWNS Docket No.:

50-424 Unit Name:

VEGP UNIT 1 Date:

July 1,1999 Completed By:

C.S. Myers. Jr.

Telephone:

(706)826-3122 i

Reporting Period:

June 1999 l

Type Method of Cause/

F: Forced Duration Shutting Corrective Actions No.

Date S: Scheduled (Hours)

Reason (1)

Down (2)

Comments N/A N/A N/A N/A N/A N/A N/A i

(1) REASON:

(2) METHOD:

A Equipment Failure (Explain) E - Operator Training / License Examination

1. Manual
4. Continuation B - Maintenance or Test F - Administrative
2. Manual Trip / Scram
5. Other C - Refueling G - Operational Error (Explain)
3. Automatic Trip / Scram

{

D - Regulatory Restriction H - Other (Explain)

CAUSE/ CORRECTIVE ACTION / COMMENTS:

EVENT 99-X QAMSE; S

CORRECTIVE ACTION:

CRITICAL PATH WAS:

NARRATIVE REPORT June 01 00.00 At 100% power with no significant operating problems.

June 30 23:59 At 100% power with no significant operating problems.

E1-2 i

1 1

i l

ENCLOSURE 2 VOGTLE ELECTRIC GENERATING PLANT - UNIT 2 l

MONTHLY OPERATING REPORT FOR JUNE 1999 TABLE OF CONTENTS i

OPERATING DATA REPORT and CHALLENGES to PORV and SAFETY VALVES Page E2-1

. UNIT SIIUTDOWNS and NARRATIVE REPORT -

Page E -2 l..

i l

'i.

.i I

h B

OPERATING DATA REPORT Docket No.:

50-425 Unit Name:

VEGP UNIT 2 Date:

July 1.1999 Completed By:

C.S. Myers Jr.

Telephone:

(706)826-3122 QRegilngJta.lus 1, Reporting Period:

June 1999

2. Design Electrical Rating (Net MWe):

1169

3. Maximum Dependable Capacity (Net MWe):

1154 This Month Year-To-Dale Cumulative

4. Number Of Hours Reactor Was Critical:

720.0 4318.2 80.556.9

5. Hours Generator On Line:

712.5 4290.8 79.800.0

6. Unit Reserve Shutdown Hours:

00 0.0 0.0

7. Net Electrical Energy Generated (MWHe):

812.055 5.013,425 88.988.763 CHALLENGES TO PRESSURIZER PORV AND PRESSURIZER SAFETY VALVES Date Tag No.

Event Desenption N/A N/A N/A I

}

l I

E21

  • J UNIT SHUTDQWNS Docket No :

50-425 Unit Name:

VEGP UNIT 2 i

Date:

July 1,1999 Completed By:

C.S. Myers. Jr.

Telephone:

(706)826-3122

)

i Reporting Period:

June 1999 Type Method of Cause/

F: Forced Duration Shutting Corrective Actions No.

Date S: Scheduled (Hours)

Reason (1)

Down (2)

Comments 99-3 99-06-05 S

7.5 B

1 See below (1) REASON:

(2) METHOD:

A - Equipment Failure (Explain) E - Operator Training / License Examination

1. Manual
4. Continuation B - Maintenance or Test F - Administrative
2. Manual Trip / Scram
5. Other C - Refueling G Operational Error (Explain)
3. AutomaticTrip/ Scram D Regulatory Restriction H Other(Explain)

CAUSE/ CORRECTIVE ACTION / COMMENTS:

EVENT 99 3.

CAUSE Scheduled maintenance of the Unit's stator water cooling system.

{

QQRRECTIVE ACTION: Replaced stator water cooling system strainer.

CRITICAL PATH WAS Power reduction to 30% reactor power. Manually tripped turbine. Replaced stator water cooling system strainer. Tied turbine to grid and return to 100% power.

l NARRATIVE REPORT June 01 00:00 At 100% power with no significant operating problems.

June 04 23:00 Commenced planned power reduction to 30% to replace a clogged in-line stator cooling strainer.

June 05 10:28 Turbine manually tripped. Strainer replacement commenced.

June 0518:00 Generator synchronized to the grid.

June 05 21:09 Power increase commences.

June 07 07:01 Reactor power at 100%.

l June 30 23:59 At 100% power with no significant operating problems.

l 5