ML20209G180

From kanterella
Jump to navigation Jump to search
Informs That Schedule for Implementation of ATWS Rule (10CFR50.62) Unchanged,Per 870311 Request.Schedule Submitted on 850930 Reflects Commitment to Implement ATWS Rule During Cycle 9 Refueling Outage
ML20209G180
Person / Time
Site: Rancho Seco
Issue date: 04/24/1987
From: Julie Ward
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Miraglia F
Office of Nuclear Reactor Regulation
References
JEW-87-623, NUDOCS 8704300494
Download: ML20209G180 (1)


Text

esuun SACRAMENTO MUNICIPAL UTILITY DISTRICT D P. O. Box 15830, Sacramento CA 95852-1830,(916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA APR 2 41981 JEW 87-623 Director of Nuclear Reactor Regulation Attention:

Frank J. Miraglia, Jr.

Division of PWR Licensing-B U S Nuclear Regulatory Commission Washington D C 20555 Docket 50-312 Rancho Seco Nuclear Generating Station Unit #1 RANCHO SECO NUCLFAR GENERATING STATION SCHEDULE FOR IMPLEMENTATION OF THE ATWS RULE

Dear Mr. Miraglia:

NRC letter dated March 11, 1987 extends the deadline for implementation of the ATWS rule (10CFR50.62) to the third refueling outage after July 24, 1984. The letter also requested that the District update its implementation schedule based on this new guidance.

The District's implementation schedule has not changed.

In our September 30, 1985 submittal, the District committed to implement the ATWS rule during the Cycle 9 refueling outage which is the third refueling outage after July 24, 1984.

If you have any questions, please contact Robert Roehler of my staff.

Sincerely,

/C r ~. Ward Deputy General Manager, Nuclear cc: George Kalman, HRC - Bethesda A. D'Angelo, NRC - Rancho Seco Ohhg h